Acme Cycle Co. v. Clarke

61 N.E. 561, 157 Ind. 271, 1901 Ind. LEXIS 157
CourtIndiana Supreme Court
DecidedOctober 11, 1901
DocketNo. 19,073
StatusPublished
Cited by15 cases

This text of 61 N.E. 561 (Acme Cycle Co. v. Clarke) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Acme Cycle Co. v. Clarke, 61 N.E. 561, 157 Ind. 271, 1901 Ind. LEXIS 157 (Ind. 1901).

Opinion

Dowling, J.

The appellees sued the appellant upon an account for goods sold and delivered. The answer was a general denial, and a plea of payment. The appellant, also filed seven paragraphs by way of counterclaim for damages in the sum of $15,000. A demurrer 'to the fourth paragraph of the counterclaim was sustained, and on motion of the appellees the fifth paragraph of the counterclaim was stricken out. A reply in denial of the second paragraph of the answer and answers in denial of the remaining paragraphs. of the counterclaim were filed by the appellees. The cause was tried by a jury, and a verdict in favor of the appellees was returned.

The errors assigned and discussed by counsel are the rulings of the court, upon the demurrer to the fourth paragraph of the counterclaim, upon the motion to. strike out the fifth paragraph of counterclaim, and upon the motion for a new trial.

The fourth paragraph of the counterclaim stated in substance that the appellees sold and agreed to deliver to the appellant, on or before September 20, 1895, one complete hub plant, consisting of one Bardons & Oliver hub machine, and one number four machine fitted up for the second oper[273]*273ation, both to be complete, with tools; and two number four Bardons & Oliver screw machines, complete, with number two spindle friction gears, etc., for all of which the appellant agreed to pay the appellees $1,650; that said ma“ chinery was not delivered until January 20, 1896; that at the time said contract was made it was well known to all persons that the demand for bicycles was so great that it could not be supplied during the years 1895 and 1896; that while there was at that time in the market an unlimited supply of all the parts of a bicycle except the hubs, no hubs could be purchased, and that all persons well knew this condition would last during the years 1895 and 1896; that the appellant, when said negotiations were pending and said contract was made, was prepared to manufacture five front' hubs and five rear hubs per day; that with a machine which would make 125 front hubs, or 75 rear hubs per day, it would manufacture at least 500 more bicycles per month than it was then doing, that the net profit on each bicycle was $5, and that these facts were contemplated by the parties at the time the contract was made. That, in consequence of the failure of the appellees to deliver said hub plant for four months after September 20, 1895, appellant failed to make 2,000 bicycles, which it would have made if it had been furnished with said hub plant, and that during said period appellant received, and was unable to fill 2,019 orders for bicycles; that appellant’s profits on said orders would have been $5 per wheel on 1,157 wheels, and $6 per wheel on 862 wheels, and that appellant was thereby damaged in the sum of $10,957.

. The sole ground of the appellant’s claim for damages is the alleged loss of contingent anticipated profits. The basis upon which they were estimated was the general demand for bicycles, the scarcity of hubs for these machines, and its belief that with a machine which would manufacture 125 front hubs or 75 rear hubs in a day, it would be able to man[274]*274ufaeture at least 500 more bicycles each month than it was then doing, and that its net profit on each bicycle would be $5. It is stated in the complaint that these facts were known to, and were contemplated by, the parties at the time the contract was made.

Before passing to the consideration of the rule of damages to be applied in this case, it is to be observed that the complaint is silent in respect to certain facts of much importance even in the view of the law taken by appellant’s counsel. We find nothing in the paragraph to indicate that at the time the hub machines were to be delivered the appellant was prepared to manufacture more than five bicycles in a day, or, say, 125 in a month. This seems to have been the limit of its capacity when the contract was made. It was then using machines which could turn out only five front hubs, and five rear hubs in one day. It is not stated that the appellant was manufacturing, or was prepared to manufacture, more bicycles than it had the capacity to make hubs for. If it did SO', it must have purchased all of its hubs in excess of those manufactured by its own plant. But, if it had a plant of sufficient capacity to manufacture more than five bicycles in a day, that fact is nowhere stated. It cannot be supposed that a small establishment, capable of turning out only five bicycles in a day, or 125 in a month, could suddenly expand, without considerable additions to its buildings, power, and other machinery, to a capacity of twenty-five bicycles in one day, or 625 in one month. If the appellant had so extensive a plant, or if in anticipation of the great increase in its business it enlarged its works after ordering the hub machines from the appellees, the complaint ‘ should have said so. As nothing of this kind is claimed, we must assume that the appellant made no change in its plant before the hub machines were delivered, and that, in fact, it waited to see what the new machines would do, and whether the demand for bicycles would justify it in enlarging its works. If this was the plan of the appellant, and if the [275]*275erection, purchase, or leasing of additional buildings in which to carry on its business, and the purchase, construction and adjustment of a vast quantity of new machinery required for the manufacture of 500 additional bicycles per month was postponed by the appellant until actual delivery of the hub machines by the appellees in January, 1896, it follows that the appellant was not prepared to use the new machines, and that if they had been delivered on or before September 20, 1895, considerable time must have elapsed before the appellant could have been prepared to increase its output from 125 bicycles per month to 625 per month. The hub of a bicycle is an important part of the mechanism, but there are many other parts, and, unless, in addition to machines for making the hubs, the appellant was prepared to manufacture all the other parts of a bicycle, it could not be said that its losses of profits on sales resulted from the failure of the appellees to deliver the hub machines. If the appellant did not intend to manufacture the other parts of the bicycles, but expected to purchase all of them, excepting the hubs, then it seems that it should have been stated with some particularity when and from what sources the appellant expected to procure such other parts and whether it had made any engagements for such supplies. If no such contracts were made hy the appellant, how could it be said with any degree of certainty that the appellant could at any time go into the market, and buy all the parts of a bicycle excepting the hubs at such prices as would enable it to make a sure and reliable profit of $5 on each bicycle ? The case as made by the fourth paragraph of the counterclaim stands thus: The appellant says that on July 20,1895, it had the capacity to manufacture five bicycles, a day, and no more. If it had a machine for making hubs alone, which would turn out seventy-five rear hubs or 125 front hubs per day, it could then manufacture and sell twenty complete bicycles per day at a profit of $5 on each bicycle. Do the facts stated authorize any such conclusion ?

[276]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Indiana & Michigan Electric Co. v. Terre Haute Industries, Inc.
507 N.E.2d 588 (Indiana Court of Appeals, 1987)
Piersol v. Hays, Exr.
47 N.E.2d 844 (Indiana Court of Appeals, 1943)
Weismann Motor Sales, Inc. v. Allen
19 N.E.2d 505 (Indiana Court of Appeals, 1939)
J. P. Smith Shoe Co. v. Curme-Feltman Shoe Co.
118 N.E. 360 (Indiana Court of Appeals, 1918)
Barkley v. Barkley
106 N.E. 609 (Indiana Supreme Court, 1914)
Illinois Surety Co. v. Frankfort Heating Co.
97 N.E. 158 (Indiana Supreme Court, 1912)
W. J. Holliday & Co. v. Highland Iron & Steel Co.
87 N.E. 249 (Indiana Court of Appeals, 1909)
Hart v. Scott
81 N.E. 481 (Indiana Supreme Court, 1907)
Leffler v. Witten
18 Ohio C.C. Dec. 533 (Wood Circuit Court, 1906)
Kagy v. Western Union Telegraph Co.
76 N.E. 792 (Indiana Court of Appeals, 1906)
Connersville Wagon