Teton Coop v. Farmers Coop.

2018 MT 66
CourtMontana Supreme Court
DecidedApril 3, 2018
Docket16-0322
StatusPublished

This text of 2018 MT 66 (Teton Coop v. Farmers Coop.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Teton Coop v. Farmers Coop., 2018 MT 66 (Mo. 2018).

Opinion

04/03/2018

DA 16-0322 Case Number: DA 16-0322

IN THE SUPREME COURT OF THE STATE OF MONTANA

2018 MT 66

TETON COOPERATIVE RESERVOIR COMPANY,

Claimant and Appellant,

LOWER TETON JOINT OBJECTORS,

Objector and Appellee,

FARMERS COOPERATIVE CANAL CO. and TETON COOPERATIVE CANAL COMPANY,

Objectors, Appellees, and Cross-Appellants.

APPEAL FROM: Montana Water Court, Case No. 41O-84 Honorable Douglas Ritter, Water Judge

COUNSEL OF RECORD:

For Appellant:

Holly Jo Franz, Ryan McLane, Franz & Driscoll, PLLP, Helena, Montana

For Appellee Farmers Cooperative Canal Co.:

Michael J.L. Cusick, Moore, O’Connell & Refling, PC, Bozeman, Montana

For Appellee Teton Cooperative Canal Company:

John E. Bloomquist, Bloomquist Law Firm, P.C., Helena, Montana

Submitted on Briefs: January 17, 2018 Decided: April 3, 2018

Filed:

__________________________________________ Clerk Chief Justice Mike McGrath delivered the Opinion of the Court.

¶1 Teton Cooperative Reservoir Company (Teton Reservoir) appeals an April 27,

2016 order of the Montana Water Court in Case 41O-84, adjudicating Teton Reservoir’s

water rights. Teton Cooperative Canal Company (Teton Canal) and Farmers Cooperative

Canal Company (Farmers) cross-appeal. We affirm.

¶2 We restate the issues on appeal as follows:

Issue One: Whether the Water Court erred in determining that Teton Reservoir’s 1902 Notice of Appropriation was valid.

Issue Two: Whether the Water Court erred by applying the equitable doctrine of laches to Teton Reservoir’s 1902 Notice of Appropriation.

Issue Three: Whether the Water Court erred in decreeing Teton Reservoir an annual volume totaling 60,000 acre feet for storage in the Bynum Reservoir.

Issue Four: Whether the Water Court erred in refusing to limit Teton Reservoir’s wintertime diversions to one-half of the available water in the Teton River.

FACTUAL AND PROCEDURAL BACKGROUND

¶3 Teton Reservoir is one of four irrigation companies located on the Teton River.

Teton Reservoir was incorporated in May 1906, for the purposes of acquiring,

developing, and improving the Bynum Reservoir and to complete one or more diversion

canals to take water from the Teton River to the reservoir. Teton Reservoir has acquired

four water rights. Teton Reservoir filed a Statement of Claim for each of its four water

rights in the current water right adjudication process for the Teton River Basin.

However, the only water right claim contested from the Water Court’s Order is the claim

based on the 1902 Notice of Appropriation (1902 Notice) filed by Donald Bradford

(Bradford).

2 ¶4 Bradford filed a Notice of Appropriation claiming 3,000 cfs from the Teton River

on July 3, 1902. The stated purpose of the 1902 Notice was “for the purpose of irrigating

and reclaiming lands lying in said Teton County.” The 1902 Notice did not identify a

reservoir. Shortly thereafter, Bradford commissioned a survey of the project. Engineer

Walter Mathews (Mathews) performed the survey and on November 29, 1902, Mathews

filed his survey report. Mathews identified a point of diversion, a reservoir with a 69,500

acre feet capacity, and surveyed over twenty-nine miles of distribution canals. Once

Mathews’s survey was approved by the Government Land Office (GLO), Bradford

acquired the rights of way and tried to obtain funding for the project to develop a canal

and reservoir system.

¶5 By 1906, Bradford was unable to obtain funding to develop the reservoir and canal

system and conveyed the 1902 Notice and the rights of way to the Wagnild group. The

Wagnild group incorporated Teton Reservoir in May 1906. Teton Reservoir obtained the

funding to develop the Bynum reservoir and canal system (Bynum System). Between

1906 and 1909 construction on the Bynum System progressed. In 1907, the original

diversion point was completed. In 1909, Teton Reservoir began to pursue a potential

Carey Act project to acquire more land for irrigation.1 Pursuing the Carey Act project led

to internal conflict among Teton Reservoir’s shareholders. Teton Reservoir’s

shareholders were in direct conflict with one another until 1914. Despite the internal 1 The Carey Act was passed in 1894 by the federal government to promote settlement and irrigation of public lands in the West. Specifically, the Act provided a grant of up to one million acres of federal land to each western state “free of cost” if the State could cause such lands to be “irrigated, reclaimed, occupied and not less than twenty acres of each one hundred and sixty acre tract cultivated by actual settlers.” 43 U.S.C. § 641.

