AeroVironment, Inc.

Armed Services Board of Contract Appeals·Decided March 30, 2016·No. ASBCA No. 58598, 58599·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) AeroVironment, Inc. ) ASBCA Nos. 58598, 58599 ) Under Contract No. W58RGZ-05-C-0338 )

APPEARANCES FOR THE APPELLANT: James J. Gallagher, Esq. Mary E. Buxton, Esq. Pillsbury Winthrop Shaw & Pittman LLP Los Angeles, CA

APPEARANCES FOR THE GOVERNMENT: E. Michael Chiaparas, Esq. DCMA Chief Trial Attorney Srikanti Schaffner, Esq. Carol L. Matsunaga, Esq. Trial Attorneys Defense Contract Management Agency Carson, CA

OPINION BY ADMINISTRATIVE JUDGE PEACOCK ON APPELLANT'S MOTION TO DISMISS AND THE GOVERNMENT'S MOTION TO AMEND PLEADINGS

AeroVironment, Inc. (appellant or AV) has filed a motion to dismiss the captioned appeals. AV alleges that all government claims disallowing costs (ASBCA No. 58599) and assessing penalties for inclusion of alleged expressly unallowable costs (ASBCA No. 58598) related to appellant's final incurred cost proposal for fiscal year (FY) 06 were resolved by settlement or payment and accordingly are moot. The government opposes dismissal and has filed a motion for approval to file amended answers (motion to amend) in both appeals allegedly to clarify the scope of its claims asserted in the contracting officer (CO) decisions from which these appeals were taken. Appellant alleges, inter alia, that the proposed amendments of the pleadings constitute new government claims beyond the scope of those asserted in the final decisions and are therefore beyond the Board's jurisdiction to address. We grant appellant's motion to dismiss and deny the government's motion to amend.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTIONS

1. On 22 February 2013, the Defense Contract Management Agency (DCMA or government) administrative contracting officer (ACO) issued two final decisions regarding A V's FY 06 final incurred cost proposal (ICP), dated 20 September 2006. One final decision (the Unallowability decision) disallowed various costs totaling $1,857,114. The amounts disallowed included over-cap executive compensation totaling $1,169 and misallocated taxes totaling $1,022,000, precisely in accordance with the conclusions in an underlying audit report prepared by the Defense Contract Audit Agency (DCAA). The Unallowability decision demanded repayment of all disallowed costs. (ASBCA No. 58599 (58599) R4, tab 4)

2. The second final decision (the Penalty decision) determined the disallowed compensation and tax costs to be expressly unallowable and assessed corresponding penalties of $429 for the $1, 169 over-ceiling executive compensation costs and $455,812 for the misallocated taxes (both as determined in the DCAA audit report). The Penalty decision demanded payment of those amounts plus the associated interest component of the penalty under FAR 42.709. (ASBCA No. 58598 (58598) R4, tab 4)

3. On 21March2013, AV timely appealed each decision. The appeal from the Penalty decision was docketed as ASBCA No. 58598 (sometimes referenced herein as the Penalty appeal) and the appeal from the Unallowability decision was docketed as ASBCA No. 58599 (sometimes referenced herein as the Unallowability appeal).

4. On 29 April 2013, AV filed its complaint in the Unallowability appeal averring in pertinent part:

VIII. AV'S FY 06 EXECUTIVE COMPENSATION COSTS DO NOT EXCEED THE CEILING ESTABLISHED BY FAR§ 31.205-6

35. In the Final Decision, the Government alleges that $1, 169 in AV' s FY 06 executive compensation costs exceed the ceiling for such costs established at FAR § 31.205-6(p).

36. AV's FY 06 executive compensation costs do not exceed the ceiling for such costs established at FAR § 31.205-6(p).

(58599, compl. at 8)

5. On 30 May 2013, the government filed its answer in the Unallowability appeal admitting the above allegations in the complaint, paragraph 35, "to the extent supported by the referenced Final decision" and alleging that the averments in the complaint, paragraph 36, stated conclusions of law and denying them to the extent that they may be deemed factual allegations (58599, answer at 5).

