Akzona, Inc. v. Southern Railway Co.

334 S.E.2d 759, 314 N.C. 488, 1985 N.C. LEXIS 2008
CourtSupreme Court of North Carolina
DecidedOctober 1, 1985
Docket628PA83
StatusPublished
Cited by17 cases

This text of 334 S.E.2d 759 (Akzona, Inc. v. Southern Railway Co.) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Akzona, Inc. v. Southern Railway Co., 334 S.E.2d 759, 314 N.C. 488, 1985 N.C. LEXIS 2008 (N.C. 1985).

Opinion

EXUM, Justice.

This case presents the issue of whether the flooding of downstream property caused by the erosion of an embankment, lawfully and purposely constructed across a stream, constitutes a taking as the trial court instructed the jury. We hold that this situation does not constitute a taking and the trial court erred in its instructions. Accordingly, we vacate the trial court’s judgment and remand the case for a new trial.

I.

Defendant, Southern Railway Company (Railroad), owns, maintains, and operates a railroad line which runs from Asheville to Murphy in North Carolina. This railroad track crosses over Pole Creek at a point just west of Asheville. At that junction the railroad track lies generally in an east-west direction, while Pole Creek flows generally north-south. Pole Creek does not approach its intersection with the railroad track in a perpendicular fashion, but rather approaches it at an acute angle.

Approximately 1,000 feet south of this intersection, Pole Creek empties into Hominy Creek, which flows generally west- *490 east. Approximately one and one-half miles downstream, Hominy Creek passes by the American Enka Plant and runs through lands owned by plaintiff, Akzona, Inc. Akzona owns and operates the Enka Plant.

In times of heavy rainfall, this basin is susceptible to flooding. In the 1940’s Akzona constructed a 12- to 15-foot dike between its plant and Hominy Creek. The dike, designed to provide some measure of protection to the Enka Plant from flooding, had four openings or passageways, each designed to permit access to the Enka Plant. Gate A allowed State Road 112 to pass through the dike; Gate B was located at the filter plant; Gates C and D permitted the railroad spurs into the plant. These gates could be closed to protect the plant by forming a solid wall between it and Hominy Creek but permission was required from the State Highway Department before Gate A could be closed.

Prior to 1956 Railroad passed its track across Pole Creek across an open trestle. This structure provided a large area through which the water in Pole Creek might pass. It also accommodated the natural creek bed intersecting the path of the railroad at an acute angle.

Railroad altered the Pole Creek crossing in 1956 by placing under the trestle three culvert pipes, each seven feet in diameter. These pipes, placed side-by-side at the extreme eastern end of the trestle, were perpendicular to the railroad tracks. In order for these culverts to accommodate the flow of Pole Creek, the natural flow and direction of the creek had to be altered. Railroad left the trestle supports in place and filled in the area beneath the trestle with gravel and dirt. When the trestle was filled to the level of the rails, some twenty feet above the creek bed, it formed a solid earthen wall across Pole Creek except for the three seven-foot culverts. The embankment, made of gravel and fill, had no shielding or spilling-type covering to prevent erosion should water overtop it. The embankment was covered with grass and vegetation.

After the embankment was created in 1956, water occasionally backed up behind it to form a pond. Some flooding occurred upstream. Blanche Young, a local resident and an upstream landowner, complained to Railroad about the flooding.

*491 After a heavy rainfall in April 1977, Pole Creek began to rise. Water backed up behind the embankment and Pole Creek came out of its banks. Water rose to a level five feet above the top of the culverts. Considerable flooding resulted to upstream property.

After the flooding, Henry VeHaun, coordinator of the Buncombe County Civil Preparedness Agency, corresponded with J. W. DeValle, Railroad’s Chief Engineer for Bridges, concerning the flooding at the Pole Creek crossing. Railroad sent John Maclin, a graduate engineer, to investigate the waterway at Pole Creek. Using customary engineering standards, Maclin calculated the size of the waterway area needed to carry off water at the embankment. In his report Maclin noted: (1) he was informed that high water had occurred at this location three or four times within the last two years; (2) the culverts do not have the capacity to carry the rainfall run-off from a storm the size of the 4 April 1977 storm; (3) an examination of the vegetation indicated that the water crested during that storm at approximately five feet above the top of the culverts; (4) significant sources of debris existed upstream which might be carried by floodwaters and block the culverts; and (5) United States Highway 19-23, which crosses Pole Creek about 500 feet upstream of the embankment, uses a highway bridge with a larger waterway that was still inadequate to carry off peak flows of Pole Creek, even though this bridge was above the sources of debris.