3 conflicts, Teton Reservoir continued to make progress on the Bynum System. In 1910

and 1911, several engineers discovered problems with the design and construction of the

dam that required resolving before Teton Reservoir could divert any water. By 1915,

Teton Reservoir had relocated the diversion point because the original diversion point

was in a poor location on the river, and it had resolved the dam’s design problems. The

1962 Teton County Water Resource survey indicated that Strabane Gage Station started

diverting floodwaters to the Bynum Reservoir in 1918.

¶6 In 1919, GLO Commissioner Tillman inspected the reservoir site and questioned

the proposed Carey Act project. The Water Court found that the inspection marked a

shift by Teton Reservoir to return to the original plan to develop the Bynum System and

abandon the Carey Act project. Teton Reservoir’s board officially abandoned the Carey

Act project in 1925 by resolution. Due to Tillman’s inspection, local irrigators began to

promote formation of the Bynum Irrigation District (BID). In 1920, BID was established.

The BID commissioned an engineer to evaluate the status of the Bynum System.

Engineer S.B. Robbins issued his report on November 10, 1920, providing

recommendations to improve the Bynum System so that it could divert and store water to

its fullest capacity. However, BID could not finish the Bynum System until it received

approval to sell bonds. Between 1920 and 1925, Teton Reservoir maintained the Bynum

System. In 1925, BID received approval to sell bonds, bought eighty percent of Teton

Reservoir’s stock, and began implementing Engineer Robbins’ recommendations. By

1927, Teton Reservoir’s current point of diversion, intake canal, reservoir, and

distribution canals were in place. When completed, the Teton Reservoir’s diversion canal

4 capacity was 1,000 cfs and the Bynum Reservoir had a capacity between 85,000 and

90,000 acre feet.2

¶7 During that period, Teton Canal developed limited water storage in the Glendora

Reservoir under its 1890 Notice of Appropriation. Teton Coop. Canal Co. v. Teton Coop.

Reservoir Co., 2015 MT 344, 382 Mont. 1, 365 P.3d 442 (hereinafter Teton Canal I). In

1936, Teton Canal expanded its water storage capacity with the development of the

Eureka Reservoir. Teton Canal again expanded the Eureka Reservoir in 1947 and 1957.

Teton Canal I, ¶ 14. In 2015, this Court determined that the Eureka Reservoir use could

not relate back to Teton Canal’s 1890 Notice and must be given a separate priority date.

Teton Canal I, ¶¶ 55, 57. We affirmed the Water Court’s determination that the priority

date for the Eureka Reservoir is December 7, 1936. Teton Coop. Canal Co. v. Teton

Coop.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McDonald v. State
722 P.2d 598 (Montana Supreme Court, 1986)
Hunter v. Rosebud County
783 P.2d 927 (Montana Supreme Court, 1989)
Larson v. Undem
805 P.2d 1318 (Montana Supreme Court, 1990)
Cole v. State Ex Rel. Brown
2002 MT 32 (Montana Supreme Court, 2002)
Anderson v. Stokes
2007 MT 166 (Montana Supreme Court, 2007)
Whitcomb v. HELENA WATER WORKS COMPANY
444 P.2d 301 (Montana Supreme Court, 1968)
Nelson v. Brooks
2014 MT 120 (Montana Supreme Court, 2014)
Skelton Ranch, Inc. v. Pondera County Canal & Reservoir Co.
2014 MT 167 (Montana Supreme Court, 2014)
Marks v. 71 Ranch, LP
2014 MT 250 (Montana Supreme Court, 2014)
Teton Co-Op Canal Co. v. Teton Co-Op Reservoir Co.
2015 MT 344 (Montana Supreme Court, 2015)
Wicklund v. Sundheim
2016 MT 62 (Montana Supreme Court, 2016)
Curry v. Pondera County Canal & Reservoir Co.
2016 MT 77 (Montana Supreme Court, 2016)
Federal Land Bank v. Morris
116 P.2d 1007 (Montana Supreme Court, 1941)
Algee v. Hren
2016 MT 166 (Montana Supreme Court, 2016)
Teton Coop Canal Co. v. Teton Coop Reservoir Co.
2018 MT 20 (Montana Supreme Court, 2018)
In Re Teton Coop. Reservoir Co.
2018 MT 66 (Montana Supreme Court, 2018)
Bailey v. Tintinger
122 P. 575 (Montana Supreme Court, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
2018 MT 66, Counsel Stack Legal Research, https://law.counselstack.com/opinion/teton-coop-v-farmers-coop-mont-2018.