2 6. On 29 April 2013, appellant also filed its complaint in the Penalty appeal. As pertinent to our decision, the following sections of the complaint address the penalty related to alleged over-ceiling executive compensation costs:

VII. AV'S FY 06 EXECUTIVE COMPENSATION COSTS DO NOT EXCEED THE CEILING ESTABLISHED BY FAR§ 31.205-6

25. In the Final Decision, the Government alleges that AV is liable for the impact of its inclusion of$ I, 169 in FY 06 executive compensation costs that allegedly exceed the ceiling for such costs established at FAR § 31.205-6(p).

26. AV' s FY 06 executive compensation costs do not exceed the ceiling for such costs established at FAR § 3 I .205-6(p).

VIII. EVEN IF AV'S FY 06 EXECUTIVE COMPENSATION COSTS HAD EXCEEDED THE CEILING ESTABLISHED BY FAR§ 31.205-6, THE GOVERNMENT MUST WAIVE THE PENALTY

27. Under FAR§ 42.709-5(b), even ifthe Government's calculation of AV's FY 06 executive compensation costs was correct, and those costs exceeded the ceiling established at FAR § 3 I .205-6(p), which AV does not concede, the Government is required to waive the penalty because the allegedly expressly unallowable executive compensation costs at issue are less than $IO,OOO.

(58598, compl. at 6-7)

7. On 30 May 2013, the government also filed its answer in the Penalty appeal admitting the allegations in the complaint, paragraph 25, "to the extent supported in the referenced Final Decision" but otherwise denying paragraphs 25 through 27.

8. Following the filing of the pleadings in both appeals, the parties requested an approximate I I-month suspension of proceedings in both appeals and engaged in settlement discussions.

9. By letter dated 23 April 2014, the parties advised the Board that they had reached a partial settlement of the disputed issues in the Unallowability appeal and

3 requested that the suspension of the appeals be terminated to address the following remaining issues excepted from the settlement:

2. Unresolved Issues in ASBCA No. 58599:

a. Executive Compensation Costs In Excess of FAR 3 l .205-6(p) Cap -- $1,169

3. Unresolved Issues in ASBCA No. 58598:

a. Penalty per FAR 42.709 on Inclusion of Expressly Unallowable Federal Income Tax Cost of $1,022,000 in Indirect Cost Claim--$455,812

b. Penalty per FAR 42.709 on Inclusion in Indirect Cost Claim of $1, 169 in Executive Compensation Costs in Excess of FAR 3 l .205-6(p) Cap $429

c. Interest on Penalties $118,622.66

4. None of the issues in ASBCA No. 58598 were resolved by the parties.

10. On 14 August 2014, the parties executed a partial settlement agreement (First PSA). The First PSA stated in part:

[T]he Parties continue to dispute FY 06 executive compensation costs which the Government alleges are in excess of the cap established by FAR 3 l .205-6(p). Accordingly, the Parties hereby reserve their respective rights to litigate this issue before the ASBCA under Appeal No. 58599. The Parties also recognize that there are separate, unresolved penalties and interest issues pending in ASBCA No. 58598 related to the inclusion of overceiling executive compensation and federal income tax expenses in [AV' s] FY 2006 Incurred Cost Submission.

(Gov't opp'n, ex. G-1 at 4-5, ~ 6)

11. The appeals were consolidated by the Board. The parties elected Board-assisted mediation of the unsettled issues and entered into an Alternative Disputes Resolution (ADR) agreement detailing procedures for the conduct of the ADR mediation.

4 12.

Free access — add to your briefcase to read the full text and ask questions with AI

AeroVironment, Inc., (asbca 2016).

AeroVironment, Inc. (AeroVironment, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Tecom, Inc. v. The United States
732 F.2d 935 (Federal Circuit, 1984)
Placeway Construction Corporation v. The United States
920 F.2d 903 (Federal Circuit, 1990)
Applied Companies v. United States
144 F.3d 1470 (Federal Circuit, 1998)
K-Con Building Systems, Inc. v. United States
778 F.3d 1000 (Federal Circuit, 2015)