Amerada Hess Corp. v. Burlington County Planning Board

951 A.2d 970, 195 N.J. 616, 2008 N.J. LEXIS 875
CourtSupreme Court of New Jersey
DecidedJuly 16, 2008
DocketA-41 September Term 2007
StatusPublished
Cited by8 cases

This text of 951 A.2d 970 (Amerada Hess Corp. v. Burlington County Planning Board) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Amerada Hess Corp. v. Burlington County Planning Board, 951 A.2d 970, 195 N.J. 616, 2008 N.J. LEXIS 875 (N.J. 2008).

Opinion

Justice LONG

delivered the opinion of the Court.

At issue on this appeal is the meaning of N.J.S.A. 40:27-6.7, a provision of the County Planning Act (CPA) that directs that a completed land use application is automatically deemed approved if the county planning board fails to take official action within thirty days, or within sixty days if both the municipal planning board and the applicant consent. There is no provision in the CPA for an extension of those time limits.

In Manalapan Holding Co. v. Planning Board of Hamilton, 92 N.J. 466, 457 A.2d 441 (1983), in interpreting an automatic approval provision in the Municipal Land Use Law (MLUL), we underscored the Legislature’s clear intent to require planning authorities to adhere to the strict statutory timetables established for approval and condemned permissive interpretation of such statutes. We also recognized a narrow exception for cases in which a planning board’s violation of the statutory time frame was inadvertent or unintentional. In such instances, we held that automatic approval would not advance the legislative goals underlying the statute.

*620 Here, the Burlington County Planning Board (the County Board) argues that automatic approval is only appropriate as a remedy for bad-faith violations of the statute and that, so long as a planning body continues to engage in good-faith dealings with the applicant, automatic approval is unwarranted regardless of how much time has passed. The lower courts disagreed, as do we.

The purpose of automatic approval is to require planning boards to make prompt decisions to benefit the applicant, the objectors, and the public at large. The Legislature obviously considered those values to be significant enough to put in place a strong automatic approval remedy with no exceptions. To interpret N.J.S.A. 40:27-6.7 as the County Board it was entitled to disregard the statutory time frames because it was continuing its dealings with the applicant and seeking further revisions of the eviscerate the scheme. To the contrary, we hold, as we did in Manalapan, that the statutory time constraints are to be strictly applied. In other words, under the CPA, if a county planning board fails to render a timely decision, the application is subject to automatic approval unless the board can establish that the delay was inadvertent or unintentional.

In this ease, the County Board failed to act within the timetable set forth in N.J.S.A. 40:27-6.7, and the applicant’s site plan was deemed approved. Because the County Board’s delay was neither inadvertent nor unintentional, we now affirm.

I

Hess Corporation (Hess) operates a gasoline station at the intersection of County Route 541 (also known as Mount Holly Road) and Cadillac Road in Burlington Township. 1 Hess acquired the development rights to an 18,679 square foot adjoining parcel and planned to use the site to modify its existing service station *621 and to construct a minimart with related site improvements. The adjoining parcel abuts Burlington Bypass (the bifurcated portion of County Route 541 constructed to move traffic around the congested parts of the area.

Because Hess’s plan for the adjacent property included a one-way egress driveway onto the Bypass, which is a county road, it needed to obtain county and municipal approval. On February 6, 2008, Hess’s engineer John Rea met with County Board engineers Thomas Jaggard and Martin Livingston to discuss the concept plan and Bypass egress. On August 7, 2003, Livingston informed Rea that the County was in the process of conducting a traffic and safety study of the Route 541 corridor and would be unable to approve the Bypass egress or make any recommendations regarding the site plan for approximately three to six months.

Approximately six months elapsed and on February 24, 2004, Rea again met with Livingston. At that meeting, Livingston voiced a preference for Hess’s design plan that featured a narrow, angled one-way egress to the Bypass, but took no action regarding the proposal. On April 15, 2004, Rea sent a memorandum to Jaggard, stating that “Hess Corporation is eager to submit revised plans to the County and Burlington Township and just wants to make sure that your engineering staff does not have any additional preliminary comments on the plans.” The engineer’s office apparently did not respond until August 5, 2004, notifying Hess that it should submit an application for informal review.

On September 13, 2004, Hess complied and filed an informal site plan application. On October 18, 2004, John A. Engle, the principal engineer of the County Board, sent a letter to Hess’s attorney, advising Hess that it would also need to obtain approval from the Burlington County Board of Chosen Freeholders for access. The letter reiterated that the County anticipated making major changes in the area, but was “not exactly sure what the final design will be at this point.” With no agreement in sight, Hess decided to finalize its site plan and formally file applications with both the Township and County Boards.

*622 On July 12, 2006, Hess filed a formal application with the County Board, seeking approval to demolish the existing structures on the adjoining parcel and to construct a 2,480 square foot Hess Express Minimart, eight gasoline dispensers, parking spaces, and related site improvements. The application included the plans for a one-way egress onto the Bypass. The next day, Hess filed an identical application with the Burlington Township Planning Board (the Township Board) for preliminary and final major site plan approval and several bulk variances.

On July 29, 2005, the County Board deemed Hess’s application incomplete and requested additional information and the balance of the application fee. Hess submitted the necessary information and fee, and the application was deemed complete on August 10, 2005. After a request from the Township Board for further information, Hess’s municipal application was deemed complete on August 28, 2005.

On September 1, 2005, Engle contacted Thomas Pugsley, a site designer for Hess, and provided Pugsley with technical review comments on the application. The engineer’s office apparently took issue with several aspects of the site plan, and Engle informed Pugsley that his office intended to recommend to the County Land Development Review Committee that it disapprove the application. Additionally, during that conversation, Engle requested an extension of the thirty-day review period, which was to expire September 12, to perform a more comprehensive analysis of the site plan proposal. Pugsley notified Engle that he would relay the request to Hess’s counsel and that a representative would respond.

With the thirty-day trigger looming and not having received a response to its request for an extension, Engle sent a letter to Hess on September 6, 2005, memorializing the review comments that had been conveyed to Pugsley. The specific comments were as follows:

Traffic Comments

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
951 A.2d 970, 195 N.J. 616, 2008 N.J. LEXIS 875, Counsel Stack Legal Research, https://law.counselstack.com/opinion/amerada-hess-corp-v-burlington-county-planning-board-nj-2008.