Aecon Buildings, Inc. v. Zurich North America

572 F. Supp. 2d 1227, 2008 U.S. Dist. LEXIS 59515, 2008 WL 3102923
CourtDistrict Court, W.D. Washington
DecidedAugust 4, 2008
DocketC07-832MJP
StatusPublished
Cited by20 cases

This text of 572 F. Supp. 2d 1227 (Aecon Buildings, Inc. v. Zurich North America) is published on Counsel Stack Legal Research, covering District Court, W.D. Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aecon Buildings, Inc. v. Zurich North America, 572 F. Supp. 2d 1227, 2008 U.S. Dist. LEXIS 59515, 2008 WL 3102923 (W.D. Wash. 2008).

Opinion

ORDER GRANTING PLAINTIFF’S MOTIONS FOR SUMMARY RE: BAD FAITH AND CPA VIOLATIONS

MARSHA J. PECHMAN, District Judge.

This matter comes before the Court on Plaintiff Aecon’s motions for summary judgment against Defendants Hartford and Zurich for bad faith and violations of the Washington Consumer Protection Act. (Dkt. Nos. 130 & 131.) Defendants oppose the motions. (Dkt. Nos. 160 & 162.) Having considered Plaintiffs motions, Defendants’ responses, Plaintiffs replies (Dkt. Nos. 176 & 177), all documents submitted in support thereof and the balance of the record, the Court GRANTS Plaintiffs motions for summary judgment.

Background

I. The Quinault Settlement and Ensuing Litigation

This insurance coverage action arises from claims made by the Quinault Indian Nation (“the Quinault”) against Aecon Buildings, Inc. (“Aecon”) regarding the construction of a casino and hotel project in Ocean Shores, Washington. Aecon was the general contractor for the project. Chinook Builders, Inc. (“Chinook”) and Western Partitions, Inc. (“Western Partitions”) were two of the subcontractors Ae-con hired to work on the project. Construction commenced in May 1998 and was substantially completed on June 9, 2000. (Dkt. No. 134, Blood Decl., Ex. 1 at ZC 000665.) In April 2004, the Quinault contacted Aecon alleging defects in the building structure that is part of the Quinault project. Under the contract between Ae-con and the Quinault, disputes between the parties were to be resolved through good faith mediation, if possible. If mediation failed, the parties agreed to binding AAA arbitration. (See Dkt. No. 105-2 at 73-74.) During the informal dispute resolution process, it became apparent that Aecon might be held responsible for defects in the work performed by a number of its subcontractors, who were not parties to the contract between Aecon and the Qui-nault or to the mandatory arbitration proceeding required under it. (First Amend. Compl. at 5.) In May 2005, Aecon sued the subcontractors in King County District Court. See Aecon v. Vandermolen Const., Cause No. 05-2-03044-5 SEA. 1 Aecon partially settled the Quinault’s claims in early June 2006 for approximately $1.9 million and fully and finally resolved the dispute on January 31, 2007, for $3.75 million after a final mediation proceeding. (Dkt. No. 105-10, 105-14.) In May 2006, Aecon also tendered the Quinault’s claims to the subcontractors and their insurers — Hartford and Zurich — who had added Aecon as “Additional Insureds” under their policies. 2 Hartford and Zurich both refused to defend or cover Aecon. Aecon initiated this suit against Hartford and Zurich in April 2007, claiming that Defendants breached *1231 their duty to defend and indemnify Aecon, breached their duty to act in good faith, and acted negligently. (Dkt. No. 3, Compl. at 25-26.) Aecon seeks declaratory relief and damages. (Dkt. No. 24, First Am. Compl. at 8-9.)

II. Tender to Subcontractors

Both of the subcontractors at issue in this litigation — Chinook (insured by Hartford) and Western Partitions (insured by Zurich) — entered into subcontract agreements with Aecon in which they agreed to defend and indemnify Aecon for claims arising out of their work and in which they agreed to list Aecon as an “Additional Insured” under their respective liability policies. (See Dkt. No. 110-5, Blood Decl., Ex. 1 at AEC 081767, 081769; Dkt. No. 105-4 at AEC 9229, 9231.)

