Anisgard v. Bray

419 N.E.2d 315, 11 Mass. App. Ct. 726, 1981 Mass. App. LEXIS 1040
CourtMassachusetts Appeals Court
DecidedApril 22, 1981
StatusPublished
Cited by17 cases

This text of 419 N.E.2d 315 (Anisgard v. Bray) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anisgard v. Bray, 419 N.E.2d 315, 11 Mass. App. Ct. 726, 1981 Mass. App. LEXIS 1040 (Mass. Ct. App. 1981).

Opinion

Rose, J.

The defendants appeal from a judgment with damages in the amount of $35,000 entered in favor of the *727 plaintiff. In his complaint, the plaintiff alleged that the defendants had breached their contract with him to share in the profits and employ him as the manager of a tennis facility to be constructed in Pittsfield in exchange for the use of the plaintiff’s idea and preparation for the construction of the facility. Refusing to follow the master’s conclusions of law, the judge found that the parties had formed an oral partnership agreement and that the defendants broke that agreement when they formed a limited partnership, in which they were the only general partners, to construct the tennis facility and share in its profits. Finding that there was insufficient evidence of the value of the plaintiff’s contribution to the partnership, the judge awarded damages under the contract theory of recovery espoused in Air Technology Corp. v. General Elec. Co., 347 Mass. 613, 624-626 (1964). We affirm the judge’s award.

The facts, as found by the master, may be summarized as follows: In 1972, or 1973, the plaintiff, a tennis professional, conceived an idea for the development of a tennis facility in the Berkshires. During 1973, and part of 1974, he spent considerable time and money developing this idea. Prior to his meeting the defendant Feeley on February 28, 1974, the plaintiff had located a suitable site for the facility, negotiated a proposed long-term lease with the owner of the property, obtained a feasibility study and preliminary architectural drawings, found a suitable builder, and had fruitful discussions with a Pittsfield bank concerning financing the project. The judge found that in connection with these efforts, the plaintiff incurred expenses in the amount of $10,000 and spent time worth $25,000.

After attempting without success to establish the facility in association with others, the plaintiff met the defendant Feeley on February 28, 1974, in the latter’s Boston office. The plaintiff described his background as an experienced tennis instructor and disclosed to Feeley his ideas concerning the establishment of the tennis facility. The plaintiff described the work he had performed in developing the site and the expenses he had incurred. He disclosed the identity *728 of the property owner with whom he had been negotiating a long-term lease and the name of the bank with which he had negotiated for financing. The plaintiff also provided Feeley with a copy of the feasibility study for the tennis facility.

On March 6, 1974, the plaintiff introduced Feeley to the owner of the proposed site and on March 7, 1974, Feeley introduced the plaintiff to Bray, a wealthy investor who frequently participated in real estate developments of various descriptions. Bray told Anisgard that Feeley was authorized to determine whether the idea was a desirable venture and if so, Feeley and Bray would obtain the necessary financing and Anisgard would participate as the manager and part owner of the enterprise.

By mid-April, Feeley had determined that the facility was a desirable project and he, Bray, and Anisgard met to discuss the financial interest each would have in the enterprise. Feeley prepared a written memorandum setting forth the terms of the parties’ agreement and submitted it to the plaintiff. The plaintiff accepted those terms which conformed with the parties’ earlier discussions. The memorandum also included, however, additional terms not previously discussed, relative to financing the project in the event that existing arrangements for financing failed to materialize. The plaintiff sought clarification of the additional terms before executing the document. He received no response and never executed the document. Sometime in early June, 1974, Feeley and Bray decided to proceed with the development of the facility in partnership with each other and to exclude the plaintiff from any participation in the project. To this end, the defendants formed on August 1, 1974, a limited partnership known as Tamarack Tennis Associates, the name the plaintiff had proposed for the facility. Although the plaintiff contacted both defendants at various times throughout the summer of 1974, they did not disclose to the plaintiff that they had excluded him from participation in the project until September 3, 1974. *729 Construction of the facility was commenced in early August, 1974, and was completed by December, 1974.

After forming the limited partnership, the defendants obtained a long-term lease of the same site the plaintiff had suggested and for which the plaintiff had provided a feasibility study. The terms of the lease were the same as those negotiated by the plaintiff. The defendants obtained financing for the construction of the facility from the same bank with which the plaintiff had negotiated. The judge found that the “[p]laintiff provided the idea for the project and performed substantial work of value to the project . . . .” She also found: “ The plaintiff’s idea and the result of his work were utilized by [the] defendants in carrying out the project.” 2

We are of the opinion that, under these facts, the defendants are liable under an implied-in-fact contract. That the plaintiff expected to be paid for the work he performed and the idea he disclosed to the defendants is not sufficient of itself to establish the existence of a contract. Day v. Caton, 119 Mass. 513, 515 (1876). It must be shown that the defendants expressly or impliedly assented to pay for the plaintiff’s services and expenses. If a party “voluntarily accepts and avails himself of valuable services rendered for his benefit, when he has the option whether to accept or reject them, even if there is no distinct proof that they were rendered by his authority or request, a promise to pay for them may be inferred.” Id. at 515. See Burton v. Burton Stock Car Co., 171 Mass. 437, 440 (1898); Baltimore & Ohio R.R. v. United States, 261 U.S. 592, 597 (1923). In the instant case, the plaintiff expected to be paid; he disclosed his idea and informed the defendants of the value of his services with the understanding that if his idea and work were used, he would be compensated. The defendants contend that since the plaintiff performed all of his services before he met *730 the defendants, he cannot recover because only a past consideration was shown. That argument fails because the tendered consideration was the conveyance of the development package which the defendants accepted through their conduct. As the plaintiff’s performance and promise were contemporaneous, the facts show present consideration. See Gellert v. Dick, 277 N.Y. 123, 125 (1938).

After the defendants examined the concept and determined that it was a desirable venture, they expressed interest in it and on three separate occasions the parties discussed the form and amount of the plaintiff’s compensation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth v. Forbes
7 N.E.3d 476 (Massachusetts Appeals Court, 2014)
Backman v. SMIRNOV
751 F. Supp. 2d 304 (D. Massachusetts, 2010)
Gaw v. Sappett
816 N.E.2d 1027 (Massachusetts Appeals Court, 2004)
Park Drive Towing, Inc. v. City of Revere
800 N.E.2d 331 (Massachusetts Appeals Court, 2003)
Castano v. New England Telephone
7 Mass. L. Rptr. 69 (Massachusetts Superior Court, 1997)
Popponesset Beach Ass'n v. Marchillo
658 N.E.2d 983 (Massachusetts Appeals Court, 1996)
Szalla v. Locke
657 N.E.2d 1267 (Massachusetts Supreme Judicial Court, 1995)
Poirier v. Raad
3 Mass. L. Rptr. 265 (Massachusetts Superior Court, 1995)
Fidelity Trust Co. v. Brennan
1993 Mass. App. Div. 230 (Mass. Dist. Ct., App. Div., 1993)
Geza J. Jako, M.D. v. Pilling Company
848 F.2d 318 (First Circuit, 1988)
Jako v. Pilling Co.
670 F. Supp. 1074 (D. Massachusetts, 1987)
Tosti v. Pro-Tection, Inc.
1986 Mass. App. Div. 132 (Mass. Dist. Ct., App. Div., 1986)
General Dynamics Corp. v. Federal Pacific Electric Co.
482 N.E.2d 824 (Massachusetts Appeals Court, 1985)
Robert Trent Jones, Inc. v. Canter
474 N.E.2d 560 (Massachusetts Appeals Court, 1985)
Vantage Point, Inc. v. Parker Bros., Inc.
529 F. Supp. 1204 (E.D. New York, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
419 N.E.2d 315, 11 Mass. App. Ct. 726, 1981 Mass. App. LEXIS 1040, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anisgard-v-bray-massappct-1981.