AECOM Technical Services, Inc.

CourtArmed Services Board of Contract Appeals
DecidedDecember 6, 2021
DocketASBCA No. 62800
StatusPublished

This text of AECOM Technical Services, Inc. (AECOM Technical Services, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AECOM Technical Services, Inc., (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) AECOM Technical Services, Inc. ) ASBCA No. 62800 ) Under Contract No. W912DY-15-R-ESP7 )

APPEARANCES FOR THE APPELLANT: Manju Gupta, Esq. William D. Edwards, Esq. Jonathan R. King, Esq. Ulmer & Berne LLP Cleveland, OH

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Karen L. King Vanek, Esq. Margaret P. Simmons, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Huntsville

OPINION BY ADMINISTRATIVE JUDGE MCILMAIL ON THE GOVERNMENT’S MOTION TO DISMISS FOR LACK OF JURISDICTION

Appellant, AECOM Technical Services, Inc., requests $681,469.70, alleging both a written contract and a contract implied-in-fact with the U.S. Army Corps of Engineers (compl. at 1 ¶ 2, 7-8). The government moves to dismiss the appeal for lack of jurisdiction, 1 saying it never had a contract with AECOM, and that the Board does not possess jurisdiction to entertain AECOM’s wrongful conversion claim (gov’t mot. at 1, 9, 12).

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

On May 8, 2015, the government awarded Contract No. W912DY-15-D-0040 to AECOM (gov’t mot., attach. 4 at 34). The contract states that “[t]he objective of this acquisition is for the design, construction, and operation of energy savings projects to help meet mandated energy savings goals established in the Energy Policy Act of 1992,” and that the government “is awarding multiple Indefinite Delivery/Indefinite Quantity

1 In conjunction with its jurisdictional motion, the government moved to dismiss portions of the appeal for failure to state a claim upon which relief may be granted, which motion will be addressed separately. (ID/IQ) type contracts to both large and small businesses” (id. at 35 §§ A.1, A.2). The contract provides:

Multiple Award Task Order Contract (MATOC) Capacity: The estimated programmatic capacity for the MATOC is $1.5 Billion. The total capacity will be shared among all awardees in the MATOC pool, both large and small businesses.

(Id. ¶ A.3) On July 13, 2015, the government issued a “Request for Proposal (RFP), W912DY-15-R-ESP7, Buckley AFB, CO” to “All Energy Savings Performance Contracting (ESPC) III MATOC Contractors” that states:

In accordance with paragraph H.2 of the CEHNC ESPC III Base Contract, “Procedures for Awarding Task Orders,” your firm is invited to submit a proposal for the efforts contained in Attachment 1, Performance Work Statement (PWS), for an Energy Savings Performance Contracting (ESPC) project anticipated at Buckley AFB, CO.

(Gov’t mot., attach. 1 at 1) On September 30, 2015, the government issued to AECOM “Solicitation W912DY-15-R-ESP7, Energy Savings Performance Contract (ESPC), Buckley AFB, CO,” informing AECOM that it “ha[d] been selected as the Energy Savings Performance Contractor for the new ESPC Buckley AFB project” (gov’t mot., attach. 6 at 196 (emphasis added)), and authorized AECOM “to proceed with Preliminary Assessment (PA) development and submission for the new ESPC project at USAF Buckley AFB” (gov’t mot., attach. 7 at 197). The government further informed AECOM that “[y]our company shall perform the PA in accordance with Sections C.5.3 and C.5.4 of the base IDIQ” (id.).

On February 17, 2016, the government “authorize[d] AECOM to proceed with the IGA/Feasibility Study, Design, and Price Proposal submission to include detailed cost and pricing data, for the Energy Conservation Measures (ECM) [] for the ESPC project at Buckley AFB, Denver, CO” (gov’t mot., attach. 8 at 198). On March 24, 2016, the government “authorize[d] AECOM to proceed with the IGA/Feasibility Study, Design, and Price Proposal submission to include detailed cost and pricing data” for additional ECMs (gov’t mot., attach. 9 at 202). On November 22, 2016, the government informed AECOM that it “ha[d] decided to not pursue this ESPC project, and has no plans to exercise its option to obtain ownership of any submitted documentation pertinent to this project issued in the NTP dated 17 Feb, 2016 for the ESPC project at Buckley AFB, Denver, CO” (gov’t mot., attach. 10 at 204).

