Architects Collaborative, Inc. v. PRES. & TRUST. OF BATES COLLEGE

576 F. Supp. 380, 1983 U.S. Dist. LEXIS 11048
CourtDistrict Court, D. Maine
DecidedDecember 7, 1983
DocketCiv. 83-0286 P
StatusPublished
Cited by3 cases

This text of 576 F. Supp. 380 (Architects Collaborative, Inc. v. PRES. & TRUST. OF BATES COLLEGE) is published on Counsel Stack Legal Research, covering District Court, D. Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Architects Collaborative, Inc. v. PRES. & TRUST. OF BATES COLLEGE, 576 F. Supp. 380, 1983 U.S. Dist. LEXIS 11048 (D. Me. 1983).

Opinion

MEMORANDUM & ORDER

GENE CARTER, District Judge.

This matter comes before the Court for a decision on the petition of the Architects Collaborative, Inc. (“Architect”) for an Order Compelling Arbitration, under 9 U.S.C. § 4, of certain disputes between the Architect and the President and Trustees of Bates College (“Owner”). Those issues arise in connection with performance of the Architect’s duties under an agreement dated November 25, 1977, entered into between the Owner and the Architect by which the Architect agreed to provide a design for a new physical education building to be built on the Owner’s premises at Lewiston, Maine. The services required of the Architect were provided in due course and the building was constructed. Subsequently, the Owner complained to the Architect that the roof and walls of the building leaked and on August 2, 1983, filed a suit in the Maine' Superior Court in and for *381 the County of Androscoggin, seeking damages from the Architect; the Salter Corporation, the general contractor on the building; Roof Systems, Inc., the roofing subcontractor; and Georgia-Pacific Corporation, the manufacturer of the roof coating material utilized.

The Complaint asserts in Count I a claim against the Architect based upon alleged negligence in the design of the roof and in the selection of materials to be utilized in the construction of the roof. In Count II the Owner asserts a claim against the Architect based upon alleged breach of the written contract between the Owner and the Architect.

In Counts II through VII the Owner asserts claims on various legal theories against the general contractor for damages resulting from alleged defects in the roof. Claims are asserted in Counts VIII through XI against the roofing subcontractor and in Counts XII and XIII, against the supplier of the roof coating material for the same damages.

On August 26, 1983, the Architect filed a demand for arbitration of the dispute between the Owner and the Architect raised by the state court lawsuit. That demand was made pursuant to Article 11.1 of the contract between the Owner and Architect which provides:

11.1 All claims, disputes and other matters in question between the parties to this Agreement, arising out of, or relating to this Agreement or the breach thereof, shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise.

The Owner has refused to submit the dispute to arbitration and here objects to the issuance of an order compelling such arbitration of the dispute on the grounds that (1) “[t]his Court lacks jurisdiction to entertain the instant petition seeking an order compelling arbitration that jurisdiction having been reserved exclusively to the State Courts of the Commonwealth of Massachusetts by agreement of the parties,” Respondent’s Brief at 2-3, and (2) “[e]ven if this Court has jurisdiction to compel arbitration, considerations of fundamental fairness and judicial economy requires [sic] denial of the petition.” Id. at 6.

After study of the pleadings herein, which include the Complaint of the Owner in the state action, and of the written submissions of the parties, and after having heard oral argument of counsel, the Court concludes that this Court has jurisdiction over the subject matter of this action by virtue of the diversity of citizenship between Petitioner and Respondent, as required by 28 U.S.C. § 1332, and by virtue of the United States Arbitration Act, 9 U.S.C. § 1, el seq., and that the contractual agreement at issue herein provided for arbitration of a controversy involving substantial commerce between the states, as contemplated by Title 9 of the United States Code.

The Court additionally finds:

(1) That Article 11 of the contract requires the parties to arbitrate all disputes arising out of the contract, including, without limitation, any dispute pertaining to the services provided by the Petitioner under the contract.

(2) The Respondent has commenced an action in the Superior Court in and for Androscoggin County, Maine, entitled “The President and Trustees of Bates College v. The Architects Collaborative, Inc., Salter Corporation, Roof Systems, Inc., and Georgia-Pacific Corporation,” in which damages of Five Hundred Thousand Dollars ($500,-000.00) are sought to be ■ recovered from • Petitioner on each of two counts, said claims arising out of the performance by Petitioner of services pursuant to its contract with the Respondent.

(3) On August 26, 1983, Petitioner filed a demand for arbitration with the American Arbitration Association. Respondent has refused to submit the dispute to arbitration.

(4) Petitioner is entitled, and herein seeks, to enforce Article 11 of the contract *382 against the Respondent. The Petitioner is ready, willing and able to proceed with arbitration in accordance with the contract.

II. DISCUSSION

The Respondents’ jurisdictional argument is based upon their construction of the Massachusetts Arbitration Act, Mass. Gen.Laws Ann., ch. 251, §§ 1-19. This argument begins with the correct assertions that the agreement between the Owner and Architect specifically provides in Article 11 that the agreement to arbitrate “shall be specifically enforceable under the prevailing arbitration law” and that the contractual choice of law provision set out in Article 13 of said contract provides that “this agreement shall be governed by the law of the principal place of business of the Architect”. It is undisputed that the Architect’s principal place of business is Cambridge, Massachusetts. Thus, Respondents say the rights of the parties to arbitration are strictly confined by the requirements of the Massachusetts Act. They rely particularly on §§ 2(a) and 16 of the Massachusetts Act which provide:

§ 2
(a) Refusal to arbitrate; application to superior court
A party aggrieved by the failure or refusal of another to proceed to arbitration under an agreement described in section one may apply to the superi- or court for an order directing the parties to proceed to arbitration. If the opposing party denies the existence of the agreement to arbitrate, the court shall proceed summarily to the determination of the issue so raised and shall, if it finds for the applicant, order arbitration; otherwise, the application shall be denied.
§ 16 Court; jurisdiction
The term “court” means any court of competent jurisdiction of this state. The making of an agreement described in section one providing for arbitration in this state confers jurisdiction on the court to enforce the agreement under this chapter and to enter judgment on an award thereunder.

(Emphasis added.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Higgins v. United States Postal Service
655 F. Supp. 739 (D. Maine, 1987)
United States v. Belanger
598 F. Supp. 598 (D. Maine, 1984)
Singh v. Superintending School Committee
593 F. Supp. 1315 (D. Maine, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
576 F. Supp. 380, 1983 U.S. Dist. LEXIS 11048, Counsel Stack Legal Research, https://law.counselstack.com/opinion/architects-collaborative-inc-v-pres-trust-of-bates-college-med-1983.