Air Control Technologies, Inc. v. Pre Con Industries, Inc.

CourtCourt of Appeals for the Ninth Circuit
DecidedJune 28, 2013
Docket11-56230
StatusPublished

This text of Air Control Technologies, Inc. v. Pre Con Industries, Inc. (Air Control Technologies, Inc. v. Pre Con Industries, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Air Control Technologies, Inc. v. Pre Con Industries, Inc., (9th Cir. 2013).

Opinion

FOR PUBLICATION

UNITED STATES COURT OF APPEALS FOR THE NINTH CIRCUIT

UNITED STATES FOR THE USE AND No. 11-56230 BENEFIT OF AIR CONTROL TECHNOLOGIES, INC.; AIR CONTROL D.C. No. TECHNOLOGIES, INC., a California 2:11-cv-02281- corporation, PA-SS Plaintiffs-Appellants,

v. OPINION

PRE CON INDUSTRIES, INC., a California corporation; FIRST NATIONAL INSURANCE COMPANY OF AMERICA , a Washington corporation, Defendants-Appellees.

Appeal from the United States District Court for the Central District of California Percy Anderson, District Judge, Presiding

Argued and Submitted April 12, 2013—Pasadena, California

Filed June 28, 2013 2 AIR CONTROL TECH . V . PRE CON INDUS.

Before: Milan D. Smith, Jr. and Mary H. Murguia, Circuit Judges, and Jack Zouhary, District Judge.*

Opinion by Judge Murguia

SUMMARY**

Miller Act

The panel vacated the district court’s order dismissing as time-barred a subcontractor’s complaint alleging federal question jurisdiction over a claim under the Miller Act, which requires that a general contractor on a federal construction project furnish a payment bond for the protection of all persons supplying labor and material on the project.

Overruling United States ex rel. Celanese Coatings Co. v. Gullard, 504 F.2d 466 (9th Cir. 1974), as clearly irreconcilable with intervening higher authority, the panel held that the Miller Act’s statute of limitations is a claim- processing rule, not a jurisdictional requirement.

The panel held that because nothing on the face of the complaint indicates the subcontractor did not work on the project or rent equipment to the general contractor within one year of the date the complaint was filed, the complaint could

* The Honorable Jack Zouhary, District Judge for the U.S. District Court for the Northern District of Ohio, sitting by designation.

** This summary constitutes no part of the opinion of the court. It has been prepared by court staff for the convenience of the reader. AIR CONTROL TECH . V . PRE CON INDUS. 3

not have been dismissed if the district court had treated the Miller Act’s statute of limitations as a claim-processing rule. The panel remanded for further proceedings.

COUNSEL

Francis Lanak and Colin McCarthy (argued), Lanak & Hanna, P.C., Orange, California, for Plaintiffs-Appellants.

Scott Robert Baker, Law Offices of Scott R. Baker, Grover Beach, California, for Defendants-Appellees.

OPINION

MURGUIA, Circuit Judge:

The Miller Act requires that a general contractor on a federal construction project furnish a payment bond “for the protection of all persons supplying labor and material” on the project. 40 U.S.C. § 3131(b)(2). Any person who has supplied labor or material on the project may bring a civil action on the payment bond against the general contractor, see 40 U.S.C.§ 3133(b)(1), but the action “must be brought no later than one year after the day on which the last of the labor was performed or material was supplied by the person bringing the action,” 40 U.S.C. § 3133(b)(4).

Air Control Technologies brought this suit under the Miller Act against Pre Con Industries and First National Insurance Company of America. Relying on United States ex rel. Celanese Coatings Co. v. Gullard, 504 F.2d 466 (9th Cir. 1974), where this court held that the Miller Act’s one-year 4 AIR CONTROL TECH . V . PRE CON INDUS.

statute of limitations is a jurisdictional requirement, the district court dismissed Air Control Technologies’s complaint for lack of subject matter jurisdiction. We overrule Celanese Coatings because it is clearly irreconcilable with intervening higher authority, vacate the district court’s dismissal of Air Control Technologies’s complaint, and remand for further proceedings.

I. Background1

Pre Con Industries (“PCI”) was the general contractor on a construction project for the United States Veterans Administration, and subcontracted Air Control Technologies (“ACT”) to work on the project’s heating, ventilation, and air conditioning (“HVAC”) systems. Pursuant to its obligations under the Miller Act, PCI and its surety, First National Insurance Company of America (“FNIC”), furnished a payment bond for the project.

