Affiliated FM Insurance Company v. Ram Construction Services of Michigan, Inc.

District Court, E.D. Kentucky·Decided July 7, 2023·No. 5:21-cv-00233·Unknown

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF KENTUCKY CENTRAL DIVISION (at Lexington)

AFFILIATED FM INSURANCE ) COMPANY, ) ) Plaintiff, ) Civil Action No. 5: 21-233-DCR ) V. ) ) WALKER PARKING ) CONSULTANTS/ENGINEERS, INC. ) MEMORANDUM OPINION AND FRIEDMAN MANAGEMENT ) AND ORDER COMPANY, ) ) Defendants. )

*** *** *** *** Plaintiff Affiliated FM Insurance Company (“Affiliated FM”) reimbursed Lexington Opportunity Fund, LLC (“LOF”) for damages after a two-story Parking Garage (the “Parking Garage”) owned by LOF collapsed in February 2021. Affiliated FM filed this action against Defendants Walker Parking Consultants/Engineers, Inc. (“Walker”), Friedman Management Company (“Friedman”), RAM Construction Services of Michigan, Inc. (“RAM”), and LNR Partners, LLC (“LNR”). It seeks subrogation of the reimbursement payments made to LOF. [Record No. 56] Walker has moved for summary judgment pursuant to Rule 56 of the Federal Rules of Civil Procedure, and Friedman filed a motion to dismiss pursuant to Rule 12(b)(6) of the Federal Rules of Civil Procedure. [Record Nos. 100, 101] For reasons that follow, the defendants’ motions will be granted. I. Background A. Parking Garage Repairs The Parking Garage was previously owned by WBCMT 2006-C29 West Vine Street,

LLC (“WBCMT”). [Record No. 56, p. 2] Friedman was appointed as Receiver of the Parking Garage pursuant to a Fayette Circuit Court order which directed the defendant to “take charge and possession of, preserve, operate, maintain, and care for the [Parking Garage].” [Record No. 56-2, p. 2] Friedman hired Walker in July 2017 to evaluate the condition of the Parking Garage and identify any necessary repairs. [Record No. 109-4] Walker assessed the Parking Garage and submitted a report (“Walker’s assessment report”) in which the defendant noted that “moisture infiltration through the control joints has led to extensive concrete deterioration

as well as corrosion of the supplemental bearing steel throughout the garage.” [Record No. 56-4, p. 5] Walker recommended several repairs, including “shor[ing] as necessary precast tee stems with exposed strands,” removing “all unsound concrete . . . and [repairing] any exposed reinforcement.” [Id. at pp. 5, 9] Friedman hired Walker again in January 2018 to prepare construction documents for the repairs contained in Walker’s assessment report. [Record No. 56-5] The parties’ contract

specifies that Walker would “[c]onduct up to four (4) observation visits during the repairs at regular intervals to review construction for general conformance with the design intent of the specifications and drawings and verify unit cost quantities.” [Id. at p. 9] Walker further agreed to “[m]ake a final punch list visit towards project completion” and to “[c]omplete any necessary closeout documentation including letters of substantial completion.” [Id.] WBCMT contracted with RAM in March 2018 to perform the repairs identified in Walker’s assessment report. [Record No. 56-6] RAM agreed to, among other things, “install new concrete and reinforcing . . . materials to restore concrete beams and joists to original condition and appearance.” [Record No. 109-7] The parties agreed that RAM would be paid for 290 square feet of beam repairs. [Record No. 56-6, p. 33]

RAM began repairing the Parking Garage in July 2018, and Walker conducted site visits in accordance with its contractual obligations. After participating in a walkthrough with a representative from the Lexington-Fayette Urban County Government (“LFUCG”) in October 2018, Walker issued a report noting that the project had progressed. [Record No. 109- 14] The report indicated that several areas of the Parking Garage required further repairs, specifically noting that RAM should repair the “interior inverted tee beam[s] . . . as noted in the construction documents.” [Id. at p. 5] Walker completed its final walk through on

