Affholder, Inc. v. MITCHELL ENGINEERING, INC.

63 Cal. Rptr. 3d 121, 153 Cal. App. 4th 510, 2007 Cal. App. LEXIS 1190
CourtCalifornia Court of Appeal
DecidedJuly 18, 2007
DocketA114943
StatusPublished
Cited by8 cases

This text of 63 Cal. Rptr. 3d 121 (Affholder, Inc. v. MITCHELL ENGINEERING, INC.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Affholder, Inc. v. MITCHELL ENGINEERING, INC., 63 Cal. Rptr. 3d 121, 153 Cal. App. 4th 510, 2007 Cal. App. LEXIS 1190 (Cal. Ct. App. 2007).

Opinion

Opinion

POLLAK, J.

Plaintiff Affholder, Inc. (Affholder), a subcontractor, appeals from a judgment entered in favor of defendant Mitchell Engineering, Inc. (Mitchell or Mitchell Engineering), a prime contractor, on its complaint for a violation of the Subletting and Subcontracting, Fair Practices Act (Pub. Contract Code, § 4100 et seq.) (the Act or Subcontracting Act). 1 Affholder contends that the trial court erred in granting Mitchell summary judgment because there is a triable issue as to whether Mitchell improperly refused to award Affholder a subcontract on a public works project after the Sacramento Regional County Sanitation District (the district), the awarding authority, issued a change order affecting the work to be performed on the project. We conclude that summary judgment was properly granted because the change order deleted the work for which Affholder had submitted a bid, and the district determined that the change order relieved Mitchell of its statutory obligation to enter a subcontract with Affholder.

Factual and Procedural History

In October 2004, Mitchell submitted a bid to the district to be the prime contractor for the Bradshaw Interceptor: Bradshaw Pipeline and Road Improvement Project Section 6B (the project). The project consisted of the construction of sewer interceptor pipes and roadway improvements in Sacramento County, and included the construction of two segmented precast *514 concrete tunnels which were to be excavated by an “Earth Pressure Balanced Tunnel Boring Machine (EPB TBM).” Affholder, a district-approved tunnel contractor, submitted a proposal to Mitchell for the performance of the tunnel work, described as bid item Nos. 8 and 9. 2 Affholder’s proposal states, “The tunnel[s] will be constructed per specifications, or better, with non-expanded bolted and gasketed segmental primary lining behind an EPB TBM.” Affholder’s proposal to Mitchell included $3,120,000 for bid item No. 8, the Jackson Highway tunnel, and $4,318,000 for bid item No. 9, the Morrison Creek tunnel. Mitchell listed Affholder in its bid to the district as the subcontractor for the “micro tunnel” portion of the work. On November 24, 2004, the district awarded Mitchell the contract for the project.

Before entering into a subcontract with Affholder, Mitchell submitted to the district, pursuant to Sacramento County’s Construction Incentive Change Proposal (CICP) Program, a proposal to change the method of tunneling. 3 “A CICP is a formally written proposal for a contract change order.” The program provides an opportunity for “the contractor to use his expertise to improve the Contract performance to create an overall reduction in the total contract price.” If the proposal is approved by the awarding authority, the contractor shares in the cost savings.

When Affholder learned that Mitchell had submitted a CICP relating to the tunnel work, it demanded that Mitchell award Affholder a subcontract and include it in the CICP negotiations with the district. In April 2005, Affholder’s attorney sent Mitchell a letter warning that “any attempt by Mitchell Engineering to shop other bids for the tunnel work on the project will constitute a violation of [the Subcontracting Act].” Affholder stated that it was “willing to negotiate a change order reflecting the changes set forth in Mitchell Engineering’s CICP” and stated that it would pursue legal action if Mitchell did not “provide Affholder with a subcontract for the tunnel work on the project . . . .” Mitchell explained, “The work Affholder bid for and for which it was listed is being deleted by [the district]. Affholder is not entitled to a subcontract for change order work, or for work it did not bid, and for which it is not listed. There is no improper substitution.”

