Blackwell, Justice.
After Mack Pitts was killed in a construction accident at Hartsfield-Jackson Atlanta International Airport, his estate and minor children sued the City of Atlanta and several contractors for breaches of contracts concerning the construction proj ect on which Pitts had been working.1 Although Pitts was not a party to these contracts, his estate and children asserted that he was an intended beneficiary and that they, therefore, had standing to sue for breach of the contracts. On cross-motions for summary judgment, the trial court found that Pitts was not an intended beneficiary, denied summary judgment to the estate and children, and awarded summary judgment to the City and contractors. In Estate of Pitts v. City of Atlanta, 312 Ga. App. 599 (719 SE2d 7) (2011), the Court of Appeals reversed, concluding that the trial court should have awarded summary judgment on the claims for [220]*220breach of contract to the estate and children, not to the City and contractors. The Court of Appeals determined that Pitts was, in fact, an intended beneficiary of the contracts, and it found that the evidence was undisputed that the City and contractors had breached the contracts. We granted certiorari, and we conclude that the Court of Appeals misapplied or failed to apply several fundamental principles of contract law in its consideration of these cases. Accordingly, we vacate the decision of the Court of Appeals, and we remand for reconsideration consistent with this opinion.
1. The record shows that a joint venture of Holder Construction Company, Manhattan Construction Company, C. D. Moody Construction Company, Inc., and Hunt Construction Group, Inc. (the “Holder-Manhattan” joint venture) contracted with the City to build an international terminal at the Airport. Holder-Manhattan subcontracted the construction work to a joint venture of Archer Western Contractors, Ltd. and Capital Contracting, Inc. (the “Archer Western-Capital” joint venture), and Archer Western-Capital subcontracted a portion of that work to A&G Trucking, Inc. In June 2007, a truck operated by A&G Trucking at the Airport struck and killed Pitts, who was employed by Archer Western Contractors to work on the construction of the international terminal. His estate and children sued A&G Trucking for wrongful death and eventually won a $5.47 million judgment, but A&G Trucking apparently could not pay the judgment.
From the inability of A&G Trucking to satisfy the judgment sprang this separate lawsuit, in which the estate and children allege that the City, Holder-Manhattan, and Archer Western-Capital owed contractual duties to ensure that A&G Trucking carried automobile liability insurance sufficient to satisfy claims up to $10 million.2 As the source of these contractual duties, the estate and children point to the contract between the City and Holder-Manhattan, as well as the subcontract between Holder-Manhattan and Archer Western-Capital. The estate and children contend that Pitts was an intended beneficiary of these contracts, that they, therefore, have standing to sue for breach of the contracts, and that the City, Holder-Manhattan, and Archer Western-Capital breached the contracts by allowing A&G Trucking to work on the construction of the international terminal without having automobile liability insurance with limits of no less than $10 million.
[221]*221From the beginning of the construction project, the City and Holder-Manhattan contemplated that Holder-Manhattan might subcontract some or all of the construction work to one or more subcontractors, and they contemplated that those subcontractors might, in turn, subcontract portions of the work to other subcontractors. To bind any subcontractors to the terms on which Holder-Manhattan had agreed to build the terminal, the City and Holder-Manhattan agreed in their contract that,
[b]y an appropriate written agreement, [Holder-Manhattan] shall require each Subcontractor, to the extent of the Work to be performed by the Subcontractor, to be bound to [Holder-Manhattan] by the terms of [the contract between the City and Holder-Manhattan], and to assume toward [Holder-Manhattan] all the obligations and responsibilities which [Holder-Manhattan] by [the contract between the City and Holder-Manhattan] assumes toward the [City]. . . . Where appropriate, [Holder-Manhattan] shall require each Subcontractor to enter into similar agreements with its Sub-Subcontractor.3
Consistent with this agreement, when Holder-Manhattan subcontracted the construction work to Archer Western-Capital, the subcontract incorporated the entirety of the contract between the City and Holder-Manhattan, and Archer Western-Capital agreed to be bound by the terms of that contract and to “assume [ ] toward [Holder-Manhattan] all of the duties and obligations that [Holder-Manhattan] has by [that contract] assumed toward [the City].” Archer Western-Capital also agreed to “likewise bind all of its lower tier sub-subcontractors and vendors to the obligations set forth in [its subcontract with Holder-Manhattan] and [the contract between Holder-Manhattan and the City].”
