Alabama v. United States Environmental Protection Agency

871 F.2d 1548
CourtCourt of Appeals for the Eleventh Circuit
DecidedApril 18, 1989
DocketNos. 88-7677, 89-7024
StatusPublished
Cited by31 cases

This text of 871 F.2d 1548 (Alabama v. United States Environmental Protection Agency) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alabama v. United States Environmental Protection Agency, 871 F.2d 1548 (11th Cir. 1989).

Opinion

JOHNSON, Circuit Judge:

This appeal arises from the issuance of a temporary injunction preventing the shipment of soil contaminated with PCBs and other toxic wastes from the Geneva Industries, Inc., toxic waste site in South Houston, Texas, to Chemical Waste Management (CWM)’s toxic waste treatment facility in Emelle, Alabama. The State of Alabama and its governor, attorney general, and head of the department of environmental management, acting in their capacities as private citizens, filed suit in federal district court seeking to enjoin shipment of these wastes. Plaintiffs asserted both constitutional claims and claims based on the Comprehensive Environmental Response, Compensation, and Liability Act, 42 U.S.C. A. § 9601 et seq. (CERCLA).

The district court issued a preliminary injunction halting EPA’s participation in the remedial action selected to clean up the Geneva Industries site, and the EPA, along with intervenors State of Texas and CWM, appealed. During the pendency of the appeal, the district court granted partial summary judgment to plaintiffs enjoining the EPA from implementing its remedial action plan to clean up the Geneva Industries site until plaintiffs have had the opportunity to comment on the remedial action plan. This Court granted defendants’ motion to consolidate the appeal from the preliminary injunction with the appeal from the grant of summary judgment. We reverse the grant of preliminary injunction, reverse the grant of summary judgment, dissolve the permanent injunction, and dismiss this case for lack of subject matter jurisdiction.

I. FACTS

In 1983, Texas submitted the site of Geneva Industries, Inc.’s former petrochemical plant in South Houston, Texas, to be included on the National Priorities List for cleanup by the EPA pursuant to CERCLA. The site is contaminated with polychlorinat-ed biphenyls (PCBs) and other toxic chemicals. The EPA placed this site on the National Priorities List, where it ranked number 37 out of over 700 sites listed. In 1983 and 1984, EPA conducted a planned removal1 to stabilize the site and to reduce the immediate health and safety risks of the contamination to residents in the area.

In 1984, the Texas Department of Water Resources, the state agency operating in cooperation with the EPA to clean up the site, contracted for a Remedial Investigation and Feasibility Study. This is a preliminary step in cleaning up a hazardous waste site under CERCLA. The contractor evaluated alternative remedial action plans and presented them to the state. In 1986, [1552]*1552the Feasibility Study describing the alternatives was released for public comment and review. A public meeting was held in May 1986, and the public comment period was held open until June 10, 1986. On September 18, 1986, the Regional Director of the EPA issued the Record of Decision memorializing the alternative chosen to clean up the Geneva Industries site. The EPA selected offsite disposal of the hazardous wastes. At the time, there were only a limited number of treatment facilities in the United States capable of handling these toxic wastes. Among those facilities was CWM’s hazardous waste treatment facility in Emelle, Alabama.

There are two separate federal statutes regulating the Emelle, Alabama, facility. The Toxic Substances Control Act, 15 U.S. C.A. § 2601 et seq. (TSCA), regulates the handling, storage, and disposal of wastes contaminated with PCBs. The Resource Conservation and Recovery Act, 42 U.S. C.A. § 6901 et seq. (RCRA), regulates other hazardous wastes. CWM’s Emelle, Alabama, facility is licensed under both federal statutes and under complementary state regulations2 to handle the wastes located at the Geneva Industries toxic waste site. The TSCA and the RCRA ensure that CWM’s toxic waste storage and treatment facility poses the least possible risk to human health and safety.

The TSCA establishes a regulatory framework for the safe handling and disposal of certain highly toxic wastes. Regulations adopted pursuant to the TSCA control the storage and disposal of PCBs. See 40 C.F.R. § 761.75(b)(8). The regulations establish very specific soil, hydrological, geological, and topographical requirements for facilities that dispose of wastes contaminated with PCBs. 40 C.F.R. § 761.75(b)(1), (2), (3), (4), and (5). The regulations also provide for monitoring the groundwater in the vicinity of the chemical waste landfill. 40 C.F.R. § 761.75(b)(6). The permit application process ensures that licensed treatment facilities comply with these requirements. 40 C.F.R. § 761.75(c)(3).

The RCRA establishes a framework for regulating the storage and disposal of hazardous wastes in general. Operators of hazardous waste treatment, storage, and disposal facilities must comply with detailed operating regulations. 42 U.S.C.A. § 6924; see generally 40 C.F.R. Part 264. This includes stringent permit application requirements and regulations. See 42 U.S. C.A. § 6925; see generally 40 C.F.R. Part 270. The regulations promulgated pursuant to the RCRA ensure that facilities disposing of hazardous wastes do so in a manner consistent with eliminating health and environmental risks caused by the hazardous wastes. A permit is valid only for a maximum term of ten years, 40 C.F.R. § 270.50(a), and each permit for a land disposal facility is reviewed after five years and is subject to modification at that point. 40 C.F.R. § 270.50(d). A permit may be terminated for noncompliance with any of its conditions, 40 C.F.R. § 270.43(a)(1), for failure to disclose material information or misrepresentation of material facts, 40 C.F. R. § 270.43(a)(2), or if the activity “endangers human health or environment” and can be regulated only through modification or termination of the permit. 40 C.F.R. § 270.43(a)(3).

CWM’s Emelle, Alabama, hazardous waste treatment facility received permits under both the TSCA and the RCRA. This facility thus has complied with elaborate federal regulations designed to ensure the safe disposal of hazardous wastes, including wastes contaminated with PCBs. To the extent these federal regulations can and do provide for the safe treatment and disposal of toxic wastes, CWM’s Emelle, Alabama, facility poses no threat to the health and safety of the residents of [1553]*1553Emelle or to other Alabama residents.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Group Management Corp.
N.D. Georgia, 2022
Camillus Clean Air Coalition v. Honeywell International, Inc.
947 F. Supp. 2d 208 (N.D. New York, 2013)
Zinnia I. Chen v. Siemens Energy Incorporated
467 F. App'x 852 (Eleventh Circuit, 2012)
State of New Mexico v. General Electric
467 F.3d 1223 (Tenth Circuit, 2006)
Bischoff v. Osceola County, FL
222 F.3d 874 (Eleventh Circuit, 2000)
T Backs Club, Inc. v. Seaton
84 F. Supp. 2d 1317 (M.D. Alabama, 2000)
United States v. City of Fort Lauderdale
81 F. Supp. 2d 1348 (S.D. Florida, 1999)
Clinton Cty Comm v. EPa
Third Circuit, 1997
United States v. Princeton Gamma-Tech, Inc.
31 F.3d 138 (Third Circuit, 1994)
Hanford Downwinders Coalition, Inc. v. Dowdle
841 F. Supp. 1050 (E.D. Washington, 1993)
United States v. Akzo Coatings of America, Inc.
949 F.2d 1409 (Sixth Circuit, 1991)
Chemical Waste Management, Inc. v. Templet
770 F. Supp. 1142 (M.D. Louisiana, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
871 F.2d 1548, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alabama-v-united-states-environmental-protection-agency-ca11-1989.