Application of Interstate Power Co.

500 N.W.2d 501, 145 P.U.R.4th 112, 1993 Minn. App. LEXIS 590
CourtCourt of Appeals of Minnesota
DecidedJune 1, 1993
DocketC3-92-2234
StatusPublished
Cited by2 cases

This text of 500 N.W.2d 501 (Application of Interstate Power Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Application of Interstate Power Co., 500 N.W.2d 501, 145 P.U.R.4th 112, 1993 Minn. App. LEXIS 590 (Mich. Ct. App. 1993).

Opinion

OPINION

ANDERSON, Chief Judge.

Relator Interstate Power Company (Interstate) petitioned the Minnesota Public Utilities Commission (MPUC) to increase electric service rates for its Minnesota customers. The MPUC issued findings of fact, conclusions of law, and an order disallowing as a claimed expense Interstate’s demand charge cost of 100 megawatts of power the MPUC determined was excess capacity. Interstate petitioned for reconsideration, and after reconsideration, the MPUC issued an order reaffirming its original decision on the excess capacity issue. Interstate obtained a writ of certiorari, seeking review of the MPUC’s original decision and order after reconsideration. We affirm.

FACTS

Interstate is an investor-owned electric and gas utility serving portions of Iowa, Illinois, and Minnesota. Interstate’s service to Minnesota customers is regulated by the MPUC.

In August 1991, Interstate entered into long-term contracts with United Power Association (UPA), Iowa Public Service (IPS), and Minnesota Power (MP) for the purchase of electric power. All three contracts included demand charges 1 and are effective May 1, 1992 through April 30, 2001. Interstate allocated Minnesota’s portion of the demand charges for those contracts as follows:

Seller Date of Contract Demand Charge Amount of Power

UPA August 7, 1991 $1,833,394.00 100 MW (megawatts)

IPS August 12, 1991 $1,958,117.00 100 MW

MP August 14, 1991 $ 227,155.00 30 MW

$4,018,666.00

*503 In the same month it signed the contracts, Interstate filed a petition with the MPUC to increase electric service rates for its Minnesota customers. Interstate requested the $4,018,666 in demand charge costs be included as a test-year operating expense in its rate case. 2 Interstate claimed the demand charge costs of the three contracts would offset costs that would otherwise be necessary to generate more expensive power at Interstate’s Lansing, Michigan plant (Lansing plant).

In January 1992, an administrative law judge (AU) conducted a hearing on Interstate’s petition. Following the hearing, the AU found that, as a result of the three contracts, Interstate would have 100 megawatts of annual excess capacity. The AU concluded that the IPS contract was unnecessary. Accordingly, the AU recommended that Interstate’s test-year expenses be reduced by $1,958,117 — the demand charge for the 100 megawatts of capacity purchased from IPS.

On June 12, 1992, the MPUC reviewed the AU’s recommendations and issued its own findings of fact, conclusions of law, and order. The MPUC agreed with the AU that Interstate’s three contracts would result in 100 megawatts of annual excess capacity. The MPUC also found that Interstate had entered into the three contracts based upon an invalid demand forecast, and that Interstate’s reliance on the forecast had been imprudent.

The MPUC did not specifically adopt the AU’s recommendation that the 100 megawatts of excess capacity should be attributed to the IPS contract. Instead, the MPUC concluded:

A convenient and appropriate proxy to indicate the cost of this amount of electricity is the price [Interstate] has contracted to pay IPS for 100 MW [megawatts] per year. The IPS contract amount for 100 MW [megawatts] per year, $1,958,117, will be excluded from the test year cost of service.

(Emphasis added.)

Interstate petitioned the MPUC for reconsideration of its June 12, 1992 order. On October 19, 1992, the MPUC issued an order reaffirming its decision to exclude the cost of the IPS contract, using it as a proxy for the demand charge cost of 100 megawatts of excess power.

ISSUES

I. Did the MPUC err by assigning the demand charge cost of the IPS contract as a proxy for the 100 megawatts of excess capacity?

II. Did the MPUC err by failing to offset the demand charge cost of the IPS contract by alleged savings that would result from the IPS contract?

III. Did the MPUC err by excluding the demand charge cost of 100 megawatts of excess capacity as an expense, rather than making adjustments for that excess capacity through the statutory fuel adjustment clause?

ANALYSIS

A public utility seeking a change in rates has the burden of proving the rate change is just and reasonable. Minn.Stat. § 216B.16, subd. 4 (1990). When reviewing a public utility’s request for a change in rates, the MPUC must allow the utility and its investors a reasonable profit, while at the same time ensuring that ratepayers are furnished utility service at reasonable rates. In re Petition of Northern States Power Co., 416 N.W.2d 719, 722 (Minn.1987) (Petition of NSP); Northern States Power Co. v. Minnesota Pub. Utils. Comm’n, 344 N.W.2d 374, 378 (Minn.1984). “Any doubt as to reasonableness should be resolved in favor of the consumer.” Minn. Stat. § 216B.03 (1990).

When determining whether ratepayers or investors should bear the expense of a claimed cost, the MPUC acts in *504 both a quasi-judicial and a legislative capacity. Petition of NSP, 416 N.W.2d at 722. When the MPUC acts in a quasi-judicial capacity, a reviewing court will apply the substantial evidence standard of review. Id. at 723. In other words, the court will determine whether the MPUC has adequately explained how it derived its conclusion and whether that conclusion is reasonable on the basis of the record. Id. at 724. When the MPUC acts in a legislative capacity, its decision will be upheld on appeal if it acted within its statutory authority, and the result was not “unjust, unreasonable, or discriminatory, as shown by clear and convincing evidence.” Id. at 723.

I.

Interstate has conceded for purposes of this appeal that its 1990 and 1991 forecasts were inaccurate, and does not challenge the MPUC’s finding that it imprudently purchased 100 megawatts of excess capacity in reliance on those forecasts. Interstate argues, however, that the MPUC erred by assigning the demand charge cost of the IPS contract as a proxy for the 100 megawatts of excess capacity.

Although the MPUC has the duty to establish reasonable rates, it must do so based upon the evidence submitted by the parties. See In re Petition of Continental Tel. Co., 389 N.W.2d 910, 914-15 (Minn.1986). A petitioning utility has the burden of proving to the MPUC that its proposed assets and revenue requirements are accurate, just, and reasonable; if the petitioner’s evidence is inaccurate, the utility has failed to meet its burden of proof, and the MPUC will either deny the rate increase or make “appropriate adjustment” to the utility’s proposal. Id. at 916.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re the Excess Surplus Status of Blue Cross & Blue Shield of Minnesota
606 N.W.2d 697 (Court of Appeals of Minnesota, 2000)
In Re the Quantification of Environmental Costs
578 N.W.2d 794 (Court of Appeals of Minnesota, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
500 N.W.2d 501, 145 P.U.R.4th 112, 1993 Minn. App. LEXIS 590, Counsel Stack Legal Research, https://law.counselstack.com/opinion/application-of-interstate-power-co-minnctapp-1993.