In May 2005, Mitchell confirmed with the district an agreement to use an “alternate tunneling method for the [project].” On June 1, 2005, Mitchell sent *515 Affholder and other approved tunnel contractors a request for proposals to perform the newly specified work. 4 Affholder did not submit such a proposal, instead continuing to insist that it was entitled to be awarded a subcontract to perform the originally specified work and then to negotiate a change order with Mitchell.

On June 23, 2005, the district issued “Change Order No. 1,” which provides, “In accordance with County Standard Specification § 9-3, this CICP changes the specified bid tunneling work. Specification sections 02320, 02330, and 02421 are deleted in their entirety and are replaced with new specification sections 02325, 02330, 02425 and 03620. Bid item No. 8 ‘108’ RCP Jackson Highway Crossing (Tunnel) in the amount of $3,510,000.00 is hereby deleted. Bid Item No. 9 ‘108’ RCP Morrison Creek Crossing (Tunnel) in the amount of $4,572,000.00 is hereby deleted. A new item titled ‘Open Face Shield Tunneling’ is hereby added in the amount of $4,082,000.00.”

On August 4, 2005, Affholder filed a superior court complaint alleging that Mitchell refused to award it a subcontract for the tunnel work in violation of the Act. After receiving Affholder’s complaint, Mitchell sent a letter to the district “respectfully requesting] the district confirm that in this situation, Affholder is not a ‘listed’ subcontractor on the above referenced contract, because the scope of work specified in Affholder’s bid was deleted by Change Order No. 1, and that Mitchell is not required to request a substitution for the performance of Change Order No. 1, by reason of Public Contract Code section 4107(c).” In December 2005, the district confirmed that “[o]nce change order #1 was adopted by the district, Mitchell Engineering was released from [its] contractually listed tunnel subcontractor.” In the same letter, the district also stated that it “has no objection to your chosen subcontractor Kiewit to perform the tunnel work .... Kiewit was chosen from the list of pre-approved tunnel contractors developed by the district for this work.” 5

*516 Mitchell moved for summary judgment and the court ultimately granted the motion. The court concluded that Mitchell did not violate the Act because “the district’s Change Order No. 1 deleted the work Affholder bid to perform and added new work which Affholder did not bid and was not listed to perform.” The court also found “[a]s a separate and independent basis for granting summary judgment, [that] to the extent that a triable issue of fact could be found as to whether all of Affholder’s work was deleted, and to the extent that a triable issue of fact could be found as to whether Kiewit Pacific performed work to which Affholder was entitled to perform, Mitchell still did not violate section 4107 because Mitchell asked the district to confirm that Affholder was not a ‘listed’ subcontractor and the district stated that ‘Once change order #1 was adopted by the district, Mitchell Engineering was released from [its] contractually listed tunnel subcontractor.’ ” 6 Affholder filed a timely notice of appeal.

Discussion

1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Synergy Project Mgmt., Inc. v. City & Cnty. of S.F.
244 Cal. Rptr. 3d 653 (California Court of Appeals, 5th District, 2019)
JMS Air Conditioning & Appliance Serv., Inc. v. Santa Monica Cmty. Coll. Dist.
242 Cal. Rptr. 3d 197 (California Court of Appeals, 5th District, 2018)
CA Bank & Trust v. Lawlor
California Court of Appeal, 2013
Cal. Bank & Trust v. Lawlor CA4/3
222 Cal. App. 4th 625 (California Court of Appeal, 2013)
Titan Elec. v. La Unified School Dist.
72 Cal. Rptr. 3d 570 (California Court of Appeal, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
63 Cal. Rptr. 3d 121, 153 Cal. App. 4th 510, 2007 Cal. App. LEXIS 1190, Counsel Stack Legal Research, https://law.counselstack.com/opinion/affholder-inc-v-mitchell-engineering-inc-calctapp-2007.