AHA Mechanical Contractors, LLC v. Shelby County Board of Education

CourtCourt of Appeals of Tennessee
DecidedJuly 15, 2026
DocketW2025-01107-COA-R3-CV
StatusPublished
AuthorJudge Steven W. Maroney

This text of AHA Mechanical Contractors, LLC v. Shelby County Board of Education (AHA Mechanical Contractors, LLC v. Shelby County Board of Education) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AHA Mechanical Contractors, LLC v. Shelby County Board of Education, (Tenn. Ct. App. 2026).

Opinion

07/15/2026 IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON April 21, 2026 Session

AHA MECHANICAL CONTRACTORS, LLC v. SHELBY COUNTY BOARD OF EDUCATION

Appeal from the Chancery Court for Shelby County No. CH-21-1403-1 Melanie Taylor Jefferson, Chancellor ___________________________________

No. W2025-01107-COA-R3-CV ___________________________________

This appeal requires us to determine whether the trial court erred in granting Appellee/Shelby County Board of Education’s motion for summary judgment on its breach of contract claim against Appellant/Contractor. Because disputes of material fact and ambiguities arising therefrom exist, the trial court’s grant of summary judgment is reversed.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Reversed and Remanded

STEVEN W. MARONEY, J., delivered the opinion of the court, in which J. STEVEN STAFFORD, P.J., W.S., and CARMA DENNIS MCGEE, J., joined.

Scott A. Frick, Memphis, Tennessee, for the appellant, AHA Mechanical Contractor, LLC.

Jamie L. Morton, Memphis, Tennessee, for the appellee, Shelby County Board of Education.

OPINION

I. Background

A. Contract Formation and Scope

On or about February 11, 2020, Appellee Shelby County Board of Education (“SCBE”) published Invitation for Bid No. 03022020 (“IFB”) related to HVAC replacement at Riverview K-8 School (the “Riverview Project”). The IFB included the Scope of Work for the Riverview Project. In relevant part, Section 3.0 of the Scope of Work states:

3.0 SCOPE OF WORK

The SCBE requests bids for Riverview K-8 HVAC Replacements. Replace existing cooling tower with new to match capacity, 500-ton, 1 440 GPM. Replacement shall include structural base, associated piping, and associated accessories such as by-pass valves. Concrete base shall be reviewed and verified to meet load & current code criteria. . . .

Appellant AHA Mechanical Contractors (“Contractor”) submitted a bid on the Riverview Project, which bid SCBE accepted. The Riverview Project is governed by a Facilities Services Agreement signed by both parties (the “Contract”). The Contract bears the insignia of SCBE on its first page, and it appears undisputed in the record that the Contract was drafted by SCBE.

The Contract incorporates, by reference, several documents related to the Riverview Project, including the IFB and the Scope of Work. Paragraph 37 of the Contract requires that, “Contractor will observe and comply with all applicable local, state, and federal laws, ordinances, and regulations . . . .” Paragraph 15 expressly permits SCBE to terminate the Contract for cause if, among other reasons, Contractor substantially violates any provision of the Contract. In such case, the Contract provides for liquidated damages and an award of SCBE’s reasonable attorneys’ fees, costs, and expenses arising from such termination of the Contract.

B. Communications Regarding the Concrete Base

The instant appeal arises from the parties’ dispute concerning the Scope of Work language, “Concrete base shall be reviewed and verified to meet load & current code criteria.” The SCBE asserts that this language requires Contractor to obtain a review and verification from a structural engineer. As discussed further below, the Contract does not define the term “load,” nor does it specify which “current code criteria” are applicable.

After executing their Contract, the parties engaged in communication, via letters, emails, and in-person discussions, concerning the requirements regarding the concrete base. From our review, at the time the parties entered their Contract, the only existing “concrete base” was the original base on which the old HVAC was constructed, which remained after that system was dismantled so that the new HVAC system could be installed by Contractor. As discussed below, Contractor subsequently made modifications to the existing concrete base.

-2- After SCBE notified Contractor that it would require an engineer’s verification that the concrete base was “load” and “code” compliant, Contractor requested that its engineer, Mr. Marshall Davis, provide same. However, on October 20, 2020, Mr. Davis declined to write an engineer’s letter that would address the concrete base for the cooling tower, stating:

We have some concerns with how the slab was done. We do not feel comfortable writing a letter with the current as-built condition. The main concern is the overturning of the cooling tower during a high wind or seismic event. For us to write a letter we would require additional modification; however, another engineer may be willing to write a letter for the as-built condition.