2 On August 26, 2020, AECOM presented to the contracting officer a certified claim “for recovery of $681,469.70 in costs AECOM has incurred in connection with the work performed to develop and design the Project” (gov’t mot., attach. 5 at 156). On December 3, 2020, the contracting officer denied AECOM’s claim (gov’t mot., attach. 16 at 239). The contracting officer stated:

Per Section C Para 5.5 of AECOM’s Base Contract numbered W912DY-15-D-0400, . . . “the Government will not be subject to any costs associated with the feasibility study unless the Government exercises its option to obtain ownership of the submitted documentation.

(Id. at 240 (emphasis added))

In its notice of appeal to the Board, AECOM states (emphasis added):

AECOM Technical Services, Inc. (“AECOM”), by and through counsel, hereby appeals the decision of contracting officer, Adam R. Sunstrom, dated December 3, 2020, a copy of which is attached as Exhibit A. The contracting officer denied AECOM’s claim under Energy Savings Performance Contract No. W912DY-15-R-ESP7 with Huntsville Center, U.S. Army Corps of Engineers (“CEHNC”) (the “Contract”).

(Gov’t mot., attach. 17 at 241) (emphasis added)) And in its complaint, AECOM alleges the following:

Since 2008, AECOM has been a prequalified energy services contractor (“ESCO”) for CEHNC for energy savings performance contracts (“ESPCs”) under indefinite delivery/ indefinite quantity multiple award task order contracts (“MATOC”) No. W912DY-15-D-0040. The MATOC is currently in its third contract iteration (“MATOC III”).

On July 13, 2015, [the government] sought a proposal from AECOM and other MATOC III holders via Request for Proposal (“RFP”) No. W912DY-15-R-ESP7 for the development and implementation of energy conservation projects at Buckley Air Force Base, Colorado (the “Project”).

....

3 After nearly 14 months of work on the Project, including multiple changes to the scope of the Project made with CEHNC’s constant assurance of an impending TO [Task Order] award, and less than one (1) month before the scheduled TO award date, CEHNC sent AECOM a letter on November 22, 2016, cancelling the Project.

Appellant’s claims, which were submitted to the [contracting officer] in AECOM’s certified claim [include] . . . AECOM is entitled to the fair market value of services provided to the government under an implied-in-fact contract.

(Gov’t mot., attach. 18 at 245-46 ¶¶ 3-4, 246 ¶ 9, 248 ¶ 19) (emphases added))

DECISION

The government says that we lack jurisdiction to entertain the appeal because, it says, it never had a contract with AECOM (gov’t mot. at 8, 11). 2 Pursuant to the Contract Disputes Act, 41 U.S.C. § 7105(e)(1)(A) (emphasis added), the Board “has jurisdiction to decide any appeal from a decision of a contracting officer of the Department of Defense, the Department of the Army, the Department of the Navy, the Department of the Air Force, or the National Aeronautics and Space Administration relative to a contract made by that department or agency.” Jurisdiction under this provision requires no more than a non-frivolous allegation of a contract with the government. Siemens Gov’t Techs., Inc., ASBCA No. 62806, 2021 WL 4395475 (Sept. 15, 2021). Thus, to establish Board jurisdiction under this provision, an appellant need only allege the existence of a contract. Id. This bar is low. Id.

Based upon the record material set forth above, we conclude that AECOM has set forth a non-frivolous allegation of a contract with the government, whether that contract be “Base Contract No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Travelers Indemnity Co. v. United States
35 Cont. Cas. Fed. 75,607 (Court of Claims, 1988)

Cite This Page — Counsel Stack