About insurance, the City and Holder-Manhattan agreed in their contract that the City would be responsible for procuring and maintaining policies to insure against certain risks and liabilities that might arise in the course of the construction project, that Holder-Manhattan and any subcontractors would be responsible for procuring and maintaining policies to insure against certain other risks and liabilities, and that, all together, these policies would provide “all [222]*222reasonably necessary insurance” for the project. To procure and maintain the policies for which the City was responsible, the City and Holder-Manhattan agreed to employ a preexisting program administered by the City and known as the “Owner’s Controlled Insurance Program” or “OCIP.”4 5They contemplated that Holder-Manhattan and any subcontractor, other than a mere supplier, would be named as an insured on the policies provided by the City, so long as they complied with the requirements for enrolling in OCIP.
In an addendum to their contract, the City and Holder-Manhattan set out the specific policies that were to be procured and maintained by the City, as well as those that were to be procured and maintained by Holder-Manhattan and any subcontractors. Though its content is not limited to the policies to be provided by the City through OCIP, the addendum itself is, somewhat confusingly, entitled “Owner’s Controlled Insurance Program” and is referenced in the contract as “OCIP.”5 The parties seem to agree that the OCIP addendum requires a subcontractor,6
at its own expense, [to] purchase and maintain . . . such insurance as will protect [the City, Holder-Manhattan, the subcontractor, and their employees, among others] from claims of the type set forth below:
1. Automobile, Bodily Injury and Property Damage Liability Insurance covering all automobiles, whether [223]*223owned, non-owned, leased or hired, with not less than the following limits:
a. Bodily Injury - $10,000,000 per person and occurrence ....
Free access — add to your briefcase to read the full text and ask questions with AI
Blackwell, Justice.
After Mack Pitts was killed in a construction accident at Hartsfield-Jackson Atlanta International Airport, his estate and minor children sued the City of Atlanta and several contractors for breaches of contracts concerning the construction proj ect on which Pitts had been working.1 Although Pitts was not a party to these contracts, his estate and children asserted that he was an intended beneficiary and that they, therefore, had standing to sue for breach of the contracts. On cross-motions for summary judgment, the trial court found that Pitts was not an intended beneficiary, denied summary judgment to the estate and children, and awarded summary judgment to the City and contractors. In Estate of Pitts v. City of Atlanta, 312 Ga. App. 599 (719 SE2d 7) (2011), the Court of Appeals reversed, concluding that the trial court should have awarded summary judgment on the claims for [220]*220breach of contract to the estate and children, not to the City and contractors. The Court of Appeals determined that Pitts was, in fact, an intended beneficiary of the contracts, and it found that the evidence was undisputed that the City and contractors had breached the contracts. We granted certiorari, and we conclude that the Court of Appeals misapplied or failed to apply several fundamental principles of contract law in its consideration of these cases. Accordingly, we vacate the decision of the Court of Appeals, and we remand for reconsideration consistent with this opinion.
1. The record shows that a joint venture of Holder Construction Company, Manhattan Construction Company, C. D. Moody Construction Company, Inc., and Hunt Construction Group, Inc. (the “Holder-Manhattan” joint venture) contracted with the City to build an international terminal at the Airport. Holder-Manhattan subcontracted the construction work to a joint venture of Archer Western Contractors, Ltd. and Capital Contracting, Inc. (the “Archer Western-Capital” joint venture), and Archer Western-Capital subcontracted a portion of that work to A&G Trucking, Inc. In June 2007, a truck operated by A&G Trucking at the Airport struck and killed Pitts, who was employed by Archer Western Contractors to work on the construction of the international terminal. His estate and children sued A&G Trucking for wrongful death and eventually won a $5.47 million judgment, but A&G Trucking apparently could not pay the judgment.
From the inability of A&G Trucking to satisfy the judgment sprang this separate lawsuit, in which the estate and children allege that the City, Holder-Manhattan, and Archer Western-Capital owed contractual duties to ensure that A&G Trucking carried automobile liability insurance sufficient to satisfy claims up to $10 million.2 As the source of these contractual duties, the estate and children point to the contract between the City and Holder-Manhattan, as well as the subcontract between Holder-Manhattan and Archer Western-Capital. The estate and children contend that Pitts was an intended beneficiary of these contracts, that they, therefore, have standing to sue for breach of the contracts, and that the City, Holder-Manhattan, and Archer Western-Capital breached the contracts by allowing A&G Trucking to work on the construction of the international terminal without having automobile liability insurance with limits of no less than $10 million.
