AEY, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJune 22, 2018
DocketASBCA No. 56470, 56471, 56472, 56473, 56591
StatusPublished

This text of AEY, Inc. (AEY, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AEY, Inc., (asbca 2018).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) AEY, Inc. ) ASBCA Nos. 56470, 56471, 56472 ) 56473, 56591 UnderContractNos. W91GY0-07-M-0815 ) W91GY0-07-M-0670 ) W91GY0-08-M-0010 )· W91GY0-08-C-0005 ) W91GY0-08-M-0040 )

APPEARANCES FOR THE APPELLANT: Jeff H. Eckland, Esq. Jared M. Reams, Esq. Eckland & Blando LLP Minneapolis, MN

APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq. Army Chief Trial Attorney MAJ Jason W. Allen, JA Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE O'SULLIVAN

AEY, Inc. (AEY) appeals from contracting officers' final decisions terminating a total of five contracts for cause, either partially or in full. The contracts were awarded by the Joint Contracting Command-Iraq (JCCI) in 2007 for arms and accessories for the Multi-National Security Transition Command in Iraq (MNSTC-I), ultimately destined for the use of the Security Forces of Iraq. We have jurisdiction under the Contract Disputes Act of 1978 (CDA), 41 U.S.<;. §§ 7101-7109. In large part, we sustain the appeals.

FINDINGS OF FACT

1. In chronological order of award, the five contracts at issue are: (1) Contract No. W91GY0-07-M-0670 (M-0670), awarded 29 July 2007 for a total amount of $4,645,785.84 (R4, tab l); (2) Contract No. W91GY0-07-M-0815 (M-0815), awarded 27 September 2007 for a total amount of $2,874,500.00 (R4, tab 3); (3) Contract No. W91GY0-08-M-0010 (M-0010), awarded 4 December 2007 for a total amount of $1,180,144.44 (R4, tab 24); (4) Contract No. W91GY0-08-C-0005 (C-0005), awarded 8 December 2007 for a total amount of $12,331,700.00 (R4, tab 5); and (5) Contract No. W91GY0-08-M-0040 (M-0040), awarded 17 December 2007 for a total amount of $1,192,915.60 (R4, tab 8). 2. Delivery for each contract line item number (CLIN) under these contracts was due no later than a specified number of days (usually 45 or 60) following AEY's receipt of the end user certificate (EUC) 1 for the item from JCCI (R4, tab 3 at 7, tab 5 at 2, tab 8 at 7, tab 24 at 5). The contracts required AEY to request an EUC from JCCI for each line item within three days of "receipt of order," which AEY interpreted to mean its supplier's receipt of AEY's order for the item, since the submitted EUC request had to identify the supplier (tr. 1/70-71). 2 The intended end users were the Security Forces of Iraq, under the Ministry of the Interior, the Ministry of Foreign Affairs, or the Ministry of Defense. Officials from one of these organizations would typically sign the EUC before delivering it back to JCCI for delivery to AEY. (Tr. 1/62-63) Delivery dates for each contract could and did vary by CLIN, depending on when AEY received an acceptable EUC for each item.

3. Each of the five contracts contained the Federal Acquisition Regulation (FAR) 52.232-4, CONTRACT TERMS AND CONDITIONS - COMMERCIAL ITEMS clause. Contracts M-0670, M-0815, M-0040, and M-0010 contained the FEB 2007 version of the clause. Contract C-0005 contained the FEB 2005 version of the clause. The following provisions of the clause are relevant to these appeals, and text appearing only in the FEB 2007 version is bracketed:

(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies ... at no increase in contract price. [If repair/replacement. .. will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services.] The Government must exercise its postacceptance [sic] rights ( 1) within a reasonable time after the defect was discovered or should have been discovered; and (2) before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

1 The EUC was essential to the process of obtaining an export license from the country in which the supplier of the arms or ammunition was located (tr. 1/60-61, 64). Because it was such an important document, AE Y's practice was to include a draft of the EUC along with each submitted request to ensure the accmacy of the EUC (tr. 1/61). 2 The government does not dispute this interpretation. 2 (t) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occun-ence.

(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

Contract Delivery Dates·

4. Contract M-0670 required delivery 45 days after receipt of EUC (R4, tab 1 at 6). It contained the following line items with country, date of receipt of EUC, and original contract delivery date indicated:

CLIN 000 I-universal laser bore sight system (20), complete with 4 adaptors, carrying pouch, batteries and instructions. EUC for U.S. received 6 September 2007 (R4, tab 27), making delivery due 22 October 2007.

CLIN 0002-Remington 870 Express 12 gauge shotgun (106), with three magazines. EUC for U.S. received 6 September 2007, making delivery due 22 October 2007.

3 ·CLIN 0003-Sniper Rifle, 7.62 x 5mm (48), to include 3 magazines, backup (adjustable) sights, bayonet mount. EUC for U.S. received 6 September 2007, making delivery due 22 October 2007.

CLIN 0004AA-AK-47 w/fixed stock (50-50 fixed/folding stock acceptable) (30,000), to include sling, 4 magazines, and cleaning kit. A corrected EUC for Montenegro for 16,000 AK-47s was received 15 October 2007 (R4, tab 46; tr. 1/161), making delivery due 29 November 2007. The EUC for the remainder of the AK-47s (14,000), sourced from Croatia, had to be re-done due to a missing import certificate, and the corrected EUC was not received until 3 April 2008 (R4, tab 108), making delivery due 19 May 2008.

CLIN 0004AB-AK-47s (100)-later terminated for convenience.

CLIN 0005-Tool kit, small arms repair (1). The record does not clearly establish when the U.S. EUC was issued.

CLIN 0006AA-DShK 12.7 x 107mm machine gun (287), to include 3 magazines and tripod. EUC for the Czech Republic was received on 28 February 2008 (R4, tab 99 at 2), making delivery due 14 April 2008.

CLIN 0006AB-DShK (2)-later terminated for convenience.

CLIN 0007AA-Machine gun light RPK 7.62 x 39mm (404), to include bipod and 3 magazines. A corrected EUC for Montenegro was received 15 October 2007 (R4, tab 46), making delivery due 29 November 2007.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
AEY, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/aey-inc-asbca-2018.