Allied Fire Protection v. Diede Construction Inc.

25 Cal. Rptr. 3d 195, 127 Cal. App. 4th 150, 2005 Cal. Daily Op. Serv. 1678, 2005 Daily Journal DAR 2255, 2005 Cal. App. LEXIS 296
CourtCalifornia Court of Appeal
DecidedFebruary 24, 2005
DocketC045720
StatusPublished
Cited by40 cases

This text of 25 Cal. Rptr. 3d 195 (Allied Fire Protection v. Diede Construction Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allied Fire Protection v. Diede Construction Inc., 25 Cal. Rptr. 3d 195, 127 Cal. App. 4th 150, 2005 Cal. Daily Op. Serv. 1678, 2005 Daily Journal DAR 2255, 2005 Cal. App. LEXIS 296 (Cal. Ct. App. 2005).

Opinion

Opinion

MORRISON, J.

Plaintiff Allied Fire Protection (Allied) appeals from a judgment in favor of defendants Diede Construction, Inc., and Wayne Diede on a fraud action after the trial court granted defendants’ motion for summary judgment on the basis of res judicata. Allied contends the fraud claim was not barred by res judicata because it did not accme until after the prior federal complaint had been filed. We agree and reverse the judgment.

FACTUAL AND PROCEDURAL BACKGROUND

Diede Construction, Inc., entered into a construction contract with the United States Department of the Air Force (USAF). Diede subcontracted the fire protection system for the project to Allied. The project was delayed by the USAF. The USAF and Diede negotiated a settlement for delay damages; the USAF agreed to pay Diede $495,000 for delays up to August 7, 1997, and $1,600 per day from August 8, 1997, until project completion. Diede and Allied settled Allied’s delay damages for $90,000.

In March 1999, Allied brought suit in federal court against Diede and a surety corporation for damages. Allied alleged Diede had breached the subcontract. During discovery, Allied found the letter from the USAF to Diede describing the additional delay damages of $1,600 per day.

The joint pretrial statement filed in the federal case included in its statement of facts that Diede failed to disclose to Allied the $1,600 per day payment, which totaled $425,400, and that Allied received no part of this second payment for delay damages. Allied claimed Diede breached the subcontract by its failure to disclose and its failure to make a payment to Allied. At the pretrial conference on February 12, 2001, Allied explained to the court it had discovered the alleged fraud in November 2000. Allied had prepared a stipulation to amend the complaint to add the fraud claim. Diede did not respond, which Allied interpreted as a rejection of the stipulation. The trial court noted Allied would have to show due diligence in conducting discovery in order to add the new claim. The court decided to take the claim *153 for additional delay damages out of the federal action unless Allied convinced the court it was entitled to amend the complaint. The final pretrial order did not mention additional delay damages as an issue in the case. The case was tried to the bench beginning April 17, 2001, and the court found for Allied in the amount of $179,380.

Allied then brought suit in state court against Diede and its principal owner, Wayne Diede. Allied alleged that Diede represented it had received only $495,400 from the USAF for delay damages and did not mention the $1,600 per day. These representations were false, Diede knew they were false, and they were made to induce Allied to enter into the $90,000 settlement of the delay damage claim. As a result of the misrepresentations, Allied made no further claim for delay damages and was damaged in the amount of no less than $142,983. Diede answered the complaint, asserting res judicata as an affirmative defense.

Diede moved for summary judgment, contending that res judicata was a complete defense to the state action. Diede argued that in the state action Allied was seeking delay damages resulting from the breach of the subcontract. The state action asserted the same cause of action as federal action. Both actions involved invasion of the same primary right: to be free of economic injury due to the wrongful conduct of Diede during performance of the subcontract. Diede contended Allied was required to include all remedies based on breach of the subcontract in the federal action.

In opposition Allied argued two primary rights were involved because a claim based on fraud was not the same as a claim based on contract.

At the hearing on the motion the trial court asked the parties to address additional authority.

In its supplemental brief, Diede argued federal law should determine the preclusive effect of the federal judgment. Under federal law, a transactional analysis is applied to determine whether the same cause of action is asserted in each of the two lawsuits. Diede contended the claims asserted in the state action arose from the same transaction, the construction contract, as the claims in the federal action.

