Allen & Gibbons Logging, Inc. v. Ball

756 P.2d 669, 91 Or. App. 624
CourtCourt of Appeals of Oregon
DecidedJune 22, 1988
Docket87-CV-0162; CA A45801
StatusPublished
Cited by8 cases

This text of 756 P.2d 669 (Allen & Gibbons Logging, Inc. v. Ball) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allen & Gibbons Logging, Inc. v. Ball, 756 P.2d 669, 91 Or. App. 624 (Or. Ct. App. 1988).

Opinion

*626 VAN HOOMISSEN, J.

Plaintiff appeals a judgment which denied it costs and attorney fees on its claim against defendants and denied its request for reformation or a set off and which awarded defendants damages on their counterclaim. We affirm in part and reverse and remand in part. 1

Defendants are in the business of buying and selling timber and hiring others to log it. Plaintiff is a logging company hired by defendants to log two of its purchases: “South Elkhorn” and “Acquired.” In November, 1984, defendant Lewis Ball (Ball) contacted Lawrence Gibbons regarding the Acquired sale, which consists of two units, one containing 92 percent of the sale and the other 8 percent. The first unit could be logged by tractor. However, the second had to be logged with skyline logging, which required additional equipment and manpower. Ball stated that defendants would pay $60 per thousand board feet logged from the sale, with an $8 per thousand deduction for logging previously done by another logger. Gibbons responded that he would have to see the areas first. They met later, and Ball gave Gibbons the sale prospectus. The men then drove to the area, which at the time was covered with four feet of snow. Ball showed Gibbons only the first unit. Gibbons agreed to take the job. The parties signed a contract which covered the entire Acquired area, not just the first unit, and did not provide for the $8 per thousand reduction for logging previously completed by another logger. Gibbons also contracted to log South Elkhorn.

Plaintiff logged through the end of 1984, but had to stop in January, 1985, because of deep snow. In June, 1985, Ball wrote plaintiff advising it that “the unit that you quit logging last winter has to be completed by July 1,1985, which is Unit No. 1.” Shortly thereafter, plaintiff finished logging that unit.

In September, 1985, Rand, defendants’ employe, called Gibbons and asked him to finish logging. Gibbons replied that he was not obliged to log the second unit. Rand said that the contract covered both. Gibbons continued to *627 assert that he was not obliged and said that all of his equipment was busy but that he would see if he could find a smaller logger to do the work. Gibbons testified that he suggested that Rand contact Peter & Sons. He also testified that he contacted Osborne of Triple O Logging and suggested that Osborne contact Ball. Osborne testified that he was looking for work in the area, that he discussed logging the second unit with Ball and that Ball suggested that Osborne get a prospectus on the sale, which he did. Osborn testified that he had tried several times to reach Ball after that and left messages, but Ball never called. Osborne also testified that he was willing and able to log the unit for $80 per thousand. It was never logged, and on March 30,1987, the United States Forest Service assessed defendants a $9,906.10 penalty.

Plaintiff completed logging South Elkhorn on October 1, 1985. It filed a complaint alleging that it had not been paid the full contract price for logging South Elkhorn. Defendants counterclaimed, alleging that plaintiff had failed to complete its contract on Acquired, resulting in defendants’ losing their profit and having to pay the penalty to the Forest Service. Plaintiff replied, seeking either reformation of the Acquired contract on the ground that it had not agreed to log both of the units or, in the alternative, a set off.

At trial, plaintiff moved to amend its pleadings to claim that interest should accrue on the damages due on South Elkhorn from October 1, 1985, rather than from January 1, 1986, as claimed in the amended complaint. Defendants did not object, and the court allowed the motion. Gibbons testified that he and Ball discussed only one unit of Acquired and the procedures and costs of logging only that unit, that he agreed only to do tractor logging for $60 per thousand board feet, that the June, 1985, letter regarding the work to be completed referred only to that unit and that the contract was intended to cover it. Ball testified that, although they only visited one unit, the contract was to log both units, that Gibbons saw the prospectus for the sale and attended a prework meeting that clearly dealt with both units and that Ball would not have made any other agreement because he could not have hired anyone else to log the second unit, because it was so small.

The trial court held:

“1.) The basis for determining moneys due under the *628 South Elkhorn contract was properly computed under the Oregon State Forestry Department Detail Certificate List (P05) submitted into evidence as Defendant’s [sic] Exhibit #106. Plaintiff is entitled to judgment against the defendants on plaintiffs amended complaint in the sum of $13,1355.92 [sic], with interest from October 1, 1985.
“2.) The contract between the parties (Exhibit 101) on Acquired Sale is clear and unambiguous. The summary of the prework meeting (Exhibit 112) as signed by the plaintiff clearly shows two units in the sale. Defendants are entitled to judgment against the plaintiff in the sum of $14,796.10. This is computed as follows.
$ 4,896.00 Loss of Profit
9,906.10 Damages per (Exhibit 108)
$14,796.10 to the Forest Service”

Defendants prepared a judgment 2 which included costs and disbursements. Plaintiff filed a motion for a new trial on the ground that the trial court did not rule on its request for a set-off or on its argument that the contract controlled the measure of damages. It also filed an objection to defendants’ cost bill, arguing that plaintiff is the prevailing party entitled to costs, disbursements and attorney fees, and submitted a cost bill. Defendants filed an objection to plaintiffs cost bill, stating that they, not plaintiff, prevailed. The trial court denied plaintiffs motion for a new trial but granted its objection to defendants’ cost bill. Plaintiff filed a new cost bill, and defendants again objected. The court ruled:

“Costs and disbursements are not awarded to either side. See the judgment dated August 28,1987.”

Plaintiff first contends that the trial court erred in denying its request to reform the contract to specify that plaintiff had to log only one unit. Before equity will reform a *629 written contract, the party seeking reformation must prove: (1) that there was an antecedent agreement to which the contract can be reformed; (2) that there was a mutual mistake or a unilateral mistake on the part of the party seeking reformation and inequitable conduct on the part of the other party; and (3) that the party seeking reformation was not guilty of gross negligence. Jensen v. Miller, 280 Or 225, 228-29, 570 P2d 375 (1977).

Because the terms in written instruments are presumed to be correct, requisites for reformation of writings must be proved by clear and convincing evidence. Koennecke v. Waxwing Cedar Prod,., 273 Or 639, 643, 543 P2d 669 (1975); Schaffner v. Oregon Central Credit Union,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cedartech, Inc. v. Strader
428 P.3d 961 (Court of Appeals of Oregon, 2018)
Stein v. Burt & Vetterlein, P.C.
946 P.2d 1168 (Court of Appeals of Oregon, 1997)
Lazaro v. State
941 P.2d 582 (Court of Appeals of Oregon, 1997)
Mendieta v. STATE, DIVISION OF STATE LANDS
941 P.2d 582 (Court of Appeals of Oregon, 1997)
Anderson v. Jensen Racing, Inc.
908 P.2d 339 (Court of Appeals of Oregon, 1995)
Meduri Farms, Inc. v. Robert Jahn Corp.
852 P.2d 257 (Court of Appeals of Oregon, 1993)
Klamath County 9-1-1 Communications Agency v. State
840 P.2d 751 (Court of Appeals of Oregon, 1992)
Bennett v. Minson
773 P.2d 813 (Court of Appeals of Oregon, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
756 P.2d 669, 91 Or. App. 624, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allen-gibbons-logging-inc-v-ball-orctapp-1988.