Algee v. Hren

2016 MT 166, 375 P.3d 386, 384 Mont. 93, 2016 Mont. LEXIS 603
CourtMontana Supreme Court
DecidedJuly 12, 2016
DocketDA 15-0688
StatusPublished
Cited by7 cases

This text of 2016 MT 166 (Algee v. Hren) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Algee v. Hren, 2016 MT 166, 375 P.3d 386, 384 Mont. 93, 2016 Mont. LEXIS 603 (Mo. 2016).

Opinion

JUSTICE SHEA

delivered the Opinion of the Court.

¶1 Carl Algee appeals an order of the Eighth Judicial District Court, Cascade County, granting partial summary judgment to Steven and Janet Hren. The summary judgment order dismissed all of Algee’s claims, while leaving some of the Hrens’ claims for further adjudication. The District Court certified the order as final pursuant to M. R. Civ. P. 54(b) to determine whether it correctly invoked the doctrine of laches to dismiss most of Algee’s claims. We address the following issue on appeal:

Whether the District Court properly applied the doctrine of laches to bar all of Algee’s claims not already barred by statutes of limitation.

¶2 We affirm.

PROCEDURAL AND FACTUAL BACKGROUND

¶3 Algee and the Hrens own adjoining properties. The Hrens’ property holds an easement that runs through Algee’s land, including along a creek embankment. In August of 2010, the Hrens began to build a road on their easement to access their property. On August 30, 2010, Algee filed a complaint with the Cascade Conservation District (CCD) regarding the Hrens’ easement road project. The CCD issued a Stop Work Order. The Hrens ceased construction, altered their plans, and submitted them to the CCD. The CCD further modified the plans before issuing the necessary permit (310 Permit) to continue road *95 construction. On September 21,2010, Algee received a letter informing him of the approved plan and the issued 310 Permit. The Hrens completed the road along their easement in October 2010, at a cost of approximately $40,000.

¶4 On August 21, 2013, Algee sued the Hrens over the easement. Algee’s Complaint alleged, in part, that the Hrens destroyed an access trail when constructing the easement road in 2010. On the same date, Algee also filed a Notice of Lis Pendens. The Lis Pendens prevented the Hrens from closing on the sale of their property, which was scheduled for August 26, 2013. On October 11, 2013, the Hrens filed their Answer, Counterclaim, and a Request for a Permanent Injunction. On April 9,2015, the Hrens filed Defendants’ Motion for Partial Summary Judgment on Plaintiffs Claims. On April 20, 2015, the Hrens filed an Amended Answer and Counterclaim through an unopposed M. R. Civ. P. 15(a)(2) motion. The Amended Answer included a Doctrine of Laches affirmative defense. 1

¶5 On July 28, 2015, the District Court entered its Order Regarding Defendants’ Motion for Summary Judgment and Plaintiffs Cross-Motion for Partial Summary Judgment on Attorney’s Fees Issue. The District Court held that Algee’s Trespass and Negligence claims were barred by the statutes of limitation, and Algee’s remaining claims were barred by laches. Algee does not appeal from the District Court’s order applying the statutes of limitation, but does challenge the Court’s ruling with respect to laches. Algee appeals.

STANDARD OF REVIEW

¶6 The parties dispute the applicable standard of review. Algee argues that the District Court’s order should be reviewed de novo because the appeal is taken from a grant of summary judgment. The Hrens argue that the standard is whether the District Court abused its discretion, relying on Williard v. Campbell Oil Co., 77 Mont. 30, 248 P. 219, 224 (1926). Regarding the appropriate standard of review to apply in this case, Williard is inapposite because it dealt with an appeal from *96 a bench trial. Williard, 77 Mont. at 33, 248 P. at 220. We have consistently held that an order on summary judgment is reviewed de novo, applying the same criteria as the district court. Denturist Ass’n of Mont. v. State, 2016 MT 119, ¶ 7, 383 Mont. 391, 372 P.3d 466 (citing Lorang v. Fortis Ins. Co., 2008 MT 252, ¶ 36, 345 Mont. 12, 192 P.3d 186). Under M. R. Civ. P. 56(c), summary judgment is appropriate where there is a complete absence of genuine issues of material fact, and the moving party is entitled to judgment as a matter of law. Lorang, ¶ 37.