In accordance with Railroad’s standard procedure, a report of the study was sent to DeValle. Based upon this report, DeValle reported in writing to his superiors that the culverts were inadequate to carry peak flows of the creek and recommended that the culverts be removed and the embankment replaced with a bridge. Railroad began plans to construct a bridge across Pole Creek. On 3 June 1977 several upstream landowners sued Railroad in a single action unrelated to the present case. They alleged that because of the inadequacy of the culverts and the diverting of the natural flow of Pole Creek, their property had been damaged. These plaintiffs alleged damages resulting from three different floods which occurred on 23 September 1975, 22 May 1976, and 5 April 1977. After these actions were initiated, Railroad discon *492 tinued its plans to remove the embankment and replace it with a bridge. 1

In late October and early November 1977, periodic rainfall fell in western North Carolina. On 5 November 1977 heavy rains began to fall in the Hominy Creek basin. The water in Pole Creek backed up behind the embankment. By 12:10 a.m. on 6 November 1977, the water had already come out of Pole Creek’s banks; it overflowed the State Road upstream of the embankment.

At 12:20 a.m. that same day, Enka’s flood crews were called to the plant to initiate a flood control procedure. They began the procedure for closing the various gates, which included digging out asphalt plugs in the holes which had been drilled into the highway. 2 The crews cleared only a small number of the holes before Hominy Creek came out of its banks and reached waist level at approximately 1:30 a.m. The crew was forced to evacuate the area near Gate A without having closed the gate. Enka was in full operation when the waters poured through Gate A. Enka was flooded to a depth of fifty-nine and one-half inches.

Akzona initiated this action alleging an unreasonable interference with surface waters, negligent design and modification of the embankment, inverse condemnation through the design of the embankment, trespass, and the creation of a dangerous instrumentality. At the beginning of the trial, Judge Allen allowed Akzona’s motion to amend its complaint to allege a sixth count, ie., willful and wanton conduct by Railroad. After a three-week trial, Judge Allen directed a verdict against Akzona on the issue of willful and wanton conduct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chappell v. N.C. Dep't of Transp.
Supreme Court of North Carolina, 2020
Wagner v. City of Charlotte
Court of Appeals of North Carolina, 2020
State v. Skinner
776 S.E.2d 898 (Court of Appeals of North Carolina, 2015)
State v. Collins
727 S.E.2d 922 (Court of Appeals of North Carolina, 2012)
State v. Harris
679 S.E.2d 464 (Court of Appeals of North Carolina, 2009)
In Re the Will of Mason
606 S.E.2d 921 (Court of Appeals of North Carolina, 2005)
Burchette v. Lynch
535 S.E.2d 77 (Court of Appeals of North Carolina, 2000)
Estate of Fennell Ex Rel. Fennell v. Stephenson
528 S.E.2d 911 (Court of Appeals of North Carolina, 2000)
Brewer v. Cabarrus Plastics, Inc.
504 S.E.2d 580 (Court of Appeals of North Carolina, 1998)
Johnson v. Amethyst Corp.
463 S.E.2d 397 (Court of Appeals of North Carolina, 1995)
State v. Thomas
460 S.E.2d 349 (Court of Appeals of North Carolina, 1995)
Muse v. Charter Hospital of Winston-Salem, Inc.
452 S.E.2d 589 (Court of Appeals of North Carolina, 1995)
Morgan v. Cavalier Acquisition Corp.
432 S.E.2d 915 (Court of Appeals of North Carolina, 1993)
Olympic Products Co. v. Roof Systems, Inc.
363 S.E.2d 367 (Court of Appeals of North Carolina, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
334 S.E.2d 759, 314 N.C. 488, 1985 N.C. LEXIS 2008, Counsel Stack Legal Research, https://law.counselstack.com/opinion/akzona-inc-v-southern-railway-co-nc-1985.