Adam v. Board of Commissioners

117 N.E. 876, 66 Ind. App. 48, 1917 Ind. App. LEXIS 185
CourtIndiana Court of Appeals
DecidedDecember 4, 1917
DocketNo. 9,323
StatusPublished
Cited by3 cases

This text of 117 N.E. 876 (Adam v. Board of Commissioners) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Adam v. Board of Commissioners, 117 N.E. 876, 66 Ind. App. 48, 1917 Ind. App. LEXIS 185 (Ind. Ct. App. 1917).

Opinion

Batmau, J. —

Appellant brought two actions against appellee on a written contract for tbe construction of [50]*50bridges in Boone county, Indiana, one being No. 4,648,> and the other No. 4,735. ' Both actions were based on the same contract, but sought to recover the balance alleged to be due for the construction of two separate bridges thereunder. By agreement of the parties these two actions were,consolidated and tried together in the court below. The complaint in cause No. 4,648 is in a single paragraph, and, briefly stated, alleges the execution of the contract in suit, and the completion of bridge No. 166 thereunder, for which he was to be paid the sum of $422; that prior to the making of such contract, a copy of which was filed with the complaint and made a part thereof, the county council of said county had appropriated the necessary funds with which to pay for said bridge, and that appellee had duly advertised the letting of such contract, and had taken all the necessary steps preceding the letting thereof; that appellant had filed his claim for said contract price and appellee had allowed thereon the sum of $397, and denied that it was liable to appellant for the remaining $25 thereof. To this complaint appellee filed a single paragraph of answer in which it admitted the execution of the contract in suit, and that it agreed to pay appellant $422 for the construction of bridge No. 166 thereunder; that appellant filed his claim for $422 for the construction of such bridge, and that appellee allowed thereon the sum of $397 and rejected the remaining $25 thereof. Such answer then alleges in substance that the auditor of said county drew his warrant, payable to appellant for said sum so allowed on said claim; that appellant accepted said warrant and received thereon the sum of $397, which he retains, and that said action was brought to recover $25 of said claim that was disallowed by appellee. To this [51]*51answer appellant filed a reply in two paragraphs, the first of which was a general denial, and the second alleges in substance the filing of said claim for $422, the allowance of $397 thereon, the rejection of the remaining $25 thereof by appellee, and the bringing of this action for said sum so rejected; that said sum of $397 had been received by appellant, but that the same had not been agreed upon as the sum which he would accept in full settlement of such claim; that the allowance of such sum was not the result of any settlement or compromise; that he did not receive the same in full settlement of his said claim, as appellee well knew, but accepted the same as part payment only; that said bridge No. 166 for which said claim was filed had been fully completed in all things in accordance with the plans and specifications therefor, and to the acceptance of the engineer in charge; that no claim was ever made by appellee to the contrary, but that it arbitrarily deducted from his said claim the said sum of $25 without right. To this affirmative paragraph of reply appellee filed its demurrer for want of facts, on the ground that it showed that appellant had waived its right to litigate the demand set out in the complaint by accepting the amount allowed on his claim by appellee. The court sustained this demurrer, to which ruling appellant excepted.

The complaint in cause No. 4,735 is in two paragraphs. The first paragraph contains substantially the same allegations as the complaint in cause No. 4,648, except that it seeks to recover a balance of $300 due for the construction of bridge No. 167, for which it is alleged appellant was to receive $623. The second paragraph differs from the first, in that it alleges that appellant filed his claim for a part of the con[52]*52tract price for such.' bridge, to wit, $323; that said sum was allowed and paid by appellee; that after the completion of said bridge No. 167 plaintiff filed his claim for the balance of said contract price, to wit, $300; that appellee allowed thereon the sum of $275, and refused to allow the balance thereof; that appellant refused to accept said amount so allowed, and never received any part thereof; and that said sum of $300 is now due and owing appellant.

Appellee answered said complaint by alleging in substance that appellant filed his claim for $623 on account of the construction of bridge No. 167; that appellee allowed thereon the sum of $323 and rejected the remainder thereof; that appellant accepted said sum so allowed, and that this action was brought to recover the remaining $300 for the construction of said bridge No. 167.

To this answer appellant filed a reply, the nature of which is not disclosed by the record. Trial by the court, finding for appellee, and judgment against appellant for costs. Appellant filed his motion for a new trial, which was overruled.

The errors assigned and relied on for reversal are that the court erred in sustaining appellee’s demurrer to the second paragraph of reply in cause No. 4,648, and in overruling appellant’s motion for a new trial. The first assigned error cannot be sustained, as the facts alleged in said paragraph of reply are clearly not sufficient to avoid the answer to which it is addressed. Such answer is drawn on the theory of a waiver by appellant of his right to maintain an action for the portion of his claim disallowed, by the acceptance of the portion allowed. The facts set up in such paragraph of reply would not avoid the effect [53]*53of such acceptance, and hence the conrt did not err in its ruling on such demurrer.

1. 2. Appellant assigned the following reasons for a new trial: (1) The decision of the court is contrary to law; (2) the decision of the court is not sustained by sufficient evidence; (3) the decision is contrary to the evidence. The last reason assigned fails to present any question to this court for its determination. Bass v. Citizens Trust Co. (1903), 32 Ind. App. 583, 70 N. E. 400. In considering the questions properly raised by the motion for a new trial, we must direct our attention to the evidence, but in doing so this court will not weigh the same for the purpose'.of determining where the preponderance lies. . If proper evidence was heard by the trial court upon which to base its decision, this court will not review it. Beavers v. Bess (1914), 58 Ind. App. 287, 108 N. E. 266; Vandalia R. Co. v. House (1914), 59 Ind. App. 10, 108 N. E. 872; Nicholson v. Smith (1915), 60 Ind. App. 385, 110 N. E. 1007; Dorrell v. Herr (1915), 184 Ind. 445, 111 N. E. 614.

3. [55]*554. 3. [53]*53We shall first consider the evidence with reference to that portion of appellant’s claim for the construction of bridge No. 166, which appellee refused to allow, being the $25 for which cause No. 4,648 was begun. There is no dispute in the evidence relating to the execution of the contract, the construction of the bridge, the acceptance of the same, the filing of a claim for the full contract price of $422, the allowance of $397 thereon, the disallowance of the remaining $25 thereof, and the acceptance by appellant of the amount so allowed. The sole question is as to the legal effect of such acceptance under the attending circumstances. It is, now firmly settled [54]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fowler v. Farm Bureau Mutual Insurance
137 Ind. App. 375 (Indiana Court of Appeals, 1965)
Fowler v. FARM BUREAU MUT. INS. CO. OF IND.
209 N.E.2d 262 (Indiana Court of Appeals, 1965)
Parrish v. Board of Commissioners
154 N.E. 879 (Indiana Court of Appeals, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
117 N.E. 876, 66 Ind. App. 48, 1917 Ind. App. LEXIS 185, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adam-v-board-of-commissioners-indctapp-1917.