DISCUSSION

¶7 Whether the District Court properly applied the doctrine of laches to bar all of Algee’s claims not already barred by statutes of limitation.

¶8 The doctrine of laches is an equitable remedy—asserted as an affirmative defense under M. R. Civ. P. 8(c)(1)—“by which a court denies relief to a claimant who has unreasonably delayed or been negligent in asserting a claim, when the delay or negligence has prejudiced the party against whom relief is sought.” Anderson v. Stokes, 2007 MT 166, ¶ 19, 338 Mont. 118, 163 P.3d 1273 (citing Montanans for Justice v. State ex rel. McGrath, 2006 MT 277, ¶ 23, 334 Mont. 237, 146 P.3d 759, and Cole v. State ex rel. Brown, 2002 MT 32, ¶ 24, 308 Mont. 265, 42 P.3d 760). To determine whether laches applies, a court must find: (1) the party against whom the defense is asserted lacked diligence in asserting a claim; and (2) that lack of diligence resulted in prejudice to the party asserting the defense. Wicklund v. Sundheim, 2016 MT 62, ¶ 40, 383 Mont. 1, 367 P.3d 403 (citations omitted). The doctrine of laches’ purpose is to “discourage stale demands by the court refusing to interfere where there has been gross laches in prosecuting rights, or where long acquiescence in assertion of adverse rights has occurred.” Montanans for Justice, ¶ 25 (quoting Castillo v. Franks, 213 Mont. 232, 241, 690 P.2d 425, 429 (1984)). Although time is a factor when determining laches’ elements, “[Haches is not a mere matter of elapsed time, but rather, it is principally a question of the inequity of permitting a claim to be enforced.” Cole, ¶ 25 (citations omitted).

¶9 One way by which a lack of diligence may be demonstrated is when a claimant contemporaneously believes another is violating his or her right, yet the claimant allows the alleged unlawful act to finalize before objecting to such action. See Cole, ¶¶ 27-30; Wagner v. Woodward, 2012 MT 19, ¶¶ 29, 33, 363 Mont. 403, 270 P.3d 21. In Cole, we held that laches barred plaintiffs from challenging the process by *97 which voters approved an initiative that imposed term limits on ten state and federal offices. Cole, ¶¶ 1, 42. The plaintiffs filed suit more than nine years after the challenged election. Cole, ¶ 17. We found that the plaintiffs contemporaneously knew of the election’s alleged deficiencies and rejected the argument that the plaintiffs’ injury was only realized nine years later when the public officials who were subject to the term limits could not stand for reelection. Cole, ¶¶ 27-30.

¶10 In Wagner, we held that laches applied when the plaintiffs failed to raise their claim before or during the defendant’s construction of a deck and fences on a lot adjacent to the plaintiffs’ land because the plaintiffs knew, or should have known, during construction that the defendant was violating the lot’s restrictive covenants.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Lindemulder
2022 MT 119 (Montana Supreme Court, 2022)
Carter v. Badrock RFD
2021 MT 28 (Montana Supreme Court, 2021)
McCann v. McCann
2018 MT 207 (Montana Supreme Court, 2018)
In Re Teton Coop. Reservoir Co.
2018 MT 66 (Montana Supreme Court, 2018)
Teton Coop v. Farmers Coop.
2018 MT 66 (Montana Supreme Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
2016 MT 166, 375 P.3d 386, 384 Mont. 93, 2016 Mont. LEXIS 603, Counsel Stack Legal Research, https://law.counselstack.com/opinion/algee-v-hren-mont-2016.