Advanced Technology Corp. v. Eliskim, Inc.

87 F. Supp. 2d 780, 2000 U.S. Dist. LEXIS 2647, 2000 WL 268012
CourtDistrict Court, N.D. Ohio
DecidedFebruary 28, 2000
Docket1:96CV755
StatusPublished
Cited by8 cases

This text of 87 F. Supp. 2d 780 (Advanced Technology Corp. v. Eliskim, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Advanced Technology Corp. v. Eliskim, Inc., 87 F. Supp. 2d 780, 2000 U.S. Dist. LEXIS 2647, 2000 WL 268012 (N.D. Ohio 2000).

Opinion

MEMORANDUM AND ORDER

ANN ALDRICH, District Judge.

Plaintiff Advanced Technology Corporation (“ATC”) brings this action seeking cost recovery and, in the alternative, contribution from defendant Eliskim, Inc. for response costs incurred by ATC under the Comprehensive Environmental Response Compensating and Liability Act of 1980, as amended, 42 U.S.C. § 9601, et seq. (“CERCLA”). ATC also seeks declaratory relief that Eliskim is liable for future response costs. Both parties have filed motions for summary judgment. For the reasons that follow, ATC’s motion for summary judgment (Doc. # 41) is granted in part and denied in part, and Eliskim’s motion for summary judgment (Doc. # 37) is granted in part and denied in part.

ATC has three remaining claims against Eliskim: 1) Cost recovery under CERCLA § 107(a); 1 2) contribution under § 113(f)(1); and 3) declaratory relief. Both parties ask for summary judgment on the first two claims, and Eliskim also asks for summary judgment on ATC’s declaratory relief claim. For the reasons explained below, summary judgment is inappropriate on ATC’s § 107(a) claim because there are disputed issues of material fact. As to ATC’s seeond claim, this Court finds that ATC is entitled to contribution from Eliskim under § 113(f)(1); however, there are disputed issues of material fact as to whether Eliskim’s contribution should be complete, partial, or nothing. Finally, summary judgment is granted in favor of Eliskim on ATC’s declaratory relief claim, and that claim is dismissed.

1. Background

Eliskim, formerly known as True Temper Corporation, 2 owned a parcel of land referred to in this litigation as the “True Temper Site” from 1902 until 1980. 3 The True Temper Site is located in Ashtabula County, Geneva, Ohio and is approximately 49 acres in size. In 1980, Eliskim sold a portion of the True Temper Site to Northeast Realty & Investments, Inc. (“Northeast”). Northeast then sold 15.5 acres to ATC, which ATC still owns. Eliskim currently owns 19.44 acres of the True Temper Site.

At some point in time prior to 1980, Eliskim’s manufacturing activities on the True Temper Site resulted in lead contamination of the soil. Some of this lead contamination occurred on the property currently owned by ATC, including an area of land surrounding a quonset hut. How much knowledge anyone, including ATC and Northeast, had of this contamination in 1980-81 is unclear. ATC had knowledge that some portions of the True Temper Site had environmental problems, because an 18.43 acre parcel that Northeast originally planned to purchase from Elisk-im and then sell to ATC was “held back” because necessary approvals were not ac *783 quired from the Environmental Protection Agency. However, the eventual sales contract between ATC and Northeast included provisions stating that Eliskim was responsible for all hazardous waste on the property ATC was purchasing and that Eliskim would remove any such waste by April 5, 1981. Further, ATC represents to this Court that they reasonably believed that the land that they purchased was not contaminated and that the contamination was limited to the 18.43 acres that were not purchased. The record available to the Court contains little additional evidence on these issues.

At some time in 1993, the Ohio Environmental Protection Agency (“OEPA”), with ATC’s permission, collected soil samples in the vicinity of the quonset hut and found lead in the soil at levels up to 1,490 parts per million (ppm). In 1994, the OEPA conducted an expanded site investigation of the True Temper Site and collected additional soil samples from the area in and around the quonset hut; this sampling revealed lead contamination as high as 2,260 ppm. However, while the OEPA did its sampling on ATC’s property with ATC’s permission, there is no evidence in the record indicating to what extent, if any, the OEPA communicated its findings to ATC and, if so, what if any directions or advice the OEPA gave to ATC regarding the contamination and/or use of the property. Further, ATC has represented to this Court that it was not aware of any lead contamination until informed of that fact by the United States Environmental Protection Agency (“EPA”) later that year, as described below.

On August 23, 1994, the EPA visited the True Temper site and discovered ATC in the process of demolishing the quonset hut. These actions exposed lead contaminated soils, and the EPA concluded that there was a risk of the lead contaminated soil becoming airborne, thereby threatening the safety of surrounding residents, employees of nearby businesses, and students at a neighboring elementary school. The EPA decided that immediate action was needed and entered into an Administrative Order of Consent with ATC (“AT-CAOC”) directing ATC to remove from the property hazardous soil that exceeded 300 ppm lead.

In the spring of 1995, ATC excavated an area of approximately 100 feet by 150 feet to an average depth of 1.5 to 2 feet. At this point ATC asked the EPA that they be allowed to stop work. In June of 1995, the EPA notified ATC that their removal action had abated the inhalation risk posed by the lead contaminated surface soils and approved ATC’s close out plan, noting that the remaining contaminated soils would be addressed in a non-time critical removal action. There are disputed questions of fact as to the extent to which ATC complied with the original terms of the AT-CAOC. There are also questions of fact regarding whether the original goal of the ATCAOC, to remove soil with contamination in excess of 300 ppm lead, was an unreasonably stringent clean-up level.

In 1997, Eliskim entered into an Administrative Order of Consent with the EPA (“ELIAOC”) to remove hazardous contaminants, including lead, from the True Temper Site. The area of the clean-up included portions of land owned by ATC. In the ELIAOC, Eliskim was required to remove soil contaminated with lead in excess of I,387 ppm.

II. Summary Judgment Standard

Under Federal Rule of Civil Procedure 56(c), summary judgment is appropriate “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed.R.Civ.P. 56(c). The moving party bears the initial burden of demonstrating the absence of a genuine issue of material fact. Celótex Corp. v. Catrett, 477 U.S. 317, 323-25,106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). The burden then shifts to the non-moving party to demonstrate the existence *784 of a material dispute as provided in Rule 56(e):

....

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pearson v. Ewing
2014 Ohio 645 (Ohio Court of Appeals, 2014)
State v. Howe Cleaners, Inc.
2010 VT 70 (Supreme Court of Vermont, 2010)
United States v. Domenic Lombardi Realty, Inc.
204 F. Supp. 2d 318 (D. Rhode Island, 2002)
United States v. Chrysler Corp.
157 F. Supp. 2d 849 (N.D. Ohio, 2001)
City of Wichita v. Aero Holdings, Inc.
177 F. Supp. 2d 1153 (D. Kansas, 2000)
Advanced Technology Corp. v. Eliskim, Inc.
96 F. Supp. 2d 715 (N.D. Ohio, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
87 F. Supp. 2d 780, 2000 U.S. Dist. LEXIS 2647, 2000 WL 268012, Counsel Stack Legal Research, https://law.counselstack.com/opinion/advanced-technology-corp-v-eliskim-inc-ohnd-2000.