Anil Construction Inc. v. Patrick D. McCollum

CourtCourt of Appeals of Tennessee
DecidedJuly 15, 2015
DocketW2014-01979-COA-R3-CV
StatusPublished

This text of Anil Construction Inc. v. Patrick D. McCollum (Anil Construction Inc. v. Patrick D. McCollum) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anil Construction Inc. v. Patrick D. McCollum, (Tenn. Ct. App. 2015).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON June 10, 2015 Session

ANIL CONSTRUCTION INC. v. PATRICK D. MCCOLLUM, ET AL.

Appeal from the Chancery Court for Madison County

No. 67465 William B. Acree, Judge

________________________________

No. W2014-01979-COA-R3-CV – Filed July 15, 2015

_________________________________

This is the second appeal of a case involving the alleged breach of a construction contract. The plaintiff general contractor hired the defendant subcontractor to build and install cabinetry for a movie theater. The subcontract provided that the work should be completed by the date the theater was scheduled to open. However, at the theater‘s opening, several items remained unfinished. The general contractor refused to pay despite the subcontractor‘s demand for payment. The general contractor filed suit alleging breach of contract for failure to complete the project in a timely manner and for defective work. The subcontractor counterclaimed for breach of contract for failure to pay under the contract. After a bench trial, the trial court found in favor of the subcontractor and awarded damages. The general contractor now appeals. Discerning no error, we affirm.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed

J. STEVEN STAFFORD, P.J., W.S., delivered the opinion of the Court, in which ARNOLD B. GOLDIN, J., and KENNY ARMSTRONG, J., joined.

Adam M. Nahmias, Memphis, Tennessee, for the appellants, Anil Construction, Inc.

Jon A. York, Jackson, Tennessee, for the appellee, Patrick David McCollum.

OPINION Background

This is the second appeal in this case involving an alleged breach of a construction contract. Accordingly, we take many of the facts from our prior Opinion, Anil Construction, Inc. v. Patrick D. McCollum, Individually and d/b/a Pat‘s Custom Cabinets, No. W2013-01447-COA-R3-CV, 2014 WL 3928726 (Tenn. Ct. App. Aug. 7, 2014) (―Anil Construction I‖). Ambarish Keshani is in the business of owning and operating movie theaters. Id. at *2. Mr. Keshani uses his own construction company, Plaintiff/Appellant Anil Construction, Inc. (―Anil Construction‖) to build the movie theaters. Id. Anil Construction operates as a general contractor and enters into contracts with subcontractors to complete various aspects of his theaters. See id. As stated in Anil Construction I, Mr. Keshani, through Anil Construction, began construction on a new movie theater in Jackson, Tennessee, the Cinema Planet 10 (―Cinema 10‖). On April 13, 2010, Anil Construction executed a contract with subcontractor Defendant/Appellee Patrick McCollum, d/b/a Pat‘s Custom Cabinets (―Mr. McCollum‖), for Mr. McCollum to build all of the cabinetry for the Cinema 10. The contract detailed the seven specific areas in Cinema 10 where Mr. McCollum was to install cabinets. In return, the parties agreed, Anil Construction would pay Mr. McCollum a total contract price of $44,650—half ($22,325) upon execution of the contract, and the other half 15 days after completion of the cabinet project. The contract describes the cabinet work as a ―turn- key‖ job, that is, both parties anticipated that the subcontractor would complete the entire project. The contract also stated that the job needed to be completed by the scheduled opening of the theater in June 2010, and that time was of the essence: Opening of [the] movie theatre in June, 2010 (Tentative date being June 11 but could move one or two weeks) is critical to Anil Construction Inc[.] and Pat‘s Cabinet understands that clearly and agrees to accommodate Anil Construction as needed.... Time is of an essence.