[221]*221From the beginning of the construction project, the City and Holder-Manhattan contemplated that Holder-Manhattan might subcontract some or all of the construction work to one or more subcontractors, and they contemplated that those subcontractors might, in turn, subcontract portions of the work to other subcontractors. To bind any subcontractors to the terms on which Holder-Manhattan had agreed to build the terminal, the City and Holder-Manhattan agreed in their contract that,
[b]y an appropriate written agreement, [Holder-Manhattan] shall require each Subcontractor, to the extent of the Work to be performed by the Subcontractor, to be bound to [Holder-Manhattan] by the terms of [the contract between the City and Holder-Manhattan], and to assume toward [Holder-Manhattan] all the obligations and responsibilities which [Holder-Manhattan] by [the contract between the City and Holder-Manhattan] assumes toward the [City]. . . . Where appropriate, [Holder-Manhattan] shall require each Subcontractor to enter into similar agreements with its Sub-Subcontractor.3
Consistent with this agreement, when Holder-Manhattan subcontracted the construction work to Archer Western-Capital, the subcontract incorporated the entirety of the contract between the City and Holder-Manhattan, and Archer Western-Capital agreed to be bound by the terms of that contract and to “assume [ ] toward [Holder-Manhattan] all of the duties and obligations that [Holder-Manhattan] has by [that contract] assumed toward [the City].” Archer Western-Capital also agreed to “likewise bind all of its lower tier sub-subcontractors and vendors to the obligations set forth in [its subcontract with Holder-Manhattan] and [the contract between Holder-Manhattan and the City].”
About insurance, the City and Holder-Manhattan agreed in their contract that the City would be responsible for procuring and maintaining policies to insure against certain risks and liabilities that might arise in the course of the construction project, that Holder-Manhattan and any subcontractors would be responsible for procuring and maintaining policies to insure against certain other risks and liabilities, and that, all together, these policies would provide “all [222]*222reasonably necessary insurance” for the project. To procure and maintain the policies for which the City was responsible, the City and Holder-Manhattan agreed to employ a preexisting program administered by the City and known as the “Owner’s Controlled Insurance Program” or “OCIP.”4 5They contemplated that Holder-Manhattan and any subcontractor, other than a mere supplier, would be named as an insured on the policies provided by the City, so long as they complied with the requirements for enrolling in OCIP.
In an addendum to their contract, the City and Holder-Manhattan set out the specific policies that were to be procured and maintained by the City, as well as those that were to be procured and maintained by Holder-Manhattan and any subcontractors. Though its content is not limited to the policies to be provided by the City through OCIP, the addendum itself is, somewhat confusingly, entitled “Owner’s Controlled Insurance Program” and is referenced in the contract as “OCIP.”5 The parties seem to agree that the OCIP addendum requires a subcontractor,6
at its own expense, [to] purchase and maintain . . . such insurance as will protect [the City, Holder-Manhattan, the subcontractor, and their employees, among others] from claims of the type set forth below:
1. Automobile, Bodily Injury and Property Damage Liability Insurance covering all automobiles, whether [223]*223owned, non-owned, leased or hired, with not less than the following limits:
a. Bodily Injury - $10,000,000 per person and occurrence ....
By its contract with the City, Holder-Manhattan agreed to “require each of its Subcontractors to procure and maintain during the life of any Subcontract, insurance of the type specified in [the OCIP addendum], except as otherwise agreed to by the [City].” In a somewhat redundant provision, Holder-Manhattan also agreed to
require each of its Subcontractors to procure and maintain, until the completion of the Subcontractor’s work, insurance of the types and to the limits specified in [the OCIP addendum], unless such insurance requirements for the Subcontractor is expressly waived in writing by the [City] which waiver shall not be unreasonably withheld.
