Sprint Spectrum, L.P. v. Zoning Bd. of Adj.

811 A.2d 956, 356 N.J. Super. 194, 2002 N.J. Super. LEXIS 517
New Jersey Superior Court Appellate Division·Decided July 24, 2002·Published·Cited by 1 cases

Opinion

HELEN E. HOENS, J.S.C.

This matter comes before the Court by way of a complaint in lieu of prerogative writ pursuant to which plaintiff Sprint Spectrum, L.P. seeks to reverse the decision of the Zoning Board of Adjustment of the Township of Green Brook which denied its application for a variance and site plan approval. The facts which give rise to this dispute and the record below are not in dispute. Plaintiff Sprint Spectrum filed an application with the defendant Zoning Board seeking permission to install certain telecommunications equipment within a PSE & G right-of-way located south of Route 22 in Green Brook Township. The plan as proposed would result in the addition of certain antennas near the top of an existing transmission tower. It is undisputed that the lot where the tower is located is partly within the Regional Highway Commercial (“RHC”) zone and partly within the Medium Density Residential (“MDR”) zone and that transmission towers and antennas are not permitted within either of those zones. In fact, it is conceded that transmission towers are permitted in Green Brook only in the conservation zone (“CA”) and the public recreation zone (“PR”). As a result of the foregoing, Sprint Spectrum was required to seek a use variance in order to secure permission to add its proposed antennas to the existing structure. At the same time that Sprint filed its use variance application, it also filed its preliminary site plan with the Township.

The application was deemed complete on July 28, 2000 and a first hearing on the matter was scheduled for November 15, 2000. Sprint contends that by virtue of the requirements of N.J.S.A. 40:55D-76(c) the Board was required to act on its application within 120 days of the date on which the application was deemed complete. As a result, Sprint asserts that by statute the Board’s [197] time to decide the issues raised in its application would have expired on November 28, 2000. Sprint contends that on November 15, 2000, counsel appeared along with four witnesses including an engineer and a professional planner who were prepared to testify about radio frequencies, the gap in transmission coverage and need for this location to address the gap, the site suitability and the site selection process.

It is uncontested that on November 15, 2000 the Zoning Board met and conducted some business unrelated to the Sprint application at which time the Board then requested that Sprint consent to an extension of time within which the Board would be able to hear the testimony and reach a decision on the Sprint application. At the time, the Board indicated that it might be able to entertain the application in December, but that because of the number of other matters then already listed for the December meeting, the Board advised the applicant that it did not anticipate being able to entertain the application until January of 2001. After discussion with counsel, the representatives of Sprint determined to refuse the extension that had been requested by the Board. Because the extension was refused, and because the Board believed that there was insufficient time in which to hear and consider the testimony needed to evaluate the application, the Board voted to deny the application in its entirety.

Now before the Court is the application of Sprint to have this Court reverse the denial of the application by Green Brook and to grant it all of the approvals sought. Sprint argues that the Board’s denial of the application without a hearing was arbitrary and capricious. Sprint contends it was unwilling to extend the period of time for Green Brook to address its application because of its perception that the Board’s treatment of a similar application by another wireless transmission provider was inappropriate. Sprint concedes that its attorney also represents Nextel, another wireless provider which was seeking to place antennas near the top of an existing facility close to the one that Sprint had selected in Green Brook. Sprint contends that the hearings in connection with Nextel’s proposal were unduly protracted and were unnecessarily burdensome and that Sprint feared that if it agreed to [198] extend the Board’s time, it would also be forced to endure what it believed would be similar unfair treatment of its application. Counsel for Sprint argues that in his experience similar applications in other communities have been heard and addressed promptly and in a single meeting before the Board and that Green Brook’s decision to conduct hearings on the very similar Nextel application over a period of some four months was a motivating factor in the decision by Sprint to refuse any extension.

Sprint argues that because of all of its witnesses were available to testify on November 15, the Zoning Board of Adjustment should have entertained all of their testimony that evening and voted on the application based upon the substance of those presentations. In light of the fact that the Board failed to do so, Sprint contends that the denial of its application without a hearing was arbitrary, capricious and unreasonable. Moreover, Sprint contends that even though the time remaining prior to the expiration of the statutory time frame was limited, the defendant could have scheduled a special meeting and ordered the defendant to appear if the time available on November 15 in fact proved to be insufficient. Finally, Sprint contends that if the Court refuses to grant relief on this record, the 120 day time frame mandated by the statute will become a nullity. Based upon the foregoing, Sprint seeks an order from this Court reversing the action of the Zoning Board and granting all of the approvals sought.

Free access — add to your briefcase to read the full text and ask questions with AI

Sprint Spectrum, L.P. v. Zoning Bd. of Adj., 811 A.2d 956, 356 N.J. Super. 194, 2002 N.J. Super. LEXIS 517 (N.J. Ct. App. 2002).

811 A.2d 956 (Sprint Spectrum, L.P. v. Zoning Bd. of Adj.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Amerada Hess Corp. v. Burlington County Planning Board
951 A.2d 970 (Supreme Court of New Jersey, 2008)