Allentown Plaza Associates v. Suburban Propane Gas Corp.

405 A.2d 326, 43 Md. App. 337, 1979 Md. App. LEXIS 381
CourtCourt of Special Appeals of Maryland
DecidedSeptember 10, 1979
Docket1274, September Term, 1978
StatusPublished
Cited by39 cases

This text of 405 A.2d 326 (Allentown Plaza Associates v. Suburban Propane Gas Corp.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allentown Plaza Associates v. Suburban Propane Gas Corp., 405 A.2d 326, 43 Md. App. 337, 1979 Md. App. LEXIS 381 (Md. Ct. App. 1979).

Opinion

Moore, J.,

delivered the opinion of the Court.

In the proceedings below, the Circuit Court for Prince George’s County (Levin, J.) granted summary judgment motions filed by the defendants, four in number, based upon the general three-year statute of limitations contained in Md. [Cts. & Jud. Proc.] Code Ann. § 5-101 (1974). 1 The court rejected the contentions of the plaintiffs, appellants here, that their causes of action in assumpsit and tort, arising out of the construction of a shopping mall, were saved by the provisions of sections 5-108 of the same Article, 2 under which no claim *339 for damages accrues “from the defective and unsafe condition of an improvement to real property” occurring more than 20 years after the completion of the improvement. We shall affirm.

I

The appellant, Allentown Plaza Associates, is a Maryland limited partnership, which entered into a prime construction contract in March 1972 with appellant, Rand Industries, Inc., as general contractor, for the construction of a shopping center, known as Allentown Mall, located in Camp Springs, Prince George’s County, Maryland. Rand later became a partner in Allentown Plaza Associates.

Because of the unavailability of natural gas from the Washington Gas Light Company, appellants installed an underground pipeline system to provide liquid propane gas for its tenants. In March 1972, Allentown Plaza entered into a contract with the appellee, Suburban Propane Gas Corporation (Suburban), to supply the propane, to provide a propane gas storage tank, and to install 23 meters for measuring and controlling pressures for the base usage on each rental unit in the Mall. These meters were to be temporary and were to be removed when natural gas became available. The first paragraph of the contract provided in part:

“All Suburban’s equipment shall remain personalty, regardless of how attached to the realty, *340 and shall remain the sole property of Suburban, and Suburban shall have access thereto at all times for purposes of removal, repair, alteration, replacement and service, including the equipment of the individual tenants, exceptas otherwise provided for in this agreement----(Emphasis added.)

Pursuant to the contract, Suburban supplied the gas meters to the site but, for reasons not disclosed in the record, did not install them. Appellants were aware on November 30, 1972 of this breach of the propane contract, but took no legal action at that time. Rather, they employed two plumbing contractors, the appellees, Joseph J. Palmer, Jr. and K-Lo Plumbing, Inc., to make the installations. By October 1973, all the meters had been installed. Service to the stores with liquid propane gas commenced. A gas leak was discovered in the underground pipeline system in February 1975, and some corrective action was taken by the appellants. In September 1975, however, addditional leaks were detected and the entire underground system was abandoned and replaced by pipelines above ground. Replacement costs were approximately $30,500.

On January 1, 1977, over 3 years after the last meter and coupling had been installed, appellants filed a declaration against the aforementioned appellees and against the firm of Freidin and Arey Associates, the mechanical and electrical engineers for the project. They alleged that the leaks were caused by corrosion of the pipes and that the corrosion was due to appellees’ failure to install insulating fittings, known in the trade as “dielectric couplings,” where the gas lines connected to the gas .meters. 3

More specifically, the claim against Suburban was in assumpsit for failure to install the meters as required under the agreement, and in tort for failing to provide dielectric *341 couplings with the meters and to warn the appellants of the need for such couplings. The plumbing contractors who made the installations were alleged to be negligent in failing to use and to install dielectric couplings. The cause of action against Freidin and Arey was based upon negligence in failing to provide specifications or warnings concerning the need for such couplings or insulating fittings and otherwise failing to protect the pipes from corrosion.

Following discovery, each of the appellees, filed a motion for summary judgment on various grounds, including, in each instance, a claim that the declaration was barred by the three-year statute of limitations governing civil actions. Md. [Cts. & Jud. Proc.] Code Ann. § 5-101 (1974). 4 In a concise memorandum opinion and accompanying order, the motions were granted.

With respect to the count in assumpsit against Suburban, the court found that a breach of the Allentown-Suburban contract occurred prior to January 1,1974, “a time computed most favorably for Allentown.” Because the declaration was not filed until January 11, 1977, more than three years had elapsed and the assumpsit claim was barred by section 5-101. The court rejected the contention that the statute did not commence to run until February 1975 when the defects in the pipe system were discovered, instead holding that the three-year period began to run from the date of the breach of the agreement and not from the time the breach was discovered. Mayor & Council of Federalsburg v. Allied Contractors, Inc., 275 Md. 151, 338 A.2d 275, cert. denied, 423 U.S. 1017 (1975). See also Leonhart v. Atkinson, 265 Md. 219, 289 A.2d 1 (1972). With respect to the negligence counts, the court also found that section 5-101 was applicable, again rejecting a contention by the appellants that the period of limitations should begin to run from the date the wrong was discovered (February, 1975) and not the date when it occurred (December, 1973). 5 Watson v. Dorsey, 265 Md. 509, 290 A.2d *342 530 (1972). With respect to appellants’ reliance upon section 5-108, 6 the court held as follows:

“We do not believe that the gas pipe and meter system involved in this instance is an ‘improvement to real property’ within the meaning of § 5-108. The law in this state regarding what constitutes an improvement for purposes of § 5-108 treatment is very unclear. As a matter of fact, we have been unable to find any recorded case on this subject. However, Bankers’ & Merchants’ Credit Company v. Harlem Park Building & Loan Association, 160 Md. 230 (1930) points to a distinction between a fixture and an improvement to realty. This Court is of the opinion that the entire underground pipe and meter system was a fixture attaching to an improvement, the improvement being the above ground structure known as Allentown Mall Shopping Center.”

II

Free access — add to your briefcase to read the full text and ask questions with AI

Related

B. Frank Joy, L. L.C. v. Dist. of Columbia Sewer and Water Authority
213 A.3d 90 (District of Columbia Court of Appeals, 2019)
Janet Leichling v. Honeywell International, Inc
842 F.3d 848 (Fourth Circuit, 2016)
Townsend Baltimore Garage, LLC v. Supervisor of Assessments
79 A.3d 960 (Court of Special Appeals of Maryland, 2013)
Supervisor of Assessments v. Greater Baltimore Medical Center, Inc.
32 A.3d 174 (Court of Special Appeals of Maryland, 2011)
Pippin v. Reilly Industries, Inc.
64 F. App'x 382 (Fourth Circuit, 2003)
Hickman v. Carven
784 A.2d 31 (Court of Appeals of Maryland, 2001)
Lewis v. Weldotron Corp.
5 F. App'x 265 (Fourth Circuit, 2001)
Pippin v. Potomac Electric Power Co.
132 F. Supp. 2d 379 (D. Maryland, 2001)
Carven v. Hickman
763 A.2d 1207 (Court of Special Appeals of Maryland, 2000)
Lewis v. Weldotron Corp.
61 F. Supp. 2d 435 (D. Maryland, 1999)
Phillips v. Langston Corp.
59 F. Supp. 2d 696 (E.D. Michigan, 1999)
In Re Reese
194 B.R. 782 (D. Maryland, 1996)
Droney v. Droney
651 A.2d 415 (Court of Special Appeals of Maryland, 1995)
Rose v. Fox Pool Corp.
643 A.2d 906 (Court of Appeals of Maryland, 1994)
St. Louis v. Rockwell Graphic Systems, Inc.
605 N.E.2d 555 (Illinois Supreme Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
405 A.2d 326, 43 Md. App. 337, 1979 Md. App. LEXIS 381, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allentown-plaza-associates-v-suburban-propane-gas-corp-mdctspecapp-1979.