Holder-Manhattan promised in the contract that it would not commence work on the international terminal until it had both “fulfilled all its requirements under the OCIP” and “obtained all of the [insurance specified in the OCIP addendum for which it was responsible],” and it promised that it would not permit any subcontractor to commence work until the subcontractor had done these things. •
2. The Court of Appeals concluded that Pitts was an intended beneficiary of the contracts among the City, Holder-Manhattan, and Archer Western-Capital,7 and as a basis for its conclusion, the court pointed to a statement of purpose contained in the OCIP addendum. According to that statement, “[t]he purpose of the OCIP is to provide one master insurance program that provides broad coverages with high limits that will benefit all participants involved in the project.”8 Relying upon the dictionary definition of “participant,” and noting that the contracts and OCIP addendum do not define “participant” [224]*224otherwise, the court reasoned that Pitts was a “participant” because he had a part in the construction project. Therefore, the Court of Appeals concluded, Pitts was an intended beneficiary of the contract between the City and Holder-Manhattan, as well as the subcontract between Holder-Manhattan and Archer Western-Capital into which the contract with the City was incorporated by reference.9 Estate of Pitts, 312 Ga. App. at 603-604 (1) (a) (i). Upon our review, it appears that the analysis of the Court of Appeals was incomplete in two respects.
First, in determining the meaning of the term “all participants,” the Court of Appeals appears to have failed to fully consider the context in which the term appears in the OCIP addendum. The Court of Appeals began its analysis by looking to a dictionary for the accepted definition of “participant,” and that was a good place to start, inasmuch as we generally accept that contractual terms carry their ordinary meanings, OCGA § 13-2-2 (2), and a dictionary is a useful tool for narrowing the range of meanings ordinarily attributed to a word. But a dictionary does not always provide a complete answer. In this case, the dictionary tells us that a “participant” is “one that participates,” and “to participate” means “to have a part or share in something.” See Webster’s New Collegiate Dictionary, p. 829 (1981). A dictionary does not, however, identify the “something” in which a “participant” has a part or shares. By necessity, that must be taken from the context in which “participant” is used. More important, the context in which a contractual term appears always must be considered in determining the meaning of the term. “[Contracts must be construed as a whole,” State Auto Prop. & Cas. Co. v. Matty, 286 Ga. 611, 616-617 (1) (690 SE2d 614) (2010), and “the whole contract should be looked to in arriving at the construction of any part.” OCGA § 13-2-2 (4). See also Murphy v. Ticor Title Ins. Co., 316 Ga. App. 97, 100 (1) (729 SE2d 21) (2012); Triple Eagle Assoc., Inc. v. PBK, Inc., 307 Ga. App. 17, 24 (2) (c) (704 SE2d 189) (2010); Service Merchandise Co. v. Hunter Fan Co., 274 Ga. App. 290, 295 (1) (617 SE2d 235) (2005).
[225]*225Once it ascertained the dictionary definition of “participant,” the Court of Appeals determined that the reference in the OCIP addendum to “all participants” unambiguously meant all persons having a part in the construction of the international terminal. That is not an entirely unreasonable understanding of the term, although it does render the phrase that follows “participants” — “involved in the project” — somewhat redundant. See Floyd v. Floyd, 291 Ga. 605, 610 (2), n. 8 (732 SE2d 258) (2012) (“[Wjhenever possible, a contract should not be construed in a manner that renders any portion of it meaningless”) (citation and punctuation omitted). But it is not the only reasonable understanding of that term. Recall that “OCIP” was used by the City and Holder-Manhattan in their contract in two different senses. “OCIP” refers in some places to the entirety of the insurance requirements set out in the OCIP addendum.10 But in other places, it refers more specifically to the preexisting program by which the City itself procures and maintains the insurance for which it is responsible on construction projects in which it is involved.* 11 Participation in that preexisting program is not open to all who have a part in the project, but is limited to contractors and subcontractors, other than mere suppliers, that fulfill the requirements to enroll in OCIP. If “OCIP,” as used in the statement of purpose on which the Court of Appeals relied, refers to the preexisting program, rather than the entirety of the requirements set out in the OCIP addendum, [226]*226it would, suggest that “participants” perhaps refers to those who participate in the OCIP program, not all those who participate in the terminal construction project.12 And no one contends that Pitts was enrolled in the OCIP program. Because it failed to consider the full context in which the reference to “all participants” appeared, the Court of Appeals went astray in its analysis.
