AECOM Technical Services, Inc.

CourtArmed Services Board of Contract Appeals
DecidedFebruary 7, 2022
DocketASBCA No. 62800
StatusPublished

This text of AECOM Technical Services, Inc. (AECOM Technical Services, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AECOM Technical Services, Inc., (asbca 2022).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) AECOM Technical Services, Inc. ) ASBCA No. 62800 ) Under Contract No. W912DY-15-R-ESP7 )

APPEARANCES FOR THE APPELLANT: Manju Gupta, Esq. William D. Edwards, Esq. Jonathan R. King, Esq. Ulmer & Berne LLP Cleveland, OH

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Karen L. King Vanek, Esq. Margaret P. Simmons, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Huntsville

OPINION BY ADMINISTRATIVE JUDGE MCILMAIL ON THE GOVERNMENT’S MOTION TO DISMISS FOR FAILURE TO STATE A CLAIM

On December 6, 2021, the Board denied the government’s motion to dismiss this appeal for lack of jurisdiction, holding that appellant, AECOM Technical Services, Inc. (AECOM), had set forth a non-frivolous allegation of a contract with the government, and that AECOM’s allegations that the government wrongfully converted AECOM’s designs and work product for its own use was a claim of tortious breach of contract that we possess jurisdiction to entertain. AECOM Technical Services, Inc., ASBCA No. 62800, 2021 WL 6103547 (Dec. 6, 2021). Familiarity with that opinion is presumed. The government had also moved to dismiss Counts II and IV of the complaint for failure to state a claim (gov’t mot. at 11-15). We deferred decision upon that motion, and address it now.

Count II alleges:

Count II: CEHNC Is Required To Pay AECOM Fair Compensation for the Value of Its Goods and Services, Including Termination for Convenience Costs

27. [Multiple Award Task Order Contract (MATOC)] III expressly includes [Federal Acquisition Regulation (FAR)] clause 52.249-2, which provides that [Huntsville Center, U.S. Army Corps of Engineers (CEHNC)] is to compensate AECOM for the fair value of services provided and received by CEHNC. When the government cancels a contract for its convenience, the government contractor may claim certain damages as provided for in the contract’s termination for convenience clause, such as costs expended prior to termination, lost profits on work actually completed, and any professional fees incurred towards the preparation and presentation of a termination settlement.

28. FAR 49.201 provides that a terminated contractor must receive fair compensation. AECOM’s recovery of precontract costs to perform the contract are justified because AECOM fully relied upon CEHNC’s repeated assurances of an impending [task order (TO)] award issuance. AECOM accommodated all of the changes requested by CEHNC because, in part, the value of the cost savings was anticipated to be significant and would have been paid over the life of the contract, and AECOM was delivering the Project requirements as directed by CEHNC.

29. The government has acknowledged the inequities of cancelling viable projects after the [Investment Grade Audit (IGA)], including the potential liability for certain costs. Specifically, in an October 22, 2019, guidance letter, the Deputy Assistant Secretary of the Air Force for Environment, Safety, and Infrastructure (SAF/IEE) wrote as follows:

Project Cancellation after IGA: Should the Installation Commander recommend cancellation or it is thought to be in the best interest of the Air Force to cancel or reduce the scope of the project due to a technically non-responsive submittal by the contractor, a cancellation notification must be provide [sic] to SAF/IEE via memorandum to include explanation. All other cancellation requests must submit to the Headquarters Air Force Facility Energy and Water Board (FEWB) via memorandum an explanation of level of effort, timeline, and detailed cause for cancellation. In the event of a cancellation, the installation may be liable to the contractor for IGA or other development expenses. If viable projects are cancelled after the IGA, the installation will not be authorized to select high return ECMs from an IGA report and

2 accomplish those ECMs as independent Government funded projects.

30. Once AECOM reached the latter stages of the IGA phase and was close to a CEHNC-assured TO, AECOM never envisioned that it would spend the time and resources that it did in direct response to government directions and not be awarded a TO. It would be contrary to law and equity for ESPC contracts to have such a loophole that would allow CEHNC to obtain such benefits without providing any compensation to an [energy services contractor (ESCO)].

WHEREFORE, AECOM prays for judgment in its favor and against CEHNC as to Count II in an amount of at least $681,469.70, together with costs incurred in making demands upon CEHNC for payment, plus interest, attorney fees, costs and for such further relief as the ASBCA deems appropriate.

(Compl. at 5-6 (bracketed material added)) Count IV alleges:

Count IV: CEHNC Breached the Contract by Wrongfully Converting AECOM’s Work Product and Intellectual Property for Its Own Use

35. CEHNC breached the contract when it violated the implied duty of good faith and fair dealing and MATOC III, Section C.26.4, by converting AECOM’s ECM designs and work product for its own use. As stated previously, CEHNC’s statement that it “has no plans to exercise its option to obtain ownership of any submitted documentation pertinent to this project” is disingenuous. CEHNC has never returned AECOM’s submitted documentation, which contained hundreds of pages of design, measurement, calculation analysis and cost estimating documents. The Base’s own news articles elaborate on the importance of energy efficiency and demonstrate that CEHNC used AECOM’s ideas and designs to implement ECMs after CEHNC cancelled the Project.

WHEREFORE, AECOM prays for judgment in its favor and against CEHNC as to Count IV in an amount of at least $681,469.70, together with costs incurred in making demands

3 upon CEHNC for payment, plus interest, attorney fees, costs and for such further relief as the ASBCA deems appropriate.

(Compl. at 7-8)

Dismissal for failure to state a claim upon which relief can be granted is appropriate where the facts asserted in the complaint do not entitle the claimant to a legal remedy; the Board will deny a motion to dismiss for failure to state a claim when the complaint alleges facts plausibly suggesting a showing of entitlement to relief. See Parsons Gov’t Servs., Inc., ASBCA No. 60663, 17-1 BCA ¶ 36,743 at 179,100. In deciding a motion to dismiss for failure to state a claim, the Board must accept well-pleaded factual allegations as true and must draw all reasonable inferences in favor of the claimant; we decide only whether the claimant is entitled to offer evidence in support of its claims, not whether the claimant will ultimately prevail. Id. at 179,101. In addition to reviewing the allegations contained in the complaint, the Board may consider matters incorporated by reference or integral to the claim, items subject to judicial notice, and matters of public record. Parwan Grp. Co., ASBCA No. 60657, 18-1 BCA ¶ 37,082 at 180,498 (considering contract terms in deciding Rule 12(b)(6) motion). Here, MATOC III is referenced in the complaint and integral to AECOM’s claim; accordingly, we may consider it in deciding the government’s motion. See id. (considering contract terms in deciding Rule 12(b)(6) motion).

With respect to Count II, the government argues that “[a]ppellant fails to state a claim under which relief can be granted because it cannot and has not alleged that the Government terminated any contract cognizable under the [Contract Disputes Act]” (gov’t mot. at 12 (alteration added)). In view of our earlier decision that AECOM has set forth a non-frivolous allegation of a contract with the government, we deny the government’s motion to dismiss Count II for failure to state a claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
AECOM Technical Services, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/aecom-technical-services-inc-asbca-2022.