American Contractors Indemnity Co. v. United States

81 Fed. Cl. 682, 2008 U.S. Claims LEXIS 118, 2008 WL 1922982
CourtUnited States Court of Federal Claims
DecidedApril 29, 2008
DocketNo. 07-374 C
StatusPublished
Cited by5 cases

This text of 81 Fed. Cl. 682 (American Contractors Indemnity Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Contractors Indemnity Co. v. United States, 81 Fed. Cl. 682, 2008 U.S. Claims LEXIS 118, 2008 WL 1922982 (uscfc 2008).

Opinion

OPINION AND ORDER

SWEENEY, Judge.

Before the court is defendant’s Motion to Dismiss. Defendant argues that plaintiff, American Contractors Indemnity Company (“ACIC”), fails to state a claim upon which relief can be granted pursuant to Rule 12(b)(6) of the Rules of the United States Court of Federal Claims (“RCFC”) because it did not obtain prior written approval from the Small Business Administration (“SBA”) for an increase in a Surety Bond Guarantee Agreement (“Guarantee Agreement”) between plaintiff and the SBA, as required by the applicable regulation. Def.’s Mot. Dismiss (“Def.’s Mot.”) 1. The court deems oral argument unnecessary. For the reasons set forth below, defendant’s motion is granted.

I. FACTUAL BACKGROUND1

Plaintiff engages in the business of issuing performance and payment contract bonds as surety for the performance of construction contracts. Compl. ¶ 1. In 2002, DiGiovanni Insulation and Refractory, Inc. (“DiGiovan-ni”), the principal contractor hired to perform alterations and construct additions to a two-story building located in New Orleans, Louisiana (“the project”), applied to plaintiff for bonds to be issued in connection with the project. Id. ¶ 9. On August 20, 2002, DiGiov-anni, as principal obligor and as a corporate indemnitor, along with Janet DiGiovanni and Emile DiGiovanni as individual indemnitors (collectively, “the indemnitors”), executed and delivered to plaintiff a General Indemnity Agreement as partial consideration for issuing bonds for the project. Id. ¶ 10; see also Pl.’s Ex. 2 (containing the general indemnity agreement signed by the parties). On September 13, 2002, DiGiovanni and the project owner, Steve Ho, executed a construction contract for the project in the amount of $1,781,850.00. Compl. ¶ 11; see also PL’s Ex. 3 (containing the September 13, 2002 construction contract).

On September 27, 2002, the SBA entered into the Guarantee Agreement with plaintiff.2 Compl. ¶7; see also PL’s Ex. 1 (containing the September 27, 2002 Guarantee Agreement). The Guarantee Agreement indicated that the SBA agreed to reimburse plaintiff 80 percent of any loss or expense suffered by plaintiff in connection with a bond issued pursuant to the terms of the Guarantee Agreement. Compl. ¶ 8; PL’s Ex. 1. It also stated that the SBA would guarantee the bonds subject to the regulations found at 13 [684]*684C.F.R. § 115 (2002).3 PL’s Ex. 1. On October 4, 2002, plaintiff executed payment and performance bonds in the amount of $1,781,850.00 in connection with the project. Compl. ¶ 11; see also Pl.’s Ex. 4 (containing both the payment and performance bonds). The penal amount of each bond was $1,781,850.00. Compl. ¶ 11; Pl.’s Ex. 4. “As additional mitigation of the anticipated exposure on the bonds requested by DiGiovanni,” plaintiff also entered into an agreement with the Louisiana Bond Assistance Program (“LBAP”) to guarantee any losses, up to $200,000.00, that plaintiff might incur on the bonds. Compl. ¶ 10.

