American Louisiana Pipe Line Company v. Federal Power Commission

344 F.2d 525
CourtCourt of Appeals for the D.C. Circuit
DecidedMay 7, 1965
Docket18108
StatusPublished
Cited by15 cases

This text of 344 F.2d 525 (American Louisiana Pipe Line Company v. Federal Power Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Louisiana Pipe Line Company v. Federal Power Commission, 344 F.2d 525 (D.C. Cir. 1965).

Opinions

WASHINGTON, Circuit Judge.

This is a natural gas case, concerning the form of the rates to be charged by the petitioner, American Louisiana Pipe Line Company. Petitioner owns and operates an interstate natural gas pipeline running from' southern Louisiana to Michigan. The pipeline began operations in 1956. Currently, American Louisiana sells over 95% of its natural gas to two Michigan corporations, Michigan Wisconsin Pipe Line Company and Michigan Consolidated Gas Company. All three companies are wholly-owned subsidiaries of the American Natural Gas Company

A few words may be said about American Louisiana’s past tariff filings. In 1954, the Federal Power Commission issued a certificate of public convenience and necessity to American Louisiana, permitting it to begin building its facilities. A condition attached to the certification stated that American Louisiana must file a tariff satisfactory to the Commission at least 60 days before beginning operations. 13 F.P.C. 380, 393 (1954). A subsequent order reaffirmed this condition and reserved “the right to reject any such proposed tariff and service agreements and to prescribe appropriate tariff and service agreements * * 15 F.P.C. 23, 43 (1956). The Commission employs two principal rate forms. The “contract demand” form of rate fixes a set price for gas in dollars and cents per unit on the basis of experience in a test year. This is the conventional rate form in general use for natural gas pipelines. In its brief, the Commission concedes that in most natural gas rate cases the contract demand rate form is to be preferred. That form assures the pipeline customers of a definite price and stable supply. In turn, the set rate level stimulates the pipeline’s efforts to cut costs, thereby generating more capital for improvement and modernization of service, eventually resulting in lower charges to the consumer. See 18 F.P.C. 795, 799 (1957) (dissenting opinion). The “cost of service” form prescribes variable rates adjusted monthly so that a pipeline recovers its actual costs plus a fixed return. This rate is apparently used with new enterprises with little or no operating experience on which to base a contract demand rate.

[527]*527On June 11, 1956, American Louisiana filed a conventional contract demand rate schedule; this was rejected by the Commission. Its principal reason was that American Louisiana was a new enterprise and had no experience on which to base specific rates:

“As set forth in more detail hereinafter, American Louisiana’s cost of service is not sufficiently definitive at this time to support specified unit demand and commodity rates, such claimed costs of service appear excessive, and the proposed contract demand tariff does not seem appropriate for the sales to affiliates for the initial few years of service. *****
“We find that a cost of service type of tariff is necessary and proper here for the initial few years of service to protect American Louisiana (and its parent) if costs increase before increased rates can be made effective and to protect the public against excessive rates during the period required to properly determine costs of service and to effect rate reductions.” (Italics added.) 16 F.P.C. 779, 780-81 (1956).

The Commission prescribed a cost of service tariff “for the initial few years of service.”

On March 18, 1957, American Louisiana again filed a tariff based on a contract demand rate schedule. The Commission rejected this filing by a vote of 3-2. Viewing the contract demand filing as “premature,” the majority found:

“The brief period of actual operation does not yield sufficient experience to justify a change from the prescribed cost of service form of rate schedule to a contract demand rate schedule.” 18 F.P.C. at 798.

This rejection was expressly stated to be without prejudice to a future filing after sufficient operating experience had been accumulated. The inter-affiliate character of American Louisiana’s sales, which had been a factor in the rejection of the original filing, was not treated as an operative fact in this decision.1

On April 6, 1959, American Louisiana filed the contract demand tariff involved in this proceeding. At that time American Louisiana had been in operation for more than the two-year period suggested in the Commission’s 1957 decision as a prerequisite to the granting of a contract demand rate. After a field audit, on July 12, 1961, the Commission staff joined in a stipulation of American Louisiana’s overall cost of service (the annual revenue required to enable it to recover its operating costs and the allowed return on its rate base), based on test year operations for the year 1960. The Commission approved the stipulation, by order of October 20, 1961, with some modifications not here relevant. The Presiding Examiner approved the change in rate form requested by American Louisiana. The level of rates was lower than the level originally requested by American Louisiana, however; it was based on the cost of service stipulated for the test year 1960.

