Anthony P. Miller, Inc. v. The United States

422 F.2d 1344, 191 Ct. Cl. 292, 1970 U.S. Ct. Cl. LEXIS 28
CourtUnited States Court of Claims
DecidedMarch 20, 1970
Docket464-61
StatusPublished
Cited by3 cases

This text of 422 F.2d 1344 (Anthony P. Miller, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anthony P. Miller, Inc. v. The United States, 422 F.2d 1344, 191 Ct. Cl. 292, 1970 U.S. Ct. Cl. LEXIS 28 (cc 1970).

Opinion

ON PLAINTIFF’S MOTION AND DEFENDANT’S CROSS-MOTION FOR SUMMARY JUDGMENT

PER CURIAM:

This case was referred to Trial Commissioner Roald A. Hogenson with directions to prepare and file his opinion on the issues of plaintiff’s motion and defendant’s cross-motion for summary judgment under the order of reference and Rule 166(c). The commissioner has done so in an opinion and report filed on October 7, 1969, wherein such facts as are necessary to the opinion are set forth. Requests for review were filed by both parties and the case has been submitted to the court on oral argument of counsel and the briefs of the parties.

With respect to Count II, the court emphasizes that its decision is based on the particular evidence in the particular record, and that it is not laying down a rule of law or a rule applicable to all cases of this type. As the trial commissioner shows, the Armed Services Board of Contract Appeals placed its decision on the evidence in the record, but in doing so wholly misconstrued that evidence and, accordingly, made a factual finding not based on substantial evidence. For that reason this administrative determination cannot stand. Whether the same, or a similar, determination could be made upon a different record in another case is not before us.

Since the court agrees with the opinion and recommended conclusion of the trial commissioner, as hereinafter set forth, it hereby adopts the same, together with the foregoing paragraph, as the basis for its judgment in this case. Therefore, as to Count II of the petition plaintiff’s motion for summary judgment is granted, defendant’s cross-motion denied and judgment is entered for plaintiff in the sum of $60,464.25. As to Count V of the petition plaintiff’s motion for summary judgment is denied, defendant’s cross-motion is granted and the petition is dismissed. The suspension of the entry of judgment for plaintiff on Count I of the petition in the sum of $3,545.57, set forth in our opinion of July 16, 1965 (348 F.2d 475, 484, 172 Ct.Cl. 60, 74), is terminated and judgment is hereby entered for plaintiff accordingly.

OPINION OF COMMISSIONER

HOGENSON, Commissioner:

Counts II and V of plaintiff’s petition are now presented for decision on plaintiff’s motion and defendant’s cross-motion for summary judgment, with supporting briefs of the parties, in review of decisions of the Armed Services Board of Contract Appeals pursuant to the standards of judicial review prescribed by the Wunderlich Act, 41 U.S. C. §§ 321, 322.

It is my opinion that plaintiff is entitled to recover the sum of $60,464.25 on Count II of the petition, but that plaintiff is not entitled to recover on Count V.

The status of the other counts of plaintiff’s petition is as follows: Count I was by the court decided in favor of plaintiff in the sum of $3,545.57, with entry of judgment suspended pending the entry of judgment on the other claims involved in plaintiff’s petition, 348 F.2d 475, 484, 172 Ct.Cl. 60, 74. Counts III and VIII have been dismissed upon stipulations of the parties. Count VI was dismissed by the court. 348 F.2d 475, 485, 172 Ct.Cl. 60, 76. Counts IV, VII and IX are being prepared in pretrial procedures for a trial de novo in this court.

Plaintiff contracted with the Department of the Air Force to construct 290 family housing units under the Capehart Housing Act on a 67.5-acre tract at Niagara Falls Municipal Airport, Niagara Falls, New York. The amount of the *1346 contract, as originally executed, was $4,762,000, later increased somewhat by supplemental agreement.

Count II — Grade Elevations

Plaintiff’s claim, denied by defendant’s contracting officer and duly appealed to the ASBCA, is that the actual grade elevations on the project site were 6 inches lower than as shown on the contract drawings, and that plaintiff was required to attain the finished design grades, which required plaintiff to bring onto the project site and compact an additional 56,132 cubic yards of earth fill.

In its decision, ASBCA No. 5704, 61-1 BCA 2905, the Board found that “the true mean ground elevation was .48 of a foot below the mean ground elevation delineated on the drawings.” The Board further found that plaintiff “was under no duty to make an investigation, prior to performance, to determine whether or not the drawings showed the correct elevations,” and further that plaintiff “had every reason to rely on their reasonable correctness.”

These basic conclusions of the Board are not assailed in this court, and are held to be final. Under attack by plaintiff is the measure of equitable adjustment prescribed by the Board, as hereinafter related.

The Board did not then determine the amount of recovery, but did decide that additional fill was in fact supplied, and remanded the claim to the contracting officer for initial determination of the quantity and value of the extra fill supplied. Further consideration of the claim by the contracting officer was then aborted by the extant ruling of the Comptroller General against further expenditures in view of the statutory limitation of costs on a Capehart Housing Act project. It was at this stage of administrative proceedings that plaintiff's petition was filed in this court.

The court thereafter held that the statutory limitation was not applicable to subject claim. 172 Ct.Cl. 60, 75, 348 F.2d 475, 484. Thereafter, such claim was by order of a formerly assigned trial commissioner of this court “remanded to the Armed Services Board of Contract Appeals for determination by that Board of (i) the quantities of additional earth spread and compacted, and (ii) the equitable adjustment per cubic yard for the furnishing of that material for the performance of the work.”

At a hearing convened thereafter by the Board, it was stipulated by the parties “that the amount of extra fill furnished by appellant was 52,350 cubic yards and that $1.00 per cubic yard plus 10% overhead and 5% profit is an equitable allowance for the costs caused by the extra fill.”

Upon recording the stipulation, the Board held that such agreement disposed of the issues on the claim, and dismissed the pertinent appeal.

In its above-cited decision, the Board concluded that “only 50% of the additional fill required should be compensable to the contractor.” Plaintiff’s arguments before this court are basically an attack upon the finality and validity of this conclusion of the Board. On this issue, the significant part of the Board’s decision is as follows:

We find from the evidence before us, considering fully the inexactness of the methods and manners used, that the true mean ground elevation was .48 of a foot below the mean ground elevation delineated on the drawings. This is approximately six inches.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cherry Hill Sand & Gravel Co. v. United States
33 Cont. Cas. Fed. 74,030 (Court of Claims, 1985)
Alfred A. Altimont, Inc. v. United States
579 F.2d 622 (Court of Claims, 1978)
American Dredging Co.
23 Cont. Cas. Fed. 80,971 (Court of Claims, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
422 F.2d 1344, 191 Ct. Cl. 292, 1970 U.S. Ct. Cl. LEXIS 28, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anthony-p-miller-inc-v-the-united-states-cc-1970.