Matherly Land Surveying, Inc. v. Gardiner Park Development, LLC

230 S.W.3d 586, 2007 Ky. LEXIS 174, 2007 WL 2403398
CourtKentucky Supreme Court
DecidedAugust 23, 2007
Docket2005-SC-000576-DG, 2006-SC-000163-DG
StatusPublished
Cited by9 cases

This text of 230 S.W.3d 586 (Matherly Land Surveying, Inc. v. Gardiner Park Development, LLC) is published on Counsel Stack Legal Research, covering Kentucky Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Matherly Land Surveying, Inc. v. Gardiner Park Development, LLC, 230 S.W.3d 586, 2007 Ky. LEXIS 174, 2007 WL 2403398 (Ky. 2007).

Opinion

Opinion of the Court by

Justice SCOTT.

Appellants, Matherly Land Surveying, Inc. (hereinafter MLS), Alva Matherly, and Carl Douglas Comer, appeal from a Court of Appeals decision holding that the statute of limitations provided in KRS 413.245 does not apply to all of the services they performed for the Appellees, Gard-iner Park Development, LLC (hereinafter GPD), Gardiner Design & Development, Inc. (hereinafter GDD), and Gregory S. Gardiner (collectively referred to as the Gardiner Entities). The Court of Appeals’ decision reversed the circuit court’s ruling which stated that any claims against MLS stemming from the dispute with the Gard-iner Entities were time barred by KRS 413.245 because the services in question were performed or overseen by a professional engineer. Woodward, Hobson & Fulton, LLP and D. Sean Nilsen (collectively referred to as WHF) are Cross-Appellees in this suit, having filed a cross motion to present issues relevant to the Gardiner Entities’ lawsuit against them for legal malpractice. We now reverse and reinstate the circuit court’s decision.

In 1997, MLS entered into a contract with GDD to provide services incidental to the construction of a subdivision in Jefferson County, Kentucky. According to this contract MLS was to provide multiple services for GDD including, but not limited to: laying out the proposed alignment of sanitary sewers and the lift stations, conducing cross-sections, profiles, and rock soundings necessary for design of the roads and sewers, designing the sanitary sewers for the subdivision, designing the internal roads for the subdivision, designing the lift stations for the sewer, and creating the record plat for the subdivision. At the time the contract was entered into, MLS was registered and licensed by the Board of Registration of Professional Engineers and Land Surveyors as a professional engineering firm in Kentucky. Alva Matherly, the owner of MLS, was a professional land surveyor licensed in Kentucky. MLS also employed several professional engineers licensed in Kentucky including Carl Comer who worked on the Gardiner project.

During a deposition, Gregory Gardiner stated that he believed that a professional *588 engineer would be providing and stamping the construction plans that were created by MLS. He further stated that he believed he had hired MLS to provide professional engineering services in completing the contract and that any of the surveying activities performed were incidental to the engineering activities.

MLS performed work on the project between August 5, 1997, and August 16, 1998. It was during this time that GDD complained that the work performed by MLS was progressing too slowly. In addition, GDD alleged that the work MLS did was incorrect. Several letters were exchanged between the parties in an attempt to work out a favorable solution, but none could be found. On August 16, 1998, MLS stopped performance on the contract. GDD subsequently hired an engineering firm and land surveying firm to complete the project.

In February 1999, the Gardiner Entities hired Cross Appellants, WHF, to represent their interests against MLS. MLS claimed at this time that they had not been paid for the work they completed and the Gardiner Entities wanted compensation for the incomplete work that had to be done by others.

Thus, the parties attempted to enter into mediation in December 1999, but this was cancelled by MLS. Thereafter, MLS’s counsel asserted that any future claims filed by the Gardiner Entities against MLS were barred by the one-year professional services statute of limitations in KRS 413.245. The Gardiner Entities fired WHF and hired new counsel.

The Gardiner Entities then filed suit against MLS, Matherly, Comer, and WHF in September 2001 and specifically asked the trial court to determine the applicable statute of limitations for any claims that might be asserted by the Gardiner Entities against MLS. Alternatively, the Gardiner Entities claimed that WHF had breached the duty of care owed to them by potentially allowing the statute of limitations to run on any future claims. Later the Gard-iner Entities filed suit against MLS for any damages it sustained due to MLS’s breach of contract. The two suits were consolidated in the Jefferson Circuit Court.

In March 2003, MLS filed a motion to dismiss, for a declaration of rights, and for summary judgment. MLS argued in these motions that the one year statute of limitations for professional services under KRS 413.245 applied to all claims made by Gardiner. WHF filed a cross motion for summary judgment arguing that Gard-iner’s claims were actually for breach of contract and hence the fifteen year statute of limitations provided for in KRS 413.090 was applicable. WHF further argued that land surveyors were not professionals under KRS 413.245, and that even if KRS 413.245 was applicable, the suit was not time barred because the alleged damages were not “fixed and nonspeculative.”

On August 27, 2003, the trial court granted summary judgment to MLS and denied WHF’s cross motion for summary judgment. The trial court however, did not address whether a land surveyor was a professional under KRS 413.245, but instead concluded that the contract was for engineering services and any land surveying services provided were incidental to the engineering services. In this respect, the trial court held:

The record appears undisputed that MLS, a professional engineering company, was performing engineering services while undertaking the Gardiner Park project, and that such services were supervised and controlled by Comer, a licensed engineer employed by MLS. Furthermore, it appears that, as a result of the alleged failure by Comer, as supervising engineer, to timely complete *589 certain aspects of the project, the alleged breach on the part of MLS occurred. As such, it appears that the one-year statute of limitations under KRS 413.245, is applicable.

In addition, the trial court rejected WHF’s arguments, including the contention that the damages were not “fixed and nonspe-culative.” The trial court held that the Gardiner Entities were fully aware of their claims and damages against MLS no later than the attempted mediation in December 1999 — and hence the applicable statute of limitations had run.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eitel v. PNC Bank, NA
W.D. Kentucky, 2024
Shan Wolfe v. Joe Kimmel
Kentucky Supreme Court, 2023
Shan Wolfe v. Joe Kimmel
Court of Appeals of Kentucky, 2021
Saalwaechter v. Carroll
525 S.W.3d 100 (Court of Appeals of Kentucky, 2017)
Corporex Companies, LLC. v. Proskauer Rose, LLP.
713 F. Supp. 2d 678 (E.D. Kentucky, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
230 S.W.3d 586, 2007 Ky. LEXIS 174, 2007 WL 2403398, Counsel Stack Legal Research, https://law.counselstack.com/opinion/matherly-land-surveying-inc-v-gardiner-park-development-llc-ky-2007.