Allied argued for application of the primary right analysis under California law, but asserted res judicata did not apply even under the federal test. Allied also cited to and placed great reliance on Doe v. Allied-Signal, Inc. (7th Cir. 1993) 985 F.2d 908, in which a second suit was filed after plaintiff discovered new facts. Allied quoted the court’s statement: “If the plaintiff is unaware of facts when filing a complaint, res judicata will not bar subsequent litigation.” *154 (Id. at p. 914, original italics.) Allied argued it did not discover the facts of Diede’s fraud until after the federal complaint was filed. The trial court found it had to apply federal law and use the transactional approach for res judicata. It found Allied was alleging that during performance of the subcontract, and while the federal case was pending, Diede defrauded Allied by not revealing that Allied was entitled to delay damages. This claim and the claims asserted in the federal action both arose from the same contract. The court granted Diede’s motion for summary judgment.

DISCUSSION

“ ‘Res judicata’ describes the preclusive effect of a final judgment on the merits. Res judicata, or claim preclusion, prevents relitigation of the same cause of action in a second suit between the same parties or parties in privity with them. . . . Under the doctrine of res judicata, if a plaintiff prevails in an action, the cause is merged into the judgment and may not be asserted in a subsequent lawsuit ....[][] A clear and predictable res judicata doctrine promotes judicial economy. Under this doctrine, all claims based on the same cause of action must be decided in a single suit; if not brought initially, they may not be raised at a later date. ‘ “Res judicata precludes piecemeal litigation by splitting a single cause of action or relitigation of the same cause of action on a different legal theory or for different relief.” ’ [Citation.] A predictable doctrine of res judicata benefits both the parties and the courts because it ‘seeks to curtail multiple litigation causing vexation and expense to the parties and wasted effort and expense in judicial administration.’’ [Citation.]” (Mycogen Corp. v. Monsanto Co. (2002) 28 Cal.4th 888, 896-897 [123 Cal.Rptr.2d 432, 51 P.3d 297].)

Allied contends res judicata does not bar its fraud action because the fraud claim did not accrue until after Allied filed the federal action. Allied asserts the fraud claim did not accrue until November 2000, when it discovered the letter from the USAF detailing the $1,600 per day payment to Diede for delay damages on and after August 8, 1997. This discovery occurred over a year and a half after Allied filed the federal action in March 1999.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Abioye v. Lee CA1/1
California Court of Appeal, 2026
Youssef v. County of Los Angeles CA2/4
California Court of Appeal, 2025
Dowling v. Uriostegui CA2/7
California Court of Appeal, 2025
Su v. Su
N.D. Illinois, 2023
5th AND LA v. Western Waterproofing Co., Inc.
California Court of Appeal, 2023
Barbaccia v. GBR Magic Sands MHP CA2/7
California Court of Appeal, 2023
Lucore v. Bank of America, N.A.
S.D. California, 2022
Max v. 8E6 Corp. CA2/1
California Court of Appeal, 2022
Lebolt v. City and County of S.F. CA1/3
California Court of Appeal, 2022
McGraw v. Pacifica Ashwood LLC
S.D. California, 2020
Stewart v. Virgin Islands Board of Land Use Appeals
66 V.I. 522 (Supreme Court of The Virgin Islands, 2017)
John Roberts v. Esther Andrews
668 F. App'x 757 (Ninth Circuit, 2016)
Kizor v. Blackwood Assocs. CA1/3
California Court of Appeal, 2016
Kalicki v. JPMorgan Chanse Bank CA4/1
California Court of Appeal, 2015
Vos v. Sandwood Enterprises CA4/1
California Court of Appeal, 2015

Cite This Page — Counsel Stack

Bluebook (online)
25 Cal. Rptr. 3d 195, 127 Cal. App. 4th 150, 2005 Cal. Daily Op. Serv. 1678, 2005 Daily Journal DAR 2255, 2005 Cal. App. LEXIS 296, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allied-fire-protection-v-diede-construction-inc-calctapp-2005.