During the course of work on the project, DiGiovanni and the project owner agreed to a $240,000.00 increase in the contract price. Compl. ¶ 12; see also Pl.’s Ex. 5 (containing handwritten modifications to the original Guarantee Agreement reflecting amendments); Def.’s Ex. 1 (containing the surety rider, “[t]o be effective March 24, 2003,” indicating an “approved changed order of $240,000.00”). Plaintiff submitted the amended Guarantee Agreement to the SBA on May 19, 2004. Def.’s Ex. 2. The SBA agreed, in consideration of payment of an additional fee, to an amendment of the Guarantee Agreement to increase its guarantee from the original contract and bond amount of $1,781,850.00 to $2,021,850.00. Compl. ¶ 12; Def.’s Ex. 2 (containing the amended Guarantee Agreement reflecting an additional $240,000.00 to the contract amount). In accordance with applicable regulations, the SBA reduced its reimbursement obligation from 80 percent to 79.14 percent of any loss suffered by plaintiff on the bonds. Compl. ¶ 12; Def.’s Ex. 2. The SBA approved the amended Guarantee Agreement on June 2, 2004.4 Def.’s Ex. 2.

In or about July 2004, plaintiff received notice of claims on the bonds. Compl. ¶ 13. Plaintiff investigated and resolved claims on the payment bond via settlement and payments totaling $204,650.67. Id. DiGiovanni was subsequently declared in default by the project owner and was terminated from performing the contract. Id. ¶ 14. Plaintiff also investigated a claim on the performance bond, which it ultimately resolved via settlement and payments totaling $650,000.00. Id. Plaintiff incurred over $100,000.00 in expenses and attorneys fees in connection with investigating and defending the claims on the bonds, id. ¶ 16, and recovered $200,000.00 from the LBAP, id. ¶ 17, in order to “partially offset the losses and expenses incurred ... in connection with the Bonds,” Pl.’s Resp. 4; see also Compl. ¶ 17 (stating that plaintiff applied the recovery from the LBAP “against its losses such that the SBA received the benefit of the recovery”). Plaintiff is currently pursuing litigation against both the project architect and the indemnitors.5 Compl. ¶¶ 15,20.

Plaintiff “timely notified [the] SBA of the claims and provided multiple reports on the status of the claims and payments made therein in full compliance with 13 C.F.R. § 115.35(a) and (b) and all other applicable regulations and standards of performance under the Guarantee Contract.”6 Id. ¶ 18. It submitted, pursuant to 13 C.F.R. § 115.35(c), “numerous requests for payment by the SBA of $619,548.51, with supporting documentation.”7 Id. ¶ 19. In its final deci[685]*685sion issued on May 4, 2007, the SBA concluded that, because plaintiff “acquiesced in the bond amount of $240,000.00 prior to obtaining the approval of [the] SBA as required by 13 CFR § 115.91(e)[,] ... [the] SBA cannot honor this claim or any other claim arising out of the DiGiovanni default.” Pl.’s Ex. 6; Compl. ¶ 19. Plaintiff alleges that the SBA’s refusal to pay under the Guarantee Agreement constitutes a breach of contract for which the SBA is liable and seeks partial reimbursement of payments it made to satisfy claims against the bonds plus attorneys fees and costs incurred related to the investigation and defense of litigation of the claims made on the bonds. Compl. Prayer for Relief ¶¶ 1-2.

II. LEGAL STANDARDS

A. Subject Matter Jurisdiction

The Tucker Act, 28 U.S.C. § 1491 (2000), confers upon the United States Court of Federal Claims jurisdiction “to render judgment upon any claim against the United States founded either upon the Constitution, or any Act of Congress or any regulation of an executive department, or upon any express or implied contract with the United States, or for liquidated or unliquidated damages in cases not sounding in tort.” Id § 1491(a)(1).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lippmann v. United States
127 Fed. Cl. 238 (Federal Claims, 2016)
Legal Aid Society v. United States
92 Fed. Cl. 285 (Federal Claims, 2010)
American Contractors Indemnity Co. v. United States
570 F.3d 1373 (Federal Circuit, 2009)
American Contractors Indemnity Co. v. United States
82 Fed. Cl. 774 (Federal Claims, 2008)
Akins v. United States
82 Fed. Cl. 619 (Federal Claims, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
81 Fed. Cl. 682, 2008 U.S. Claims LEXIS 118, 2008 WL 1922982, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-contractors-indemnity-co-v-united-states-uscfc-2008.