American Boys Construction Company

Armed Services Board of Contract Appeals·Decided September 13, 2017·No. ASBCA No. 60515·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) American Boys Construction Company ) ASBCA No. 60515 ) Under Contract No. W56SGK-16-C-0013 )

APPEARANCE FOR THE APPELLANT: Mr. Nadeem Alamyar President

APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq. Army Chief Trial Attorney MAJ Bruce L. Mayeaux, JA Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE PROUTY

This appeal is about the compensation due to appellant, American Boys Construction Company (ABC), for the government's terminating the above-captioned contract (the contract) for convenience. ABC alleges 1 that in the nine days between contract award and a government stop-work order, it incurred $67,793 in compensable costs under the contract- primarily for supplies that it obtained in preparation for contract performance, but also for stand-by labor costs (app. hr. at 2; app. reply br.; see also R4, tab 10 at 4). 2 Because we find that ABC's purchase of the materials for which it now seeks compensation was unreasonably premature and that the amounts sought for stand-by labor costs have not been substantiated, we deny this appeal, although we would have been open to some stand-by labor costs if only ABC had presented evidence of such costs.

1 After initially requesting that this appeal proceed via a hearing, appellant ultimately elected to proceed under the auspices of Board Rule 11, in which the appeal is decided exclusively upon the written record. 2 ABC's briefs do not specify the amount of money sought in this appeal, nor does its complaint or any other filing made with the Board, except that its reply brief stated that it was seeking the amount requested by the termination settlement proposal it submitted to the contracting officer (app. reply hr. at 4). That amount was $67,793 (R4, tab 10 at 4). FINDINGS OF FACT

On 14 February 2016, the government's Regional Contracting Center- Capital in Kabul, Afghanistan (RCC), awarded the contract at issue in this appeal to ABC (R4, tab 1 at 1-2). This firm-fixed-price contract in the amount of$120,801 ($113,301 for the actual performance; $7,500 (estimated) for Defense Base Act Insurance) was for the installation of a "sniper screen" at a base in Kabul (id. at 3). The contract's 60-day period of performance was set to begin on 28 February 2016 and conclude on 29 April 2016. ABC was required to commence work within 5 days of receiving the notice to proceed from the government. (Id. at 6)

On 17 February 2016, ABC's project manager, Mr. Walusimbi John, emailed Sergeant First Class (SFC) Brandon Cooper, the contracting specialist assigned to provide administrative support on the contract (app. supp. R4, tab 1 at 2)3 • Mr. John said that he had "attached [a] list of suppliers for the project." SFC Cooper responded by informing Mr. John that he was looking forward to working with him again, but that the email included no attachment (id. at 3). The record does not indicate whether ABC responded with a re-sent attachment, and, given the email sent by ABC to SFC Cooper three days later (discussed below), we think it unlikely that it did.

On 18 February 2016, four days after contract award, the government held a preconstruction conference as provided for by the contract (see R4, tab 1 at 15 (contractual provision incorporating Federal Acquisition Regulation (FAR) 52.236-26, PRECONSTRUCTION CONFERENCE (FEB 1995) into the contract), tab 2 (signed memorandum detailing conference)). According to a memorandum describing the conference that was signed by both government and ABC representatives, among other matters discussed, ABC was informed of the contractual requirement to tender material submittals to the government on a specified form, the Air Force Form 3000 (R4, tab 2 at 2-3). Government representatives who attended this meeting included Major (MAJ) Joseph Cederstrom (the contracting officer (CO)), SFC Cooper, and First Lieutenant (lLT) David Morin (the CO's technical representative) (R4, tabs 14-16). SFC Cooper provided written testimony that, although he did not specifically recall the discussion held during this meeting, the standard practice at all such meetings he attended in Afghanistan was to follow the agenda set forth in the

3 ABC submitted to the Board, on 14 February 2017, a number of documents to act as its supplement to the Rule 4 file. After the first page, entitled, "Supplement," the pages are sequentially numbered through page 6, followed by a two-page declaration by ABC's president, Mr. Nadeem Alamyar. There were no tabs delimiting any groups of the documents, but we will consider all of the documents up to the declaration to be in tab 1 of ABC's supplement to the Rule 4 file, with Mr. Alamyar's declaration to constitute tab 2 to ABC's supplement to the Rule 4 file.

2 memorandum discussed above. This included informing the contractor that it was not to begin work prior to a notice to proceed issued by the CO and that materials needed to be approved by the CO via the Air Force Form 3000 "prior to installation" (R4, tab 15 at 2).

At some point around the time of the preconstruction meeting, government contracting personnel were alerted to the possibility that ABC might be the subject of security concerns that would preclude it from being permitted access to the base where the sniper screen was to be installed. lLT Morin's testimony suggests that this knowledge came about just before this meeting (see R4, tab 16 at 3); SFC Cooper's testimony implies that those concerns arose just after that meeting (R4, tab 15 at 2-3 ). The exact timing of when contracting officials obtained this knowledge need not be resolved here.

Two days after the preconstruction meeting, on 20 February 2016, ABC's project manager, Mr. John, emailed the material submittals to SFC Cooper with an attached Air Force Form 3000. Mr. John copied MAJ Cederstrom and lLT Morin on the message. (R4, tab 3) MAJ Cederstrom, the CO, testified that he never approved ABC's submittals (R4, tab 14 at 4). SFC Cooper and lLT Morin also deny knowledge of any approval of the material submittals (R4, tab 15 at 3, tab 16 at 4-5).

ABC alleges, in Mr. Alamyar's declaration, that Mr. John spoke with lLT Morin on 14 February 2016 about the materials needed for the project and that, due to their scarcity, lLT Morin had given him the "green light" to purchase these materials at that time (R4, tab 12 at 3). We find that this allegation is, more likely than not, incorrect, and conclude that no such approval was ever given. Mr. Alamyar's declaration regarding Mr. John's discussions with lLT Morin is, of course, double hearsay. Although we do not have any rule preventing the consideration of hearsay, see Board Rule 1 l(d) (permitting the weight of the evidence to rest within the discretion of the Board), the further the written testimony strays from the first-hand knowledge of the declarant, the less persuasive it becomes. In contrast, lLT Morin specifically denied engaging in any such conversation in his declaration (R4, tab 16 at 4). This denial by lLT Morin is made particularly persuasive by its consistency with his usual practice of disclaiming his authority to make contractual decisions that were reserved for the CO. It is further buttressed by the evidence that, contrary to ABC's allegations, the materials needed for the job did not appear to be scarce (id. at 4-5).

In any event, shortly after the preconstruction meeting, the government's security concerns about ABC ripened, and, on 23 February 2016, SFC Cooper emailed a stop-work order to ABC on behalf of the CO (R4, tabs 5, 14 at 4, tab 15 at 3). The stop-work order directed ABC to suspend all work on the contract and to cease its

3 efforts to obtain Defense Base Act insurance or any other materials needed for the performance of the contract (R4, tab 5).

Free access — add to your briefcase to read the full text and ask questions with AI

American Boys Construction Company, (asbca 2017).

American Boys Construction Company (American Boys Construction Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)
Dawco Construction, Inc. v. The United States
930 F.2d 872 (Federal Circuit, 1991)