Ahl v. Harrisburg etc. R.

18 A. 477, 129 Pa. 49, 1889 Pa. LEXIS 1225
CourtSupreme Court of Pennsylvania
DecidedOctober 21, 1889
DocketNos. 53 and 438
StatusPublished
Cited by13 cases

This text of 18 A. 477 (Ahl v. Harrisburg etc. R.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ahl v. Harrisburg etc. R., 18 A. 477, 129 Pa. 49, 1889 Pa. LEXIS 1225 (Pa. 1889).

Opinion

q. p. ahl’s appeal.

Opinion,

Me. Justice Williams:

The questions .involved in this controversy are questions of fact. We learn from the report of the master that the Harrisburg & Potomac Railroad Co. was organized, and the construction of its road undertaken, largely through the instrumentality of D. Y. Ahl and P. A. Ahl, his brother and business partner. In 1877, D. Y. Ahl was president of the company, and P. A. Ahl was the contractor, not only for the grading, but for furnishing"and laying the ties and rails. He had just finished one section, and nearly completed another, extending from Langsdorf to Jacksonville, a distance of four miles, when serious financial embarrassment overtook him. D. Y. Ahl appears to have been interested with, or responsible for the performance of his brother, and to have been involved in the same difficulties. They had invested their money and pledged their credit in the construction of the road until they feared to go further. They sought the advice of family friends, who were also interested in the early completion of the railroad; and the conclusion was reached that the further prosecution of the “work under the contract should be conducted in the names of Q. P. Ahl and T. W. Ahl, and that D. Y. Ahl and P. A., Ahl and the firm of P. A. Ahl & Bro. should put their [58]*58effects into the hands of C. W. Ahl for the payment of their debts. An assignment of the contract was accordingly made to Q. P. & T. W. Ahl, who were accepted by the railroad company, and who proceeded to complete the section in their own names. An assignment was also made by D. V. & P. A. Ahl and P. A. Ahl & Bro. to C. W. Ahl, for the purpose of paying their debts. Neither Q. P. Ahl nor T. W Ahl paid anything for the assignment of the contract to them, but took possession of the grading and the materials, and finished the section. The work was accepted by the railroad company, and paid for in stock and bonds, in accordance with the original contract. The stock and bonds were turned over to C. W. Aid, the assignee of D'. Y. and P. A. Ahl, and appropriated by him to the payment of their debts, in accordance with the understanding had when they surrendered their property to him.

Six years after the completion of the section, and the delivery of the stock and bonds in payment therefor, this bill was filed; setting out that the plaintiff and T. W. Ahl were partners in the work of completing the section, the contract for which had been assigned to them; that the money used by the' firm was advanced by the plaintiff; that the accounts of the firm were still unsettled; that the bonds and stock issued-by the railroad company in payment for the construction of the road between Langsdorf and Jacksonville belonged to him, but were in the hands of P. A. Ahl and C. W. Ahl; that they had been received with full notice of his title, and used by C. W. Ahl and P. A. Ahl for the payment of the debts of P. A. Ahl & Bro., or some other purpose. Relief was prayed for against each of the defendants separately, — against T. W. Ahl for a dissolution of the alleged partnership, for discovery, and an account; against the Harrisburg & Potomac Railroad Co. for an ascertainment of the amount of bonds to which the plaintiff is entitled in payment for the section between Langsdorf and Jacksonville, and for the delivery of the same to him; against P. A. Ahl for discovery and account as to the bonds received by him applicable to the work on the said section; against C. W. Ahl for discovery and account as to the bonds received by him applicable to the same section. The defendants answered separately. They denied that a partnership existed between the plaintiff and T. W. Ahl in the work done on the railroad. [59]*59They denied that Q. P. and T. W. Ahl, or either of them, took any title under the assignment made by P. A. Ahl, and alleged that the work was agreed to be done, and was in fact done, for P. A. Ahl, and under his directions. They further alleged that the bonds and stock had been issued upon the acceptance of the section by the railroad company to the plaintiff himself, and by him turned over voluntarily to P. A. Ahl, in accordance. with the arrangement made when the contract was transferred; and that P. A. Ahl had delivered them to C. W. Ahl for sale and appropriation upon the debts of himself and his firm, and that such an appropriation had been in fact made by C. W. Ahl. Separate issues of fact were thus raised between the plaintiff and each of the defendants. These were heard by a master, who found for the defendants upon every issue raised. These findings were examined by the learned judge of the court below on exceptions, and after such examination they were concurred in. The facts, therefore, may be regarded as settled ; but we have looked into the testimony to see if any plain mistake has been made by the master and the court below, and we are satisfied that the evidence fully justifies the findings. There was competent and sufficient evidence before the master to sustain each of them; and his findings, and the decree of the court based on them, must be regarded as settling the facts.

