Aep Texas Central Company and T&D Solutions, Llc v. Marta Arredondo

Texas Supreme Court·Decided November 20, 2020·No. 19-0045·Published

Opinion

IN THE SUPREME COURT OF TEXAS ══════════

No. 19-0045

══════════

AEP TEXAS CENTRAL COMPANY AND T&D SOLUTIONS, LLC, PETITIONERS, v.

MARTA ARREDONDO, RESPONDENT ══════════════════════════════════════════ ON PETITION FOR REVIEW FROM THE COURT OF APPEALS FOR THE FOURTH DISTRICT OF TEXAS ══════════════════════════════════════════

Argued September 16, 2020

JUSTICE LEHRMANN delivered the opinion of the Court.

The issues presented in this personal-injury case include whether an electric utility owed a duty to ensure the safe performance of its independent contractor’s work and whether genuine issues of material fact exist with respect to the contractor’s own negligence. The court of appeals answered yes to both questions, resulting in a partial reversal of the trial court’s summary judgments in favor of the utility and the contractor. We hold that the utility did not retain control over the pertinent details of the contractor’s work and thus owed no duty that would otherwise flow from such control. However, we agree with the court of appeals that fact issues preclude summary judgment for the contractor. Accordingly, we affirm the court of appeals’ judgment in part and reverse it in part.

I. Background

AEP Texas Central Company is an electric utility. On July 1, 2012, AEP entered into a two-year contract with T&D Solutions, LLC, pursuant to which T&D was to supply to AEP on an as-needed basis “all supervision, labor, equipment and specified materials necessary to perform underground distribution line construction and/or maintenance services,” “underground distribution line construction and/or maintenance bid projects,” and “storm restoration services.” 1 The contract designated T&D an “independent contractor[] . . . solely responsible for the supervision, direction, and control of its employees and Subcontractors.” AEP contracted with another company, TechServ Consulting and Training Ltd., to inspect the work of AEP’s contractors, including T&D.

Pursuant to the T&D contract, AEP issued a work order that included a directive to T&D to remove a stub pole—a utility pole from which electric wires have been removed and the top portion cut off—located in a municipal right-of-way on the edge of Marta Arredondo’s property in Falfurrias, Texas. Removal of a stub pole involves “[p]ulling it out of the ground and returning it back to the yard, [and] filling the hole up with dirt.” T&D removed the pole and certified the job as complete on December 2, 2013. TechServ in turn certified the job as complete on December 9, 2013.

On July 30, 2014, Arredondo was injured while mowing her lawn when she stepped into a hole approximately two-and-a-half feet deep in the area where the pole had been removed. According to Arredondo, the grass in that area had grown tall because the pole had been left on

1 The “Contract Letter” the parties signed incorporated several additional documents that governed performance. References to the “contract” include all such documents.

the ground for some period of time before being hauled away. Arredondo “called the City” to report the issue, and an AEP employee was dispatched to the property to fill the hole.

Arredondo sued AEP, T&D, and TechServ for negligence, negligence per se, and gross negligence. Arredondo alleged that the defendants “had a utility easement” on her property and “created a defect in the easement property when they removed the pole and failed to fill the hole or otherwise warn of its existence.” The defendants each moved for no-evidence and traditional summary judgment, and the trial court granted all three motions. Arredondo appealed.

The court of appeals affirmed the summary judgment as to all claims against TechServ and as to the negligence per se and gross negligence claims against T&D. 567 S.W.3d 383, 388 (Tex. App.—San Antonio 2018). Arredondo did not file a petition for review, and those portions of the court of appeals’ judgment are thus final. TEX. R. APP. P. 53.1 (“A party who seeks to alter the court of appeals’ judgment must file a petition for review.”). The court of appeals reversed the trial court’s summary judgment as to the negligence claim against T&D and as to all claims against AEP, remanding the case to the trial court for further proceedings on those claims. 567 S.W.3d at 388. AEP and T&D filed petitions for review, which we granted. We address each petition in turn.

II. Contractor T&D’s Petition In holding that summary judgment was improper on Arredondo’s negligence claim against T&D, the court of appeals first held that the claim sounds in ordinary negligence rather than premises liability. Id. at 393; see Occidental Chem. Corp. v. Jenkins, 478 S.W.3d 640, 644 (Tex. 2016) (“Although premises liability is itself a branch of negligence law, it is a ‘special form’ with different elements that define a property owner or occupant’s duty with respect to

those who enter the property.”). The court further held that T&D owed Arredondo a duty to either warn of or make safe the hole it created by removing the utility pole. 567 S.W.3d at 394. Finally, the court did not address T&D’s argument that Arredondo failed to raise a fact issue as to whether T&D breached that duty, holding T&D waived the issue by raising it for the first time in reply to Arredondo’s summary-judgment response. Id. at 394 n.5.