Nonetheless, on October 29, 2020, Mr. Davis prepared a letter for Contractor, stating, “The as-built condition meets the overall design intent.” The parties dispute whether Mr. Davis’ “as-built condition” statement satisfies the “[c]oncrete base shall be reviewed and verified to meet load & current code criteria” requirement of the Contract. SCBE argues, and the trial court found, that, although Mr. Davis’ October 29, 2020 letter states that the “as-built condition meets the overall design intent,” it does not address the concrete base or state whether the concrete base was ever reviewed and verified to meet load and current code criteria before any modifications were made to it.

SCBE sent at least three letters to Contractor requesting that Contractor comply with its alleged contractual obligation to provide an engineer’s verification that the concrete base would meet all load and code criteria. Although Contractor responded to these demands, none of the responses contained an engineer’s opinion.

C. Notices of Default and Termination of the Contract

On January 15, 2021, SCBE sent a letter terminating the Contract. The January 15th letter stated, in relevant part:

Contractor is in default of its obligations under the Construction Contract for failure to perform the Work in accordance with the Contract Documents, including without limitation Contractor’s failure to provide verification that the concrete base will meet load and current code criteria as required by the Scope of Work set forth in [the IFB]. Further, as expressly stated in the letter dated July 8, 2020, the engineer engaged by Contractor to review the cooling tower support frame based his opinion of the frame’s sufficiency upon the assumption that “[t]he new cooling tower support frame will be installed on a new concrete foundation designed by others at the existing cooling tower location.” Owner obtained an approved structural design for the new concrete cooling tower at no cost to Contractor. Nonetheless, Contractor has not -3- agreed to install a new concrete foundation that can be confirmed and verified by a licensed professional to meet load and code criteria as required by the IFB and has failed to perform the Work in accordance with the Contract Documents.

In response to SCBE’s letter terminating the Contract, Contractor’s attorney sent a letter to SCBE on January 28, 2021, stating, in relevant part:

[SCBE] does not have either a factual or legal basis for terminating the [Contract] . . . . All work performed by [Contractor] on the [Riverview] Project was performed in full compliance with the specifications included in the [IFB]. The current dispute is directly attributable to the lack of proper specifications developed by [SCBE] for what it apparently intended for this Project. In addition, various field modifications to the installation that were not contained in the specifications were installed as a direct result of requests made by [SCBE] representatives who are managing the Project on behalf of [SCBE].

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dick Broadcasting Company, Inc. of Tennessee v. Oak Ridge FM, Inc.
395 S.W.3d 653 (Tennessee Supreme Court, 2013)
German v. Ford
300 S.W.3d 692 (Court of Appeals of Tennessee, 2009)
Kafozi v. Windward Cove, LLC
184 S.W.3d 693 (Court of Appeals of Tennessee, 2005)
Staubach Retail Services-Southeast, LLC v. H.G. Hill Realty Co.
160 S.W.3d 521 (Tennessee Supreme Court, 2005)
State Ex Rel. Pope v. United States Fire Insurance Co.
145 S.W.3d 529 (Tennessee Supreme Court, 2004)
Staples v. CBL & Associates, Inc.
15 S.W.3d 83 (Tennessee Supreme Court, 2000)
Marshall v. Jackson & Jones Oils, Inc.
20 S.W.3d 678 (Court of Appeals of Tennessee, 1999)
White v. Kaminsky
264 S.W.2d 813 (Tennessee Supreme Court, 1954)
Shadrick v. Coker
963 S.W.2d 726 (Tennessee Supreme Court, 1998)
Bob Pearsall Motors, Inc. v. Regal Chrysler-Plymouth, Inc.
521 S.W.2d 578 (Tennessee Supreme Court, 1975)
Doe v. HCA Health Services of Tennessee, Inc.
46 S.W.3d 191 (Tennessee Supreme Court, 2001)
Schaeffer v. American Honda Motor Co., Inc.
976 F. Supp. 736 (W.D. Tennessee, 1997)
Rogers v. First Tennessee Bank National Ass'n
738 S.W.2d 635 (Court of Appeals of Tennessee, 1987)
Coble Systems, Inc. v. Gifford Co.
627 S.W.2d 359 (Court of Appeals of Tennessee, 1981)
Springfield Tobacco Redryers Corp. v. City of Springfield
293 S.W.2d 189 (Court of Appeals of Tennessee, 1956)
Carvell v. Bottoms
900 S.W.2d 23 (Tennessee Supreme Court, 1995)
Planters Gin Co. v. Federal Compress & Warehouse Co.
78 S.W.3d 885 (Tennessee Supreme Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
AHA Mechanical Contractors, LLC v. Shelby County Board of Education, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aha-mechanical-contractors-llc-v-shelby-county-board-of-education-tennctapp-2026.