Anson v. Eastburn

582 F. Supp. 18, 14 Envtl. L. Rep. (Envtl. Law Inst.) 20, 1983 U.S. Dist. LEXIS 11441
District Court, S.D. Indiana·Decided November 22, 1983·No. TH 82-114, C·Published·Cited by 3 cases

Opinion

*20 BROOKS, District Judge.

This matter comes before the Court upon the motions of the American Electric Power corporate defendants (hereinafter the AEP corporate defendants); Willis White, Jr. and William Black as individual defendants (hereinafter White and Black); and C.E. Eastburn as District Engineer for the United States Army Corps of Engineers (hereinafter Corps) for Summary Judgment as to Count I of plaintiffs’ complaint pursuant to Rule 56, Federal Rules of Civil Procedure.

All of the defendants have filed extensive briefs in support of their motions as well as replies to the plaintiffs’ briefs in opposition. Plaintiffs collectively filed responses to defendants’ motions for summary judgment and pursuant to this Court’s order of May 13, 1983 filed affidavits in support of their position.

Count I of plaintiffs’ complaint is an action brought under the National Environmental Policy Act (hereinafter NEPA), 42 U.S.C. §§ 4321 et seq., and alleges in the most general terms the following:

(1) that the AEP corporate defendants are constructing a coal-fired generating plant and associated transmission lines in the Southern Indiana area;
(2) that certain permits are required for the project, some of which were issued by the Corps of Engineers;
(3) that the Corps of Engineers is required to comply with NEPA in performing their duties with regard to the issuance of permits;
(4) that as part of the requirements of NEPA an Environmental Impact Statement (hereinafter EIS) must be prepared;
(5) that the EIS as prepared by the Corps was inadequate and improper;
(6) that because of the inadequacies - of the EIS the provisions of NEPA were violated;
(7) that the defendant C.E. Eastburn (hereinafter Eastburn) as District Engineer knew that the EIS was inadequate but proceeded to issue the required permits anyhow; and
(8) that such actions were arbitrary, capricious, and an abuse of discretion.

An examination of the complaint shows that plaintiffs do not specifically point to any shortcomings in the EIS which would render it inadequate or improper. Nor does plaintiffs’ response to the motions for summary judgment shed any light on exactly what provisions of the EIS are deemed insufficient. However, at the hearing held on defendants’ motions for summary judgment plaintiffs’ counsel appeared to indicate that the primary complaint is that the Corps failed to either discover from the material provided to them that there was no need for the plant, or to undertake a separate investigation as to the need for electrical power. In this regard, and pursuant to the Court’s order, plaintiffs’ counsel submitted affidavits from the following people: (1) Rees Shearer, Executive Director of the Coalition of American Electric Consumers, a named plaintiff in this cause; (2) Kanu R. Shak, an electrical engineer; (3) Frank Hauck, a civil engineer; (4) Beverly Coulson, another named plaintiff. Perusal of the four affidavits indeed shows that the main complaint is directed at the Corps evaluation or non-evaluation of the need for the project. Hauck’s affidavit states that “... [M]y study was directed toward what the statement says and what it omits about the need for electric power ...” and as Shearer stated in his affidavit, “[T]he primary research insufficiency in the ... Environmental Impact Statement ... is the complete failure of the Corps to undertake an independent assessment of the need for the project ...” The Coulson and Shak affidavits also point to alleged insufficiencies in the Corps determination of need for the project, although both also address other matters such as the inadequacies of the EIS’s treatment of the impact of the transmission lines themselves, the socio-economic impact on coal miners, and the plants possible contribution to acid rain.

The National Environmental Policy Act sets forth a declaration of national environmental policy and requires the Federal Government to use “all practicable means, *21 consistent with other essential considerations of national policy, to improve and coordinate Federal plans, functions, programs, and resources to achieve a wide range of environmental goals. See, 42 U.S.C. § 4331. To advance this policy Section 4332(2)(C) of Title 42 U.S.C. requires in pertinent part that all agencies of the Federal Government:

Include in every recommendation or record on proposals for legislation and other major Federal Actions significantly affecting the quality of the human environment, a detailed statement by the responsible official on
(i) The environmental impact of the proposed action
(ii) Any adverse environmental effects which cannot be avoided should the proposal be implemented.
(iii) Alternatives to the proposed action.

Free access — add to your briefcase to read the full text and ask questions with AI

Anson v. Eastburn, 582 F. Supp. 18, 14 Envtl. L. Rep. (Envtl. Law Inst.) 20, 1983 U.S. Dist. LEXIS 11441 (S.D. Ind. 1983).

582 F. Supp. 18 (Anson v. Eastburn) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Price v. Obayashi Hawaii Corp.
914 P.2d 1364 (Hawaii Supreme Court, 1996)
Hampel v. Autoridad de Energia Electrica de Puerto Rico
716 F. Supp. 52 (D. Puerto Rico, 1989)
Sierra Club v. Marsh
714 F. Supp. 539 (D. Maine, 1989)