Adams v. Houston & Texas Central Railway Co.

7 S.W. 729, 70 Tex. 252
CourtTexas Supreme Court
DecidedMarch 16, 1888
DocketNo. 2475-5437
StatusPublished
Cited by42 cases

This text of 7 S.W. 729 (Adams v. Houston & Texas Central Railway Co.) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Adams v. Houston & Texas Central Railway Co., 7 S.W. 729, 70 Tex. 252 (Tex. 1888).

Opinion

Station, Chief Justice.

■ This is an action of trespass to try title, prosecuted by S. J. Adams, in his own right, and as executor of the last will of J. L. Leonard, to recover one hundred and five sections of land located and surveyed for them by valid alternate certificates owned by them. The appellee claims the land by virtue of surveys made for it prior to the time the locations and surveys were made for Adams & Leonard. The cause was tried without a jury and the conclusions of fact found show fully the nature of the controversy between the parties. The conclusions are as follows:

“1. The land certificates under which the plaintiff claims were issued October 10, 1879, to the Dallas & Wichita Railroad Company, and were, by the company, conveyed to Adams & Leonard. The plaintiff represents the ownership of Adams*& Leonard.
2. The said certificates were regularly located June and July, 1880, upon the land sued for, surveys made January, 1881; field notes and certificates were returned to and filed in the land office in February, 1881. These field notes and certificates remain in the land office.
3. The plaintiff shows title sufficient to recover upon unless the land had been previously appropriated by the defendant by. files, locations, surveys, etc., of which the plaintiff had notice before their locations were made.
4. July 1, 1872, certain land certificates were issued by the State to the defendant. Some -of these certificates are the basis of the claim of the defendant to the land in controversy.
[256]*2565. After the issuance of these certificates the defendant caused its agent to set about locating them. In so doing, the agent, Elgin, from the maps in the office of the surveyor of Jack Land District, ascertained the existence of a large body of vacant land, of irregular shape, and of area not well ascertained. This land was known in general direction to be west and northwest of the mouth of Miller’s creek, a tributary falling into the Brazos on its right bank. This vacancy was pointed out by said agent to the surveyor of said land -district for survey under, and by virtue of land certificates belonging to defendant, and then in the office of said surveyor, and the legal appropriation of said vacancy was attempted by locating-thereon the certificates of the defendant. Partial surveys were made, and the agent, to secure the land from others, made files on August 5 and on November 28, 1872. These files were made in accordance with the map in the surveyor’s office, taking them as correct. The files made November 28, do not call for each other, but were made upon calls on said map, which, had the map been correct, would have placed the files so as to form a connected block, and to include the vacancy sought to-be appropriated, as was the intent of the defendant in making surveys and files. These were of eighteen certificates of six hundred and forty acres each, calling for a survey dependent for location upon the mouth of Miller’s creek, one hundred and sixty-three certificates, thirty-nine, twenty-five and forty-seven —total, three hundred and twenty-eight certificates making a block. A file was made August 5,1872, of seventy-five six hundred and forty acre certificates in a body, not connected with the later files, but dependent, also, upon said map for its locality.
Surveys were made (some before the date of the files, November 28), and in a block of surveys resembling in outline the apparent vacancy so ascertained and pointed out for location, by virtue of certificates of the defendant. (This block of surveys was west of the mouth of Muggins’s creek, about ten miles southeast of the mouth or Miller’s creek. There seems to have been a mistake, taking Muggins's creek for Miller’s.) Field notes of these surveys were approved and recorded in ¡the surveyor’s office; and the field notes, together with the , certificates by virtue of which the surveys were made, were I returned to and filed in the land, office in October and November, 1872, and they still remain in the land office.