ACT began working on the project in December 2008, and shortly thereafter encountered conditions on the job site that made the work more expensive than anticipated. PCI fired ACT in November 2009 when ACT demanded reimbursement for its unanticipated costs. ACT then offered to allow PCI to rent ACT’s equipment for use on the project, and PCI accepted the offer.

On March 14, 2011, ACT filed a complaint against PCI and FNIC in the Central District of California, alleging: (1) PCI breached both the original HVAC-service contract and

1 At this stage in the litigation, we accept Air Control Technologies’s version of the facts. N. Cnty. Cmty. Alliance, Inc. v. Salazar, 573 F.3d 738, 741–42 (9th Cir. 2009). AIR CONTROL TECH . V . PRE CON INDUS. 5

the equipment-rental contract; (2) PCI owed ACT money in quantum meruit for the HVAC services; and (3) a claim for recovery on the payment bond under the Miller Act. The complaint alleged the district court had federal question jurisdiction over the Miller Act claim and supplemental jurisdiction over the state law claims.

Defendants filed a 12(b)(1) motion to dismiss ACT’s complaint for lack of subject matter jurisdiction. An action under the Miller Act “must be brought no later than one year after the day on which the last of the labor was performed or material was supplied by the person bringing the action,” 40 U.S.C. § 3133(b)(4), and in Celanese Coatings Co., 504 F.2d at 468–69, this court held that the Miller Act’s statute of limitations is a jurisdictional requirement. As is proper with a factual attack in a 12(b)(1) motion, Defendants submitted materials outside the pleadings that they claimed demonstrated ACT’s complaint was untimely. See Safe Air for Everyone v. Meyer, 373 F.3d 1035, 1039 (9th Cir. 2004).

The district court agreed, finding that ACT (1) performed no labor on the federal project after November 2009, and (2) failed to demonstrate that it supplied any materials pursuant to the equipment-rental contract for use on the federal project within one year of filing the complaint. See United States ex rel. Pippin v. J.R. Youngdale Constr. Co., 923 F.2d 146, 149–50 (9th Cir. 1991). Citing Celanese Coatings, the district court dismissed ACT’s complaint for lack of subject matter jurisdiction. ACT timely appealed. 6 AIR CONTROL TECH . V . PRE CON INDUS.

II. Discussion

A. The Miller Act’s Statute of Limitations

There is an intra-circuit split as to the effect of a plaintiff’s failure to meet the Miller Act’s one-year statute of limitations. In 1963, this court held the Miller Act’s statute of limitations was not a jurisdictional requirement, rejecting the argument that “the prescribed period is a condition precedent to recovery” under the Act. United States ex rel. E.E. Black Ltd. v. Price-McNemar Constr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arbaugh v. Y & H Corp.
546 U.S. 500 (Supreme Court, 2006)
Bowles v. Russell
551 U.S. 205 (Supreme Court, 2007)
Henderson v. Shinseki
131 S. Ct. 1197 (Supreme Court, 2011)
Payne Ex Rel. D.P. v. Peninsula School District
653 F.3d 863 (Ninth Circuit, 2011)
United States v. Price-M
320 F.2d 663 (Ninth Circuit, 1963)
Atonio v. Wards Cove Packing Company
810 F.2d 1477 (Ninth Circuit, 1987)
Jack Leeson v. Transamerica Disability Income
671 F.3d 969 (Ninth Circuit, 2012)
Supermail Cargo, Inc. v. United States
68 F.3d 1204 (Ninth Circuit, 1995)
Sebelius v. Auburn Regional Medical Center
133 S. Ct. 817 (Supreme Court, 2013)
Von Saher v. Norton Simon Museum of Art at Pasadena
592 F.3d 954 (Ninth Circuit, 2010)
North County Community Alliance, Inc. v. Salazar
573 F.3d 738 (Ninth Circuit, 2009)
Highland Renovation Corp. v. Hanover Insurance Group
620 F. Supp. 2d 79 (District of Columbia, 2009)
Reed Elsevier, Inc. v. Muchnick
176 L. Ed. 2d 18 (Supreme Court, 2010)
Holland v. Florida
177 L. Ed. 2d 130 (Supreme Court, 2010)
Miller v. Gammie
335 F.3d 889 (Ninth Circuit, 2003)
Safe Air for Everyone v. Meyer
373 F.3d 1035 (Ninth Circuit, 2004)
United States v. Gullard
504 F.2d 466 (Ninth Circuit, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
Air Control Technologies, Inc. v. Pre Con Industries, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/air-control-technologies-inc-v-pre-con-industries--ca9-2013.