Appalachian Power Co. v. United States

607 F.2d 935, 221 Ct. Cl. 398, 1979 U.S. Ct. Cl. LEXIS 279
CourtUnited States Court of Claims
DecidedOctober 17, 1979
DocketNo. 62-78
StatusPublished
Cited by4 cases

This text of 607 F.2d 935 (Appalachian Power Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Appalachian Power Co. v. United States, 607 F.2d 935, 221 Ct. Cl. 398, 1979 U.S. Ct. Cl. LEXIS 279 (cc 1979).

Opinion

KASHIWA, Judge,

delivered the opinion of the court:

This case is the last phase of a protracted, but unsuccessful, effort by plaintiff, Appalachian Power Company (Appalachian),1 to build and operate the Blue Ridge [401]*401Pumped Storage and Hydroelectric Project (Blue Ridge Project) on the New River above Galax, Virginia. The project was initiated by preliminary plans in 1962 and a formal application in 1965. Like similar hydroelectric projects initiated on or about the same period of this project, plaintiff ran into difficulties.2 Since the Congressional enactment of Pub. L. No. 94-407 (approved September 11, 1976), amending the Wild and Scenic Rivers Act of 1968, 16 U.S.C. § 1271 et seq., it is clear the proposed Blue Ridge Project will not be built. The question remaining for our decision is whether the enactment of Pub. L. No. 94-407 constituted, as plaintiff alleges, a taking of plaintiffs hereinafter described Federal Power Commission (FPC) license granting the plaintiff the right to build and operate the Blue Ridge Project. This question was recognized by Congress but left to the decision of this court.3

This taking issue is before the court on plaintiffs motion for partial judgment on the pleadings under Rule 38(c) of this court. The parties to the case agree that the question of whether defendant is liable is ripe for decision. Every fact necessary for the court’s decision on the issue has been established by the pleadings, which makes Rule 38(c) the appropriate procedural vehicle. After carefully considering the parties’ briefs and oral arguments, we hold in favor of defendant. There was no compensable taking.

Appalachian is a public utility company engaged in the business of providing electric power to customers in the [402]*402States of Virginia and West Virginia. Its principal place of business is in Roanoke, Virginia. Appalachian commenced its effort to build the Blue Ridge Project on June 20, 1962, when it applied to the FPC for a preliminary permit under 16 U.S.C. § 798 (1976) to maintain priority of application for a license to construct the project. The FPC issued the preliminary permit on March 11, 1963.

Following the completion of feasibility studies, Appalachian filed on February 27, 1965, an application for a license to construct the Blue Ridge Project. The purposes of the project were to provide additional on-peak electric generating capacity to meet future projected needs of customers of the American Electric Power System and to improve the reliability of the American Electric Power System. Hearings on the proposed project and license application commenced in May 1967 and continued for two years.

On October 1, 1969, the administrative law judge issued his initial decision on the proposed project concluding that: "[t]he modified Blue Ridge Project represents the maximum utilization of the applicable reach of the New River sub-basin above Galax, Virginia with optimum project benefits * * *. No alternative site or source would provide the needed power more economically.” Appalachian Power Co., Project No. 2317, 51 F.P.C. 1906, 1966-1967 (1974). Accordingly, the initial decision recommended that a license be granted to Appalachian for the project.

Following the initial decision recommending that the project be licensed, additional hearings and administrative-proceedings were conducted; and the administrative law judge issued two more opinions reaffirming the recommendation to issue an FPC license to Appalachian. The FPC twice heard oral arguments on the case and the commissioners personally examined the proposed Blue Ridge Project site. All parties requesting to do so were permitted to intervene despite deficiencies inherent in some petitions and that they were filed several years after the original license application. Also, the FPC staff prepared and circulated a final Environmental Impact Statement on the proposed project on June 17, 1973. Parties were given the opportunity to cross-examine FPC staff witnesses with respect to the Environmental Impact Statement at further hearings in July 1973. Furthermore, parties were allowed [403]*403to file additional direct evidence with the FPC as late as July 13, 1973. No such evidence was filed by any party.

On July 14, 1974, the FPC, in a unanimous decision, issued the license to Appalachian; but the license expressly provided that it would not become effective until January 2, 1975.4 Appalachian formally accepted the license by action of its Board of Directors on June 20, 1974. North Carolina then sought judicial review of the FPC’s action in the United States Court of Appeals for the District of Columbia, alleging procedural defects in the FPC’s decision-making process.

The Blue Ridge license became effective on January 2, 1975, in accordance with its terms subject however, as shown hereafter, to review by the respective United States Courts of Appeals and the Supreme Court as expressly spelled out in 16 U.S.C. §825l (1958), a specific Federal Power Act provision. Prior to the effective date of the license, North Carolina sought a stay of the FPC’s licensing order from the Court of Appeals. On January 31, 1975, the court granted the stay, 29 days after the license became effective. On March 24,1976, in North Carolina v. FPC, 533 F. 2d 702 (D.C. Cir. 1976), the Court of Appeals vacated the stay it had issued pending the appeal and upheld the FPC’s order granting the license.5 Two days later the FPC declared that the license "is in effect.” North Carolina then sought a writ of certiorari from the United States Supreme Court. 45 U.S.L.W. 3017 (1976).

Before the Supreme Court considered North Carolina’s petition for certiorari, Congress passed, and on September 11, 1976, the President signed, Pub. L. No. 94-407, 90 Stat. [404]*4041238, amending the Wild and Scenic Rivers Act of 1968, 16 U.S.C. § 1271 et seq. Section 1 of the Act added to the national wild and scenic rivers system "that segment of the New River in North Carolina extending from its confluence with Dog Creek downstream approximately 26.5 miles to the Virginia State Line.” The Blue Ridge Project affected this segment. Section 2, set out in the margin,6 rendered any FPC license ineffective for that portion of the river and provided that "no project or undertaking so licensed shall be permitted to invade, inundate or otherwise adversely affect such river segment.”

Following the enactment of Pub. L. No. 94-407 the Supreme Court, following a procedure urged by the Solicitor General’s office, granted North Carolina’s petition for certiorari, vacated the judgment below, and remanded the case to the Court of Appeals for further consideration in light of Pub. L. No. 94-407. 429 U.S. 891 (1976). The Court of Appeals upon reconsideration concluded that North Carolina’s challenge was moot and dismissed the petition for review.

Plaintiff filed its petition in this court on February 14, 1978.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
607 F.2d 935, 221 Ct. Cl. 398, 1979 U.S. Ct. Cl. LEXIS 279, Counsel Stack Legal Research, https://law.counselstack.com/opinion/appalachian-power-co-v-united-states-cc-1979.