Second, even if “all participants” unambiguously includes Pitts, the Court of Appeals also appears to have drawn its conclusion about the extent to which he was an intended beneficiary of the contracts too broadly. It is settled under Georgia law that one not a party to a contract, but who is an intended beneficiary of the contract, may sue “the promisor” for its breach. OCGA § 9-2-20 (b). But in the contracts at issue here, each party to those contracts — the City, Holder-Manhattan, and Archer Western-Capital — was a promisor with respect to some contractual promises and was a promisee with respect to others. And it is perfectly clear that, even if Pitts is an intended beneficiary of the “OCIP,” he is not an intended beneficiary of every promise contained in the contracts. To determine the extent to which the estate and children properly may sue any one of the parties to these contracts as a “promisor,” it is essential to identify the specific contractual promises, if any, of which Pitts was an intended beneficiary, and his rights as an intended beneficiary attach only to those promises. See Starrett v. Commercial Bank of Ga., 226 Ga. App. 598, 601 (1) (486 SE2d 923) (1997) (“Notwithstanding the ultimate purpose of the agreement, individual contract provisions may be intended to benefit a stranger to the contract, thus creating a third-party beneficiary.”); accord Gardner & White Consulting Svcs., Inc., 222 Ga. App. 464, 466 (474 SE2d 663) (1996) (“The remedies available to the beneficiary are exactly the same as would be available to him if he were a contractual promisee of the performance in question.”) (citation and punctuation omitted; emphasis supplied); Walls, Inc. v. Atlantic Realty Co., 186 Ga. App. 389 (367 SE2d278) (1988) (“[Although the subcontract does contain a provision whereby Walls agreed to indemnify Atlantic, Atlantic would be entitled to enforce that provision against Walls if, but only if, Atlantic is a third-party beneficiary thereof.”) (emphasis supplied).
Consistent with Georgia law, courts in other jurisdictions have observed that “[sjtatus as a third-party beneficiary does not imply standing to enforce every promise within a contract, including those [227]*227not made for that party’s benefit.” BNP Paribas Mtg. Corp. v. Bank of America, 778 FSupp.2d 375, 415 (VI) (S.D.N.Y. 2011) (citation omitted). See also Civix Sunrise, GC, LLC v. Sunrise Road Maintenance Assn., 997 So2d 433, 435 (Fla. App. 2008) (“Contrary to the appellees’ contention, their status as third-party beneficiaries under paragraphs 3,13, and 14 does not automatically entitle them to claim fees under paragraph 20.”). To the contrary, “a third party beneficiary... can only enforce those promises made directly for his benefit.” Clark v. California Ins. Guar. Assn., 200 Cal. App.4th 391, 398 (3) (Cal. App. 2011). As the California Supreme Court has explained:
A third party should not be permitted to enforce covenants made not for his benefit, but rather for others. He is not a contracting party; his right to performance is predicated on the contracting parties’ intent to benefit him. As to any provision made not for his benefit but for the benefit of the contracting parties or for other third parties, he becomes an intermeddler. Permitting a third party to enforce a covenant made solely to benefit others would lead to the anomaly of granting him a bonus after his receiving all intended benefit.