The Commission rejected the Presiding Examiner’s decision insofar as it permitted the change in rate form. It relied exclusively on the fact that American Louisiana sells virtually all of its gas to affiliates. In its Opinion and Order No. 387 issued May 16, 1963, the Commission ruled:

“We conclude that, contrary to the examiner, American Louisiana’s change from a cost-of-service to a conventional rate should be denied. As years of regulatory experience attest, sales to affiliates present possibilities of abuse and should be scrutinized with eare. * * * A cost-of-service rate affords us an effective and feasible means of supplying the desired supervision. Under such a rate, the seller’s charges to its affiliates are computed on the basis of its actual costs for succes[528]*528sive billing periods, plus the return allowed. Thereby the seller is permitted all costs to which it is entitled but no more, thus achieving the desideratum of utility rate regulation. **«■** -X-
“These arguments of Michigan Wisconsin [American Louisiana] do not support the requested change, nor was any evidence adduced to support it. American Louisiana is undeniably an affiliate of Michigan Wisconsin and Michigan Consolidated, which purchase in excess of 95 percent of its gas. These circumstances justify applying to it requirements not invoked against companies otherwise situated. * * * And on the present facts, we conclude that we can best attain the objective of rate regulation — the allowance of all proper costs and return but no more — by requiring the continued use of a cost-of-service form of rate.” (Footnotes omitted.)

American Louisiana has petitioned this court under Section 19(b) of the Natural Gas Act of 1938, 52 Stat. 831, as amended, 15 U.S.C. § 717r(b) (1958), to review this decision imposing a cost of service rate form. It has been the Commission’s regular practice to require established natural gas pipelines to sell on a contract demand basis. This practice is reflected in its regulations, which provide that a cost of service rate form will be allowed only “Upon application and for good cause shown.” 18 C.F.R. § 154.52.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Public Service Commission of the State of New York v. Federal Energy Regulatory Commission, Commonwealth Gas Pipeline Corp., Carolina Pipeline Corporation, Transcontinental Gas Pipe Line Corporation, Intervenors. North Carolina Natural Gas Corporation, Public Service Company of North Carolina, Inc., Piedmont Natural Gas Company, Inc. v. Federal Energy Regulatory Commission, Carolina Pipeline Company, Commonwealth Gas Pipeline Corporation, Public Service Commission of the State of New York, Transcontinental Gas Pipe Line Corp., Brooklyn Union Gas Co., Columbia Gas Transmission Corp., Washington Gas Light Company, Atlanta Gas Light Company, Intervenors. North Carolina Utilities Commission v. Federal Energy Regulatory Commission, Carolina Pipeline Company, Commonwealth Gas Pipeline Corporation, Public Service Commission of the State of New York, Transcontinental Gas Pipe Line Corp., Brooklyn Union Gas Co., Columbia Gas Transmission Corp., Washington Gas Light Company, Atlanta Gas Light Company, North Carolina Natural Gas Corp., Intervenors. Long Island Lighting Company v. Federal Energy Regulatory Commission, Transcontinental Gas Pipe Line Corp., North Carolina Natural Gas Corp., North Carolina Utilities Commission, Carolina Pipeline Company, Commonwealthgas Pipeline Corporation, Public Service Commission of the State of New York, Brooklyn Union Gas Company, Washington Gas Light Company, Atlanta Gas Light Company, Intervenors. The Brooklyn Union Gas Company v. Federal Energy Regulatory Commission, Transcontinental Gas Pipe Line Corp., Public Service Commission of the State of New York, Commonwealth Gas Pipeline Corporation, North Carolina Natural Gas Corp., North Carolina Utilities Commission, Washington Gas Light Company, Atlanta Gas Light Company, Intervenors. Transcontinental Gas Pipe Line Corporation v. Federal Energy Regulatory Commission, Carolina Pipeline Company, North Carolina Natural Gas Corp., Brooklyn Union Gas Company, Intervenors
642 F.2d 1335 (D.C. Circuit, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
344 F.2d 525, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-louisiana-pipe-line-company-v-federal-power-commission-cadc-1965.