Parrish v. Board of Commissioners

154 N.E. 879, 89 Ind. App. 277, 1927 Ind. App. LEXIS 290
CourtIndiana Court of Appeals
DecidedJanuary 23, 1927
DocketNo. 12,512.
StatusPublished

This text of 154 N.E. 879 (Parrish v. Board of Commissioners) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parrish v. Board of Commissioners, 154 N.E. 879, 89 Ind. App. 277, 1927 Ind. App. LEXIS 290 (Ind. Ct. App. 1927).

Opinion

McMahan, C. J.

The questions involved in this appeal relate to the right of a person who has filed a claim against a county to maintain an action against the county for that part of his claim which was disallowed, after having accepted the amount which the commissioners had allowed. , Demurrers were sustained to the second paragraph of appellant’s complaint and to the second and third paragraphs of his reply, and judgment was rendered for appellee on the pleadings.

*278 The first paragraph of complaint alleges, in substance, that James A. Parrish and the board of commissioners of Shelby county entered into a contract by which Parrish agreed to build a certain bridge according to plans and specifications for the sum of $1,700, plus $12 per cubic yard for all extra concrete used in the footings and piers; that thereafter, the commissioners determined that one of the abutments should be reconstructed by placing concrete around and beneath the base thereof, and directed the contractor so to do; that in accordance therewith the contractor completed the bridge and, in so doing, used 147 extra cubic yards of concrete around and beneath such abutment; that the contractor thereafter filed his claim for the extra concrete work in the sum of $1,617, which claim was disallowed and rejected by the board of commissioners, notwithstanding there was sufficient money in the hands of the treasurer of the county to pay said claim, and which had been appropriated therefor. After such disallowance, said contractor, for a consideration, assigned his said claim to appellant.

The second paragraph of complaint to which the demurrer was sustained was for work and labor done and material furnished at the special instance and request of appellee in the erection of the abutment mentioned in the first paragraph of complaint.

Appellee filed answer in three paragraphs, the first and second being in denial and payment. Both of these answers .'were later withdrawn. The third paragraph of answer admits the execution of the contract, set out in the complaint, and alleges that in November, 1913, the contractor, James A. Parrish, filed his claim with the auditor for the sum of $2,701, that being the amount claimed by him as the balance due from the county on account of the contract for the construction of the bridge; that the commissioners later allowed $1,084 of the amount claimed, and disallowed $1,617 of said claim; *279 that a warrant on the treasurer in the sum of $1,084 was delivered to said contractor; that no appeal was taken from the action of the board in disallowing said sum of $1,617, but that the contractor accepted said warrant for $1,084, and cashed the same, and thereafter assigned disallowed portion to appellant. Appellant replied in three paragraphs; the first, a general denial, was later withdrawn. The second paragraph alleges that the claim filed by the contractor with the board of commissioners for $2,701 consisted of three separate and distinct items, as follows: First, to balance due contractor, on account of substructure of bridge, $700; second, for extra material re-inforcing footing on each abutment, thirty-two cubic yards concrete, $384; third, 147 cubic yards concrete, $1,617; that the commissioners allowed the first and second items and disallowed the third. It admits the contractor accepted and cashed the warrant for $1,084, but alleges there was no dispute or disagreement between the parties as to the first and second items which it is alleged were “liquidated items . of indebtedness” based on and regulated by the contract; that no part of said $1,084 was allowed as a consideration for the disallowance of the $1,617; that the only dispute between the contractor and the commissioners was with reference to the item for $1,617; that the said three items constituted three separate and distinct claims. The third paragraph of reply is the same as the second, except it is there alleged that the board of commissioners did not contemplate or intend that the acceptance, by appellant’s assignor, James A. Parrish, of the two items allowed should estop or prevent him from controverting with the board his right to collect the $1,617, and that said James A. Parrish did not contemplate or know that the acceptance of the warrant for $1,084 would raise any question as to his right to recover the part disallowed *280 and that he was not advised by attorneys as to the effect of such acceptance.

Appellant contends that when a claimant files two liquidated claims against a county on one sheet of paper and as one claim, and the board considers each claim separately and allows in whole a, part of one claim and disallows in whole the other, such action of the board as to each claim is wholly independent, and that the acceptance of the amount of the claim allowed does not prevent the claimant from prosecuting an action against the county for the amount of the claim disallowed, and does not amount to an accord and satisfaction, and that parol testimony may be heard to determine whether a payment and allowance by the board of commissioners was an accord and satisfaction.

No claim shall be allowed by the board of commissioners unless such claim, duly itemized and verified, shall have been filed in the auditor’s office. §5964 Burns 1926, §6008 Burns 1914. The commissioners shall examine into the merits of all claims so presented, and may, in their discretion, allow any claim, in whole or in part, as they may find it to be just and owing. §5965 Burns 1926, §6005 Burns 1914. If a claim be disallowed in whole or in part, the claimant may appeal, or, at his option, bring an action against the county. §5975 Burns 1926, §6019 Burns 1914.

In Western Construction Co. v. Board, etc. (1912), 178 Ind. 684, 98 N. E. 347, the appellant filed a claim against the county. The claim was made up of four items, aggregating $8,788.58. The sum of $7,000 was allowed on the claim and paid. At a subsequent term of the board, the unpaid portion of the claim was rejected and suit commenced to recover the part rejected. The court on page 688, after calling attention to the statute which prohibits a party procuring a judgment from appealing after receiving any money paid or collected there *281 on (§695 Burns 1926), said: “And if it be shown, on appeal to this court, that appellant has accepted any benefit based on the theory of the legality of the judgment appealed from, the appeal will be dismissed,” and continuing, on page 689, said: “An allowance or dis-allowance of a claim, by a board of commissioners, is not a judgment within the ordinary meaning of that word. In such case, the board acts in an administrative capacity, as a board of audit. ... In many respects, however, the action of the board is as binding on the claimant as is a judgment, and unless resort is had to one of the two statutory remedies above mentioned, the action of the board is conclusive against the claimant.”

In Adams v. Board, etc. (1917), 66 Ind. App. 48, 117 N. E.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Etzold v. Board of Commissioners
146 N.E. 842 (Indiana Court of Appeals, 1924)
Western Construction Co. v. Board of Commissioners
98 N.E. 347 (Indiana Supreme Court, 1912)
Adam v. Board of Commissioners
117 N.E. 876 (Indiana Court of Appeals, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
154 N.E. 879, 89 Ind. App. 277, 1927 Ind. App. LEXIS 290, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parrish-v-board-of-commissioners-indctapp-1927.