In its petition for review in this Court, T&D takes no issue with the court of appeals’

holdings regarding the nature and scope of the duty T&D owed Arredondo. We thus express no opinion on that portion of the court of appeals’ analysis. Fort Worth Transp. Auth. v. Rodriguez, 547 S.W.3d 830, 849 (Tex. 2018) (“A petition for review must state all issues or points presented for review, and issues not presented in the petition for review are waived.” (citing TEX. R. APP. P. 53.2(f))). Instead, T&D focuses on the breach element of Arredondo’s negligence claim. See IHS Cedars Treatment Ctr. of DeSoto, Tex., Inc. v. Mason, 143 S.W.3d 794, 798 (Tex. 2004) (“The elements of a negligence cause of action are the existence of a legal duty, a breach of that duty, and damages proximately caused by the breach.”). Specifically, T&D contends that (1) the summary-judgment evidence conclusively establishes that T&D “properly filled the hole with dirt after it extracted the stub pole on Arredondo’s property” and thus that T&D did not breach any duty owed to Arredondo, and (2) T&D timely and properly raised that argument in its motion for summary judgment. As discussed below, we disagree with T&D’s characterization of the evidence and hold that a fact issue exists as to whether T&D failed to properly fill the hole. Accordingly, even assuming that T&D properly raised the breach issue in the trial court, the court of appeals correctly reversed summary judgment as to the negligence claim against T&D.

To be entitled to summary judgment, T&D had the burden to prove that no genuine issue of material fact exists and that T&D is entitled to judgment as a matter of law. Hillis v. McCall, 602 S.W.3d 436, 439–40 (Tex. 2020); TEX. R. CIV. P. 166a(c). 2 We review an order granting summary judgment de novo, taking as true all evidence favorable to the nonmovant and indulging every reasonable inference in the nonmovant’s favor. Valence Operating Co. v. Dorsett, 164 S.W.3d 656, 661 (Tex. 2005).

Free access — add to your briefcase to read the full text and ask questions with AI

Aep Texas Central Company and T&D Solutions, Llc v. Marta Arredondo, (Tex. 2020).

Aep Texas Central Company and T&D Solutions, Llc v. Marta Arredondo (Aep Texas Central Company and T&D Solutions, Llc v. Marta Arredondo) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Shell Oil Co. v. Khan
138 S.W.3d 288 (Texas Supreme Court, 2004)
Chon Tri v. J.T.T.
162 S.W.3d 552 (Texas Supreme Court, 2005)
Valence Operating Co. v. Dorsett
164 S.W.3d 656 (Texas Supreme Court, 2005)
Central Ready Mix Concrete Co. v. Islas
228 S.W.3d 649 (Texas Supreme Court, 2007)
Victoria Electric Cooperative, Inc. v. Williams
100 S.W.3d 323 (Court of Appeals of Texas, 2003)
Redinger v. Living, Inc.
689 S.W.2d 415 (Texas Supreme Court, 1985)
Fifth Club, Inc. v. Ramirez
196 S.W.3d 788 (Texas Supreme Court, 2006)
El Chico Corp. v. Poole
732 S.W.2d 306 (Texas Supreme Court, 1987)
Louisiana-Pacific Corp. v. Andrade
19 S.W.3d 245 (Texas Supreme Court, 1999)
Carter v. William Sommerville and Son, Inc.
584 S.W.2d 274 (Texas Supreme Court, 1979)
Koch Refining Co. v. Chapa
11 S.W.3d 153 (Texas Supreme Court, 2000)
Goolsby v. Kenney
545 S.W.2d 591 (Court of Appeals of Texas, 1976)
Clayton W. Williams, Jr., Inc. v. Olivo
952 S.W.2d 523 (Texas Supreme Court, 1997)
Ford Motor Co. v. Miles
967 S.W.2d 377 (Texas Supreme Court, 1998)
MCI Telecommunications Corp. v. Texas Utilities Electric Co.
995 S.W.2d 647 (Texas Supreme Court, 1999)
Gonzalez v. Ramirez
463 S.W.3d 499 (Texas Supreme Court, 2015)
Occidental Chemical Corp. v. Jenkins
478 S.W.3d 640 (Texas Supreme Court, 2016)
Fort Worth Transp. Auth. v. Rodriguez
547 S.W.3d 830 (Texas Supreme Court, 2018)
State v. Morello
547 S.W.3d 881 (Texas Supreme Court, 2018)