AECOM Technical Services, Inc. v. Flatiron AECOM, LLC

District Court, D. Colorado·Decided March 28, 2024·No. 1:19-cv-02811·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLORADO Judge William J. Martínez

Civil Action No. 19-cv-2811-WJM-KAS

AECOM TECHNICAL SERVICES, INC.,

Plaintiff-Counterclaim Defendant,

v.

FLATIRON | AECOM, LLC,

Defendant-Counterclaim Plaintiff.

ORDER DENYING THE JOINT VENTURE’S CONSTRUED RULE 50 MOTIONS

The Court presided over an 18-day jury trial which began on January 29, 2024. On February 17, 2024, at the close of Plaintiff AECOM Technical Service, Inc.’s (“ATS”) case-in-chief, Defendant Flatiron AECOM, LLC (“Joint Venture” or “JV”) moved for judgment as a matter of law on ATS’s breach of contract claim pursuant to Federal Rule of Civil Procedure 50(a). (ECF No. 423 at 8.) The Court took the motion under advisement. On March 8, 2024, after resting its own case, the JV renewed its Rule 50(a) motion and additionally moved for judgment as a matter of law under Rule 50(a) on ATS’s affirmative defense of failure to mitigate damages. (ECF No. 446 at 110–13.) The Court took the motions under advisement and submitted the action to the jury, subject to the motions. (ECF No. 446 at 131.) On February 23, 2024, the jury returned a verdict in favor of ATS on its breach of 1 contract claim, as well as on the Joint Venture’s counterclaim. (ECF No. 441.) Given this verdict, the Court construes the Rule 50(a) motions as renewed motions for judgment as a matter of law under Rule 50(b). For the reasons below, both motions are denied.

I. LEGAL STANDARD Judgment as a matter of law is appropriate where “a party has been fully heard on an issue during a jury trial and the court finds that a reasonable jury would not have a legally sufficient evidentiary basis to find for the party on that issue.” Fed. R. Civ. P. 50(a)(1). Stated another way, “[a] directed verdict is justified only where the proof is all one way or so overwhelmingly preponderant in favor of the movant so as to permit no other rational conclusion.” Hinds v. Gen. Motors Corp., 988 F.2d 1039, 1045 (10th Cir. 1993). In reviewing a Rule 50 motion, the Court must draw all reasonable inferences in favor of the nonmoving party. Wagner v. Live Nation Motor Sports, Inc., 586 F.3d 1237, 1244 (10th Cir. 2009).

Where a party properly moves for judgment as a matter of law prior to the case being submitted to the jury, that party may renew the motion after the jury returns its verdict. See Fed. R. Civ. P. 50(b); Atchley v. Nordam Grp., 180 F.3d 1143, 1147–48 (10th Cir. 1999). In resolving a Rule 50(b) motion, the Court “will not weigh evidence, judge witness credibility, or challenge the factual conclusions of the jury.” Deters v. Equifax Credit Info. Servs., Inc., 202 F.3d 1262, 1268 (10th Cir. 2000). II. ANALYSIS A. ATS’s Breach of Contract Claim The JV argues that ATS has failed to satisfy two conditions precedent set forth in 2 Section 2.5 of the Subcontract for its breach of contract claim: (1) the condition precedent that every potential change order (“PCO”)1 must receive written authorization from the Design Change Control Board (“DCCB”); and (2) that every PCO must be outside the scope of work described in the Subcontract. (ECF No. 446 at 113.)

Section 2.5 of the Subcontract provides: 2.5 Design Change Control Board. The Parties agree on the establishment of a Design Change Control Board described on Attachment 1. Contractor shall not be obligated to make any payments to Designer for work performed which is outside the work scope described herein (“change”) or (“changes”), unless Designer has obtained the written authorization to perform the work for which the compensation is sought from the Design Change Control Board; provided, however Contractor may approve changes resulting in cost decreases or cost increases less than $50,000 so long as such approval is in writing executed by the Contractor’s project manager. When the Design Change Control Board authorizes change work it shall obtain a mutual agreement with the Designer on a cost for the work it authorizes and an adjustment in the Designer’s schedule. Contractor shall not have to pay more than the amount specified by the Design Change Control Board for the change work authorized without further action by the Design Change Control Board, subject also to the dispute resolution process. The Design Change Control Board shall authorize payments for Contractor directed changes and for changes which Owner acknowledges are its responsibility. Payment shall be made when the work is performed for such Contractor directed changes and for changes which Owner acknowledges are its responsibility. For changes which the Parties believe are the Owner’s responsibility but which the Owner has not acknowledged as its responsibility, payment shall be made when payment is received from Owner which may not occur (if it occurs at all) until after a determination that there was an Owner directed change by the dispute resolution procedures contained in the Design/Build Contract. Designer specifically agrees to accept the risk that

1 At times, the parties refer to PCOs as “proposed” change orders. The Court sees the terms “proposed” and “potential” as interchangeable, and their alternate use does not affect the outcome of this Order. 3 changes which the Parties believe to be Owner directed and which are approved for payment by the Design Change Control Board at Designer’s request may not be found to be Owner’s responsibility in the dispute resolution procedures and therefore not paid for by the Owner, provided that such changes are sufficiently itemized by the Contractor and adjudicated by the Owner separate from other changes. For work approved by the Design Change Control Board and identified as the Contractor’s responsibility, Contractor shall pay Designer for such changes as Additional Design Services. Designer’s invoices to Contractor for the costs of its subcontractors who perform work approved by the Design Change Control Board shall be compensated as Additional Design Services. Such costs of Designer’s subcontractors shall not be further marked up by Designer. For work approved by the Design Change Control Board and identified as the Owner’s responsibility, Contractor shall pay Designer on the same basis as Contractor is permitted to bill Owner for the services Designer performs under the terms of the Design/Build Contract and such payment shall be subject to Sections 2.6 and 2.7.

(ECF No. 37-3 at 21–22 (italics added).) First, the Joint Venture argues that there is no evidence in the record that ATS satisfied the condition precedent that it obtained written authorization from the DCCB to perform the work for which it seeks compensation. (ECF No. 423 at 9; ECF No. 446 at 113.) Further, the JV argues that ATS never presented evidence that it was “somehow thwarted from working toward forming the DCCB or that the JV somehow frustrated that process.” (ECF No. 446 at 115–18.) To the contrary, the JV argues that summary exhibit P3662 demonstrates that all of the PCOs were submitted to the JV before the lawsuit was filed on October 2, 2019, over four months before ATS filed suit, and there is no dispute that the DCCB was in effect at that time. (ECF No. 446 at 118.) However,

Free access — add to your briefcase to read the full text and ask questions with AI

AECOM Technical Services, Inc. v. Flatiron AECOM, LLC, (D. Colo. 2024).

AECOM Technical Services, Inc. v. Flatiron AECOM, LLC (AECOM Technical Services, Inc. v. Flatiron AECOM, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Olano
507 U.S. 725 (Supreme Court, 1993)
Atchley v. Nordam Group, Inc.
180 F.3d 1143 (Tenth Circuit, 1999)
Deters v. Equifax Credit Information Services, Inc.
202 F.3d 1262 (Tenth Circuit, 2000)
Wagner v. Live Nation Motor Sports, Inc.
586 F.3d 1237 (Tenth Circuit, 2009)
McGill v. DIA Airport Parking, LLC
2016 COA 165 (Colorado Court of Appeals, 2016)