November 29, 2018. LFUCG notified RAM after construction began that the parties were required to secure permits for the project. [Record No. 100-3, p. 200] Walker employee Kyle Pawlak submitted drawings to LFUCG indicating Walker’s proposed repairs in September 2018. [Record No. 109-12] Pawlak sent a letter to LFUCG in January 2019 certifying that RAM had “substantial[ly] complet[ed]” the repair work as described in Walker’s assessment report and

drawings. [Record No. 109-19] Dawn Davis, a LFUCG employee, questioned the accuracy of the initial completion letter. Davis asked Pawlak why Walker “had marked many of the areas on the upper parking deck to be repaired in your drawings, but decided that now they don’t need [to be] repaired.” [Record No. 109-18] Davis further requested that Walker ensure that “the work that was shown on your drawings was completed” and that he identify “any work that has been removed from the scope of the project.” [Id.] On January 30, 2019, Walker sent a revised letter to LFUCG (the “completion letter”). [Record No. 56-7] The completion letter states, in relevant part: As part of our scope of work in the construction administration phase of the project, Walker made periodic visits to observe the progress and quality of the restoration work. Based on our limited observations, it is our opinion that the structural restoration work has been performed in substantial conformance with the permit documents and approved shop drawings as of Walker’s last visit on November 29, 2018.

[Record No. 56-7] LFUCG accepted Walker’s submission and issued a certificate of completion for the Parking Garage. [Record No. 100-3, p. 225] B. LOF’s Purchase of The Parking Garage LOF successfully bid on the Parking Garage during an online auction in January 2019. [Record No. 100-2, p. 44] LOF employed the Webb Companies to oversee the purchase of the Parking Garage and manage the property pursuant to a written agreement (the “Management Agreement”). [Record No. 110-3] The Management Agreement specifies that Webb would be appointed “as an independent contractor to manage the . . . related parking garage,” and that Webb “hereby accepts such appointment and the fiduciary relationship thereby established.” [Id. at p. 1] Dudley Webb, co-founder of the Webb Companies, oversaw the management of the Parking Garage. [Record No. 100-2, p. 13] Webb and LOF attorney Tom Marks assisted LOF in signing an agreement (the “Purchase Agreement”) to purchase the Parking Garage from WBCMT on January 30, 2019. [Record Nos. 56, p. 5, 78-1] The Purchase Agreement provides that the parties would execute their contract on January 30, 2019 and close on the purchase on March 4, 2019. [Record No. 78-1, pp. 2, 9] The contract defines the term “Seller” to include “the heirs, personal representatives, successors and assigns of the respective part[y],” and defines the “Seller Group” as including “Seller and its member and such member’s trustee, master servicer, special servicer and certificate holders, all subsidiaries . . . and each of the foregoing parties’ past, present, and future . . . agents, employees, representatives . . . assigns and attorneys.” [Id. at pp. 8, 29]

Free access — add to your briefcase to read the full text and ask questions with AI

Affiliated FM Insurance Company v. Ram Construction Services of Michigan, Inc., (E.D. Ky. 2023).

Affiliated FM Insurance Company v. Ram Construction Services of Michigan, Inc. (Affiliated FM Insurance Company v. Ram Construction Services of Michigan, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Barton v. Barbour
104 U.S. 126 (Supreme Court, 1881)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Matherly Land Surveying, Inc. v. Gardiner Park Development, LLC
230 S.W.3d 586 (Kentucky Supreme Court, 2007)
Presnell Construction Managers, Inc. v. EH Construction, LLC
134 S.W.3d 575 (Kentucky Supreme Court, 2004)
Queensway Financial Holdings Ltd. v. Cotton & Allen, P.S.C.
237 S.W.3d 141 (Kentucky Supreme Court, 2007)
Hazel v. General Motors Corp.
863 F. Supp. 435 (W.D. Kentucky, 1994)
Northwestern National Insurance v. Osborne
610 F. Supp. 126 (E.D. Kentucky, 1985)
Cohen v. North Ridge Farms, Inc.
712 F. Supp. 1265 (E.D. Kentucky, 1989)
Munday v. Mayfair Diagnostic Laboratory
831 S.W.2d 912 (Kentucky Supreme Court, 1992)
CSX Transportation, Inc. v. First National Bank of Grayson
14 S.W.3d 563 (Court of Appeals of Kentucky, 2000)
Fluke Corp. v. LeMaster
306 S.W.3d 55 (Kentucky Supreme Court, 2010)
Old Mason's Home of Kentucky, Inc. v. Mitchell
892 S.W.2d 304 (Court of Appeals of Kentucky, 1995)
Blanton v. Cooper Industries, Inc.
99 F. Supp. 2d 797 (E.D. Kentucky, 2000)
Keeneland Ass'n, Inc. v. Eamer
830 F. Supp. 974 (E.D. Kentucky, 1993)
Smith v. General Motors Corp.
979 S.W.2d 127 (Court of Appeals of Kentucky, 1998)