Allan Construction Co. v. United States

646 F.2d 487, 28 Cont. Cas. Fed. 81,291, 227 Ct. Cl. 193, 1981 U.S. Ct. Cl. LEXIS 206
CourtUnited States Court of Claims
DecidedApril 8, 1981
DocketNo. 433-78
StatusPublished
Cited by7 cases

This text of 646 F.2d 487 (Allan Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allan Construction Co. v. United States, 646 F.2d 487, 28 Cont. Cas. Fed. 81,291, 227 Ct. Cl. 193, 1981 U.S. Ct. Cl. LEXIS 206 (cc 1981).

Opinion

COWEN, Senior Judge,

delivered the opinion of the court:

Plaintiff (Allan Construction Co., Inc.), and Francis L. Bertling, as joint venturers, entered into a levee repair contract with the Corps of Engineers. During the first 2 years of the contract, progress payments were made payable to "Allan Construction Co., Inc. & Francis L. Bertling (Joint Venture).” About 2 years after the contract was executed, Francis L. Bertling (Bertling) was adjudicated to be bankrupt, following which two progress payments were made payable to "Allan Construction Co., Inc. & Daniel E. O’Cbnnell, Trustee in Bankruptcy for Francis L. Bertling (Joint Venture).” Those checks were mailed to the trustee, Whereupon plaintiff declared by letter that this action was a breach by the Government which effectively terminated the contract, but said that plaintiff would complete the contract on a quantum meruit basis. Plaintiff continued performance, completed the work, and was eventually paid all remaining moneys due under the contract. Plaintiff brought this action to recover the sum of $882,596, plus overhead and profit, as damages which plaintiff asserts it is entitled to recover on.a quantum meruit basis. For the [195]*195reasons to be discussed, we find, upon the facts before us, that if and to the extent that the defendant breached the contract, plaintiff has been paid the full amount it is entitled to recover as damages.

I.

The facts that are material to our decision are not in dispute. On June 30,1970, plaintiff and Francis L. Bertling, d/b/a/ Bertling Construction Company (Bertling), entered into a contract with the United States, acting through the Corps of Engineers (hereafter the Corps or defendant), for the performance of repair work on levees along the East Brazos River in Texas. On June 24, 1970, prior to the date the contract was executed, Henry S. Cherry, plaintiffs vice-president, wrote the Corps of Engineers, stating that if the contract was awarded "we will perform all work required according to the plans and specifications pertaining thereto.” On the same day, a substantially similar letter was submitted by Bertling. In the block on the contract form giving the name and address of the contractor, it was stated that it was a joint venture, and the signature page likewise designated the contractor as a joint venture. In the performance and payment bonds, the principal was designated as "Allan Construction Co., Inc. & Francis L. Bertling, Joint Venture.” The notice to proceed was issued on July 1,1970; it was sent to the joint venture at its post office address, and the receipt thereof was acknowledged by the written signature of Henry Cherry, plaintiffs vice-president.

In order to receive payment under the contract, it was necessary for the contractor to submit payment estimates and on 23 of these forms the contractor was again designated as a joint venture, and the payee was described as "Allan Construction Co., Inc. & Francis L. Bertling, (Joint Venture).” On Payment Estimates 1-14, covering the period from August 31 to September 30, 1971, Francis L. Bertling signed for the joint venture. On Estimates 15-23, covering the period from October 31, 1971 to June 23, 1972, Henry Cherry signed for the joint venture. These 23 progress payments totaled $1,062,777, which represented the earnings under the contract to June 23, 1972, less $21,673 [196]*196withheld as retained percentage. On Estimate No. 23, plaintiff represented that the contract was 84.29 percent complete.

Twenty-three checks representing the progress payments were made payable to "Allan Construction Co., Inc. & Francis L. Bertling (Joint Venture).” Five of those checks were picked up personally by Francis L. Bertling; the remainder were mailed to the post office address of the joint venture designated in the contract.

On October 4,1971, Bertling informed a representative of the Corps that due to his financial difficulties, plaintiff would take over the administration of the contract. On the same day, plaintiffs president informed defendant’s representative that Bertling would still be a part of the joint venture. For the next 9 months, work under the project continued without incident under plaintiffs management. As before, progress payments were made payable to plaintiff and Bertling as a joint venture, and this was done without complaint on plaintiffs part, up to and including the 23rd progress reporting period which ended in June 1972.

The event which precipitated the present controversy occurred on June 28,1972, when Bertling filed a petition in bankruptcy. He was adjudicated a bankrupt, and on July 11, 1972, notice of this fact was sent to defendant. Defendant then began extensive efforts to comply with its obligations to make progress payments due under the contract and at the same time to avoid violations of any requirements of the district court. Having learned that Daniel E. O’Connell had been appointed trustee in bankruptcy for Bertling, defendant made inquiry of his office and was advised that to the extent that payment would otherwise be made to Bertling, the payments should be made payable to the trustee. On September 29, 1972, defendant directed a letter to E. H. Patton, Jr., Referee in Bankruptcy, describing the executory contract the Corps had entered into with the joint venture, referring to the instruction it had received from the trustee’s office, and stating that defendant contemplated issuing a check payable to "Allan Construction Co., Inc. and Daniel E. O’Connell, Trustee in Bankruptcy for Francis L. Bertling [197]*197(Joint Venture),” to be mailed to the contractor’s address. The letter further requested that the referee advise whether this or some alternate action would be proper and also requested an early reply to avoid a delay in making the progress payment and the possibility of a breach of contract. On August 31,1972, Payment Estimate No. 24, signed by plaintiffs vice-president was submitted for the period from June 24, 1972 to August 31, 1972, in the amount of $15,678. On September 30, 1972, Payment Estimate No. 25 was submitted by plaintiffs vice-president for the period from September 1, 1972, to September 30, 1972, in the amount of $9,270. As in the past, the payment estimates provided for the amounts to be paid to the joint venture at the address designated in the contract.

On October 3, 1972, Arthur E. Moller, Referee in Bankruptcy, responded to defendant’s letter of September 29, 1972, with the statement that the trustee had been vested by operation of law with title to all of the property of Bertling, the bankrupt, "including all rights of action and interest in any executory contract.” The letter further stated that any payments becoming due to Bertling should be made to O’Connell, as trustee.

Believing that it was acting in compliance with the instructions of the referee, the defendant sent the trustee a letter on October 4, 1972, enclosing a check in the amount of $15,678 for Estimate No. 24, payable to the plaintiff and to the trustee. The check was accompanied by a letter stating that the plaintiff was conducting operations to complete the contract and that plaintiff would appreciate action by the trustee to identify and make available to plaintiff the proceeds of the check. On October 16, 1972, a check in the amount of $9,270, for Estimate No. 25, was sent to the trustee; and again it was made payable jointly to the plaintiff and to the trustee.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hansen Bancorp, Inc. v. United States
67 Fed. Cl. 411 (Federal Claims, 2005)
Fairbanks North Star Borough v. Tundra Tours, Inc.
719 P.2d 1020 (Alaska Supreme Court, 1986)
In Re By-Rite Distributing, Inc.
47 B.R. 660 (D. Utah, 1985)
L'Enfant Plaza Properties, Inc. v. United States
31 Cont. Cas. Fed. 71,681 (Court of Claims, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
646 F.2d 487, 28 Cont. Cas. Fed. 81,291, 227 Ct. Cl. 193, 1981 U.S. Ct. Cl. LEXIS 206, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allan-construction-co-v-united-states-cc-1981.