Murphy v. Allstate Ins. Co., 553 P2d 584, 588 (Cal. 1976) (citations omitted).13
The Court of Appeals appears to have assumed that, if Pitts was an intended beneficiary as a “participant” in the construction project, he was an intended beneficiary for all purposes of every provision of the OCIP addendum, as well as other provisions of the contracts that have some relation to the provisions of the OCIP addendum. See Estate of Pitts, 312 Ga. App. at 604-605 (1) (a) (i). But the statement of purpose from which the court ascertained that Pitts was a beneficiary does not say explicitly that the entire OCIP addendum, much less the entire contract, was made for his benefit. Rather, that statement provides that “[t]he purpose of the OCIP is to provide one master insurance program that provides broad coverages with high [228]*228limits that will benefit all participants involved in the project.” The question, again, is in what sense does the statement of purpose use the terms “OCIP” and “master insurance program.” If “OCIP” and “master insurance program” refer only to the insurance to be provided by the City through OCIP, then Pitts would not necessarily be an intended beneficiary of the provisions that his estate and children seek to enforce about automobile liability insurance to be provided by a subcontractor at its own expense. And even if “OCIP” and “master insurance program” refer more generally to the entire OCIP addendum, Pitts might or might not be an intended beneficiary of provisions in the contracts not specifically related to the OCIP addendum, such as the general provision that Holder-Manhattan bind subcontractors to the terms of its contract with the City. Moreover, Pitts might or might not be an intended beneficiary for all purposes of contractual provisions contained in the OCIP addendum to the extent that those provisions explicitly state that they are to protect “participants” for certain specified purposes.14 As noted earlier, the Court of Appeals failed to identify the specific contractual provisions of which Pitts was an intended beneficiary and the scope of his rights as an intended beneficiary under those specific provisions, and in so doing, it neglected the settled principle that a third party is entitled to enforce only those specific provisions of a contract of which he is an intended beneficiary.15
3. The Court of Appeals also appears to have erred in reaching its conclusion that the City breached its contract with Holder-Manhattan by failing to ensure that A&G Trucking carried automobile liability insurance up to $10 million. First, the court appears to have failed to separately consider the contractual obligations of each of the contracting parties. See Estate of Pitts, 312 Ga. App. at 604-605 (1) (a) (i). Instead, it seems that the court conflated the City, Holder-Manhattan, and Archer Western-Capital, notwithstanding that the [229]*229City and Archer Western-Capital were not even parties to the same contracts, and notwithstanding that a promise made by one contracting party is not necessarily attributable to another. For instance, the Court of Appeals determined that the contract between the City and Holder-Manhattan “set forth the responsibilities of the City and [Holder-Manhattan] regarding establishing and maintaining the [OCIP],” and it found that “[t]hese responsibilities included the duty to ensure that subcontractors of any tier complied with the minimum insurance requirements of the [OCIP addendum] before working on the construction project.”16 Id. But upon our review of that contract and the OCIP addendum, we find no promise by the City to ensure that subcontractors carried adequate insurance. To the contrary, the contract requires the submission of certificates of insurance to the City, but it expressly provides that “[t]he acceptance by the [City] of any Certificate of Insurance does not constitute approval or agreement by the [City] that the insurance requirements have been satisfied.” Only a promisor is liable for breach of contract, see OCGA § 9-2-20 (b), and although the City has argued throughout this case that it is not a promisor with respect to the contractual promises that the estate and children contend were broken, the Court of Appeals failed to fully address that argument.
The City did promise in its contract with Holder-Manhattan to “maintain the required and necessary OCIP policies” and to “procure, pay for and administer the OCIP.” The Court of Appeals mentioned these promises in its opinion, but the significance that it attributed to them is unclear. Estate of Pitts, 312 Ga. App. at 607 (1) (b). To the extent that the Court of Appeals concluded that the City failed to fulfill these obligations with respect to automobile liability insurance for A&G Trucking, it erred. These obligations plainly refer to the insurance for which the City was responsible and was to bear the [230]*230expense under the OCIP addendum, but procuring and maintaining automobile liability insurance clearly was the responsibility instead of Holder-Manhattan and any subcontractors.
4. For these reasons, the decision of the Court of Appeals cannot be affirmed.17 As we have explained, there are important questions in these cases that the Court of Appeals never asked or fully answered. We also note that certain other arguments raised by the parties in the Court of Appeals may bear upon those questions, but also never have been addressed — for instance, the estate and children argue that certain parol evidence properly may be considered in construing the relevant contracts, and they contend that one or more of the defendants has made admissions in judicio that work an estoppel with respect to some of the questions presented in these cases. Because the analysis of the Court of Appeals is incomplete in several respects — and because parol evidence and alleged admissions in judicio that the Court of Appeals never addressed at all may bear upon that analysis — we will not undertake to supply an answer to all the unanswered questions that remain. We express no opinion about whether any party is entitled to summary judgment on this record. Instead, we leave it to the Court of Appeals to supply the answers to the unanswered questions, applying the settled principles of contract law set out in our opinion.18 The judgment of the Court of Appeals is vacated, and these cases are remanded for further proceedings consistent with this opinion.
Judgment vacated and cases remanded with direction.
All the Justices concur, except Hunstein, C. J., Thompson, P. J., and Hines, J., who dissent.