The legal questions involved are equally free from difficulty. The master having found that the alleged partnership -with T. W. Ahl never existed, the dismissal of the bill as to him is the necessary consequence. The finding that the railroad company issued the bonds and stock due upon the completion of the section between Langsdorf and Jacksonville, at the proper time, and delivered them into the plaintiff’s own hands, entitled the company to a decree in its favor. The finding that P. A. Ahl received such bonds as came to his hands from the plaintiff in accordance with an arrangement tbat he was to receive them, because entitled to them, was fatal to the plaintiff’s claim for relief against him. As to C. W. Ahl, the master finds that the bonds that came to his hands were delivered by P. A. Ahl to him for the payment of debts, and were actually so used, and that the plaintiff had no title to them whatever. This sweeps away the plaintiff’s case as to this defendant. [60]*60Nothing remains, therefore, of the case made in the bill against either one of the defendants.

It has been urged in argument, that, if the plaintiff took nothing under the assignment of the construction contract to him, then the arrangement should be held to be void as a device to hinder and delay creditors of P. A. Ahl. On this subject the master finds that the transfer was intended to facilitate the completion of the section, and thereby to secure at the earliest moment practicable the entire sum to be paid under the contract for the benefit of creditors. It was therefore not a fraud in fact, and it cannot be held to be a fraud in law, upon the facts presented by the master’s report. But, suppose the fact to be, as is alleged, that the transfer from P. A. Ahl to the plaintiff was intended to hinder and delay the creditors of P. A. Ahl, and that it was therefore void as to the persons intended to be defrauded, how would Q. P. Ahl be helped by such a conclusion? He is a party to the fraudulent transfer, a particeps eriminis. The proceeds of the fraudulent transaction are out of his hands, and he asks a chancellor to take them from the hands of his co-conspirator, and place them in his own. He is not prompt and eager to seek relief, but waits for six years. He states a cause of action in his bill, every fact of which is found against him.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Universal Builders, Inc. v. Moon Motor Lodge, Inc.
244 A.2d 10 (Superior Court of Pennsylvania, 1968)
Spang v. Wertz Engineering Co.
114 A.2d 143 (Supreme Court of Pennsylvania, 1955)
Meth v. Meth
62 A.2d 848 (Supreme Court of Pennsylvania, 1948)
Siranovich v. Butkovich
58 A.2d 461 (Supreme Court of Pennsylvania, 1948)
Lare v. Young
33 A.2d 662 (Superior Court of Pennsylvania, 1943)
Bevan v. Local Branch No. 898, U. M. W.
23 Pa. D. & C. 502 (Lehigh County Court of Common Pleas, 1934)
Cella v. Davidson
156 A. 99 (Supreme Court of Pennsylvania, 1931)
Milasinovich v. Milasinovich
88 Pa. Super. 196 (Superior Court of Pennsylvania, 1926)
Lafean v. American Caramel Co.
114 A. 622 (Supreme Court of Pennsylvania, 1921)
Mercantile Library Co. v. University of Pennsylvania
69 A. 861 (Supreme Court of Pennsylvania, 1908)
Hanna v. Clark
41 A. 981 (Supreme Court of Pennsylvania, 1899)
Gwinn v. Lee
6 Pa. Super. 646 (Superior Court of Pennsylvania, 1898)
Silvis v. Clous
1 Pa. Super. 41 (Superior Court of Pennsylvania, 1895)

Cite This Page — Counsel Stack

Bluebook (online)
18 A. 477, 129 Pa. 49, 1889 Pa. LEXIS 1225, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ahl-v-harrisburg-etc-r-pa-1889.