[257]*2576. Subsequent to the return of these surveys and certificates of the land office, it became known in the land office and to the defendant that by reason of a mistake made as to connections and initial point of said surveys (sho.wn to have been caused by want of correct maps and consequent inability to obtain proper calls) a part of them conflicted with land previously appropriated by other certificates and surveys. The extent of such conflict was not known until ascertained by an actual survey of the territory as noted hereafter.
7. Upon discovering that there was a mistake, as the surveys could not be placed on the land office maps, upon vacant lands, as shown in the land office, the defendant employed one Dennis Corwin, a skillful surveyor, to make an actual survey of the territory in which defendant was seeking to locate its certificates. Early in the year 1873, Corwin went upon the land and ascertained the metes and bounds of the vacancies sought to be appropriated.
8. When Corwin had ascertained the facts and had acquired • the necessary knowledge of the true locality of the land the defendant was seeking to appropriate, he was appointed deputy surveyor of the land district in which the land was included, without having in his possession the certificates of the defendant (which were in the land office) or copies of them. Early in the year 1873 he proceeded to make surveys upon vacant public land (the same the defendant had attempted to file upon) in the name of said certificates of the defendant, which certificates, by mistake, had been surveyed upon other and located land. The surveyor made two surveys of six hundred and forty acres to each certificate—the certificates being what are called alternates. The field notes of these surveys bear date November and December, 1873, and they were approved and recorded in the surveyor’s office, and they were returned to the land office in May, 1874, and were filed in June, 1874, in said office. These surveys were made upon vacant public land. The two surveys for each certificate were placed in a file with the appropriate certificate as belonging to it, the certificates first having been withdrawn from the field notes first returned. The surveys were examined and found correct, and were mapped upon the maps of the land office.
9. The said surveys made by Corwin were returned to and filed in the land office with the full understanding and consent of the Commissioner of the Land Office, given upon written ap[258]*258plication of defendant. The surveys were called "corrected” surveys, but the nature of them, as being upon different land from the first surveys, was known and approved.
10. From 1873 the defendant paid taxes upon the said certificates as located lands, and has paid up to this date upon the land in controversy.
11. At the time of issuance of the certificates under which the plaintiffs claim, the surveys made by Corwin were mapped as located lands on the maps of the land office. Such was the condition of the maps at the adoption of the Constitution of 1876, and of the Revised Statutes, September 1, 1879, and at the subsequent dates of the issuance of the certificates and location of them, under which plaintiff claims.
13.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Atlantic Refining Company v. Noel
443 S.W.2d 35 (Texas Supreme Court, 1969)
Rudder v. Ponder
293 S.W.2d 736 (Texas Supreme Court, 1956)
Kirby Lumber Co. v. Adams
62 S.W.2d 366 (Court of Appeals of Texas, 1932)
Stark v. Chaison
50 S.W.2d 776 (Texas Commission of Appeals, 1932)
Blaffer v. State
31 S.W.2d 172 (Court of Appeals of Texas, 1930)
Chaison v. Stark
29 S.W.2d 500 (Court of Appeals of Texas, 1930)
State v. Bradford
25 S.W.2d 706 (Court of Appeals of Texas, 1930)
Schnackenberg v. State
229 S.W. 934 (Court of Appeals of Texas, 1921)
Main v. Cartwright
200 S.W. 847 (Court of Appeals of Texas, 1918)
Baugh v. McLain
173 S.W. 922 (Court of Appeals of Texas, 1915)
Sullivan v. State
164 S.W. 1120 (Court of Appeals of Texas, 1914)
Fielder v. Houston Oil Co. of Texas
165 S.W. 48 (Court of Appeals of Texas, 1914)
McCullough v. Randall
158 S.W. 219 (Court of Appeals of Texas, 1913)
Thompson Bros. Lumber Co. v. Toler
151 S.W. 1111 (Court of Appeals of Texas, 1912)
State v. Louisville & Nashville Railroad
96 N.E. 340 (Indiana Supreme Court, 1911)
Pate v. McLain
136 S.W. 538 (Court of Appeals of Texas, 1911)
Harvell v. . Lumber Co.
70 S.E. 389 (Supreme Court of North Carolina, 1911)
Harvell v. Weldon Lumber Co.
154 N.C. 254 (Supreme Court of North Carolina, 1911)
Murphy v. Luttrell
120 S.W. 905 (Court of Appeals of Texas, 1909)
Hulett v. Ras Platt
109 S.W. 207 (Court of Appeals of Texas, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
7 S.W. 729, 70 Tex. 252, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adams-v-houston-texas-central-railway-co-tex-1888.