Albert Brauer v. Republic Steel Corporation

460 F.2d 801
CourtCourt of Appeals for the Tenth Circuit
DecidedJuly 7, 1972
Docket71-1258
StatusPublished
Cited by8 cases

This text of 460 F.2d 801 (Albert Brauer v. Republic Steel Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Albert Brauer v. Republic Steel Corporation, 460 F.2d 801 (10th Cir. 1972).

Opinion

BREITENSTEIN, Circuit Judge.

In this diversity action, brought in the United States District Court for the District of Kansas and tried to a jury, plaintiffs-appellees had judgment for $273,736.00 against defendant-appellant, Republic Steel Corporation, on claims of breach of warranty and negligence arising out of the sale of pipe in Oklahoma for use in Kansas.

Plaintiffs, owners of adjacent oil leases in Kansas, entered into a unit operating agreement for the secondary recovery of oil by a waterflood project. A waterflood project is a process for the recovery of additional oil from a field whose primary deposits have been depleted. Pressurized salt water is injected through pipes into oil-bearing formations to raise the pressure and make recoverable otherwise unobtainable oil deposits. A detailed description of waterflooding appears in Tidewater Oil Company v. Jackson, 10 Cir., 320 F.2d 157, cert. denied 375 U.S. 942, 84 S.Ct. 347, 11 L.Ed.2d 273.

Brauer was designated unit operator and retained C.R.A., Inc., to do the engineering work. On C.R.A.’s recommendation, Brauer placed an order with McAdams Pipe & Supply Company of Bristow, Oklahoma, a supplier for Republic, for the purchase of Republic pipe. The pipe was delivered in July-August, 1963, and water was first injected on October 1, 1963. Breaks or leaks in the pipeline began in the spring of 1964 and continued in increasing intensity until it was necessary to replace the pipe. The breaks were along the seams of the pipe.

Plaintiffs say that the failures were caused by the particular nature of the weld seam in that the electric weld caused the microstructure of the weld to differ from that of the surrounding pipe thereby making the weld anodic to the rest of the pipe. There was evidence that the anodic character of the weld seam could have been rectified by a process known as normalizing or annealing the pipe after it had been welded. Republic contends that the pipe failures were due to the corrosive nature of the soil in which the pipe was buried.

The breach of warranty claims are based on representations made by Myers, a sales representative of Republic, to *803 C.R.A. engineers in April, 1963. The negligence claim is based on the failure to normalize or anneal the pipe after the seam had been welded.

The first question is whether the action is barred by the applicable statutes of limitation. The pipe was purchased in Oklahoma in May, 1963, and delivered to the project in Kansas about two months later. The first use was in October and the first leaks occurred in the spring of 1964. In answer to a special interrogatory the jury found “that the date on which plaintiffs first knew or should have known that the pipe in question was not fit for the purpose for which it was sold, was January, 1965.” The action was brought by Brauer on October 7, 1966, and alleged breach of warranty. By an amended complaint filed on August 1, 1967, Olson and C.R.A. were brought in as additional plaintiffs and the allegations were expanded to include the claim of negligence.

The Oklahoma version of the Uniform Commercial Code has a five-year statute of limitation on contract actions, including warranty claims. 12A O.S.A. § 2-725. Although Kansas had adopted the Uniform Commercial Code, the claims with which we are concerned arose prior thereto and must be determined under the then law. The effective Kansas statutes provided a three-year limitation on warranties such as found in this case, 4 K.S.A. (1964) § 60-512, and a two-year limitation on negligence actions, 4 K.S.A. (1964) 60-513. The trial court held that the action was not barred.

The first problem is whether the statutory limitations of Kansas, the state of the forum, or of Oklahoma, the state where the contract of sale was made, apply. In a diversity case, the federal court follows the conflict principles of the forum state. Klaxon Company v. Stentor Electric Manufacturing Co., Inc., 313 U.S. 487, 496, 61 S.Ct. 1020, 85 L.Ed. 1477, and Smith v. Greyhound Lines, Inc., 10 Cir., 382 F.2d 190, 192. Kansas has held that the law of the forum governs the application of statutes of limitation, unless some exception is provided. Green v. Kensinger, 199 Kan. 220, 429 P.2d 95, 98. Republic argues that there is no exception, and for purposes of this appeal we will assume that Kansas would apply its statutes of limitation. In any event, the warranty claims are clearly not barred under the five-year Oklahoma statute.

We turn to the Kansas three-year statute. It does not say when an action accrues and limitations begin to run. In reliance on Freeto Construction Co. v. American Hoist & Derrick Co., 203 Kan. 741, 457 P.2d 1, Republic argues that the period began to run at the time of delivery of the pipe in July-August, 1963, and, hence, an action brought in October, 1966, was barred. Although Freeto says that a warranty can be breached at the time of delivery, the Kansas Supreme Court pointed out that the Freeto record contained nothing that suggested a prospective or continuing warranty. Ibid, at 4-5. In Freeto, like the case at bar, the cause of action arose before Kansas adopted the Uniform Commercial Code. The Kansas court noted this and said that the UCC provisions found in K.S.A. 84-2-725 were “substantially in accordance with decisions of this court.” Ibid, at 6. Section 84-2-725(2) provides that

“ * * * where a warranty explicitly extends to future performance of the goods and discovery of the breach must await the time of such performance the cause of action accrues when the breach is or should have been discovered.”

In the case at bar the representations which form the base of the warranty claims went to durability. They were of a prospective or continuing nature. In our opinion under preUCC law Kansas would recognize a prospective warranty and an action for breach thereof accrues when the breach is or should have been discovered. Substantial evidence sustains the jury’s answer to the special interrogatory that the date when the plaintiffs first knew, or should have known, that the pipe was not fit for the purpose for which it was *804 sold was January, 1965. The original complaint was filed on October 7, 1966, well within the three-year period.

On the negligence claim the parties agree that the two-year Kansas statute applies. 4 K.S.A. (1964) § 60-513 provides :

« * * * jf the fact of injury is not reasonably ascertainable until some time after the initial act, then the period of limitation shall not commence until the fact of injury becomes reasonably ascertainable to the injured party, * *

Republic says that the statute began to run in June, 1964, when “major” leaks occurred.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Collins v. Wal-Mart, Inc.
245 F.R.D. 503 (D. Kansas, 2007)
Penn Millers Insurance Ex Rel. S & C Construction Co. v. United States
472 F. Supp. 2d 705 (E.D. North Carolina, 2007)
Greenhorn v. Marriott International, Inc.
258 F. Supp. 2d 1249 (D. Kansas, 2003)
Menne v. Celotex Corp.
722 F. Supp. 662 (D. Kansas, 1989)
FirstMiss, Inc. v. United States
7 Ct. Int'l Trade 52 (Court of International Trade, 1984)
Voth v. Chrysler Motor Corporation
545 P.2d 371 (Supreme Court of Kansas, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
460 F.2d 801, Counsel Stack Legal Research, https://law.counselstack.com/opinion/albert-brauer-v-republic-steel-corporation-ca10-1972.