A. Western Partitions / Zurich

On May 3, 2006, Aecon’s attorney Linda Chu tendered the Quinault’s claims against Aecon to Western Partitions and its insurer, Zurich, through a broker. (Dkt. No. 105-5.) On May 12, Aecon’s tender was assigned to and received by Zurich claims handler Caryn Kreman. (Dkt. No. 134, Blood Decl., Ex. 1 at ZC 000003.) On June 28, Ms. Kreman sent a letter to Aecon denying its tender of claims and indicating that she had not received any additional information from Aecon, including the underlying subcontractor agreement. (Id. at ZC 00020-23.) Between receipt of the tender on May 3 and denial on June 28, Ms. Kreman performed the following activities related to Aecon’s claim:

• May 12 — Reviewed insurance policy; called Linda Chu and left a message requesting additional information. (Id. at ZC 000003; id., Ex. 2 at 87, 90-92.)
• May 15 — Sent Ms. Chu a letter acknowledging tender and seeking additional information regarding a description of the work performed and the date of completion, a copy of the job file, and a copy of the Quinault’s claims; left voice mail with insurance broker seeking material Ms. Chu had enclosed with May 3 tender letter, but which Ms. Kreman had not received. (Id., Ex. 1 at ZC 000038; Ex. 2 at 87, 93-98.)
• May 15 — June 28 — -Draft letter denying tender (Id., Ex. 2 at 109-10, 115.)

On June 5, Ms. Chu sent additional information to Ms. Kreman, including the subcontractor files, the certificate of project completion, the Quinault’s expert’s reports documenting the damage to the project, and the Quinault’s counsel’s letters regarding future economic damages and legal fees. (Id., Ex. 1 at ZC 000213.) Ms. Kre-man’s claims notes do not reflect that she personally received those documents and she testified in her deposition that she probably did not receive them because she would have documented their receipt. (See id., Ex. 2 at 152-53). But Zurich’s records reflect that those documents were received by Zurich on June 8, 2006. (Id., Ex. 1 at ZC 000212.)

Regardless, Ms. Kreman testified in deposition that she did not need any additional information (and specifically did not need to investigate when any damage occurred) because it was clear to her from the claim itself that the claim was for “completed operations” and that therefore the policy did not cover Aecon as an additional insured because the subcontractor’s work had been completed and the project had been turned over to the Quinault before the damage occurred. (Id., Ex. 2 at 163-87, 213.) Ms. Kreman apparently believed that because the claim was assigned to her, and that neither she nor her “unit” handled ongoing operations claims, the damage to the project must have taken place after Western Partitions left the project. (Id. at 172, 251.) Aside from reading about it in Ms. Kreman’s deposition, *1232 Zurich’s 30(b)(6) deponent was not familiar with any such “unit.” (See id., Ex. 4, at 115-16.) Ms. Kreman admitted in her deposition that she believed she did not need to investigate any facts to make her determination. (Id. at 172, 180-81, 186-87, 213.) She testified that she believed that the “claim that was presented to [Zurich]” contained information documenting that water intrusion occurred only after Western Partitions left the job site, but she could not identify any document in the claim file that supported her belief. (Id. at 215-16.) She admitted that she did

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Becker v. Tig Insurance Company
W.D. Washington, 2022
Rodman v. Ethicon Inc
W.D. Washington, 2021
Bayley Construction v. Great American E & S Insurance
980 F. Supp. 2d 1281 (W.D. Washington, 2013)
Harris v. Extendicare Homes, Inc.
829 F. Supp. 2d 1023 (W.D. Washington, 2011)
Columbia Casualty Co. v. Gordon Trucking, Inc.
758 F. Supp. 2d 909 (N.D. California, 2010)
Aecon Bldgs. Inc. v. Vandermolen Const. Co.
230 P.3d 594 (Court of Appeals of Washington, 2010)
Aecon Buildings, Inc. v. Vandermolen Construction Co.
230 P.3d 594 (Court of Appeals of Washington, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
572 F. Supp. 2d 1227, 2008 U.S. Dist. LEXIS 59515, 2008 WL 3102923, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aecon-buildings-inc-v-zurich-north-america-wawd-2008.