2 Construction of the movie theater did not go as planned. Id. Cinema 10 did not open in June 2010 as stated in the parties‘ contract. Id. The opening was delayed until October 1, 2010, for reasons that the parties dispute. Additionally, the cabinetry was not completed, even at the delayed October 1, 2010, opening of Cinema 10. Regarding this delay, [t]he record contains various email communications between the parties regarding the delay. In many of them, Mr. Keshani is urging Mr. McCollum to complete the job; in others, Mr. McCollum is pressing Mr. Keshani to pay him the balance owed on the contract. Mr. Keshani asserted that the delays in completion were caused by Mr. McCollum. Mr. McCollum in turn maintained that the delays were caused by factors outside of his control. Mr. McCollum would later testify at trial that the cabinetry work was installed and in use by October 12, 2010. In November 2010, Mr. Keshani sent emails to Mr. McCollum accusing him of taking items from the Cinema 10 that he was not authorized to take. Id. at *2–*3. In Mr. Keshani‘s email of November 16, 2010, he included a list of fifteen allegedly defective items (―Items 1 through 15‖) that he asked Mr. McCollum to correct or complete. As provided in Mr. Keshani‘s email to Mr. McCollum, Items 1 through 15 include: (1) Bar back wall shacks [sic] when swing door is used. Still does. (2) Formica in concession/bar area coming loose at spots. (3) Bar top flips still not corrected properly to sit on top of the bar counter and now hinges are bent. (4) Bar Top flips are not square with bar. Still are not. (5) Glass shelf does not support the weight of the liquor bottles. Still exist. You are saying to put wood on each side of shelf, while your man Jimmy told me, when has was at Cinema that, it would not help. He thought the solution was to put support in the middle of each shelf. Which one of you is correct? We just want it to be able to hold the liquor bottles, at the same look good and be practical in use without hindrance.

3 (6) Liquor Cabinet is not level/plum this is evident when looking at the mirror on the right side of the cabinet. This may be because the back bar top is sagging on the left. Still exist. (7) White piece of wood is exposed below Formica – close to the center. Still exist. (8) Foot rail in front of the bar sits off the floor in couple places. [S]till exist. (9) Formica – many places have damaged edges due to filing – poor work. Still exist. (10) Waves are evident in the front of concession Formica and poor joints. Jimmy put putty in joints but does not match with color and in time it will disappear. [N]eeds proper solution. (11) TV poles are mounted now, but the left one is not sitting level and tight on top of counter and sways. This is risky and creates liability. (12) Still have issues with many cabinet locks. (13) Trash can‘s [sic] enclosures sway door does not swing properly. Sticks due to clearance. (14) Bar front does not have rope light groove at bottom. Your offering to hang rope light does not solve the issue. There should be groove at bottom, just like at top. (15) Concession still dont [sic] have toe kick in front. Mr. Keshani stated that he would not pay Mr. McCollum until these items were complete. Additionally, Mr. Keshani forbade Mr. McCollum from going onto the theater property without arranging it in advance in writing with Mr. Keshani personally. Mr. Keshani told Mr. McCollum that he did not consider the job to be complete until all of the listed items were done, and he made it clear that he would not pay the balance of the contracted fee until all of them were resolved. In an effort to address their disagreement, Mr. Keshani and Mr. McCollum had a face-to-face meeting on November 23, 2010. It did not go well. Mr. Keshani emphasized the items 4 that still needed to be resolved, and Mr. McCollum insisted on getting payment from Mr. Keshani. According to Mr. Keshani, the meeting culminated in Mr. McCollum threatening him with bodily harm. After that, both sides threatened legal action. On December 1, 2010, Mr. Keshani emailed Mr. McCollum that he would pay Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Neal Lovlace v. Timothy Kevin Copley
418 S.W.3d 1 (Tennessee Supreme Court, 2013)
Franklin County Board of Education v. Crabtree
337 S.W.3d 808 (Court of Appeals of Tennessee, 2010)
Poole v. Union Planters Bank, N.A.
337 S.W.3d 771 (Court of Appeals of Tennessee, 2010)
Madden Phillips Construction, Inc. v. GGAT Development Corp.
315 S.W.3d 800 (Court of Appeals of Tennessee, 2009)
White v. Moody
171 S.W.3d 187 (Court of Appeals of Tennessee, 2004)
Walker v. Sidney Gilreath & Associates
40 S.W.3d 66 (Court of Appeals of Tennessee, 2000)
Blair v. Brownson
197 S.W.3d 681 (Tennessee Supreme Court, 2006)
McClain v. Kimbrough Const. Co., Inc.
806 S.W.2d 194 (Court of Appeals of Tennessee, 1990)
Bruce v. Bruce
801 S.W.2d 102 (Court of Appeals of Tennessee, 1990)
Jones v. Garrett
92 S.W.3d 835 (Tennessee Supreme Court, 2002)
Bowden v. Ward
27 S.W.3d 913 (Tennessee Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Anil Construction Inc. v. Patrick D. McCollum, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anil-construction-inc-v-patrick-d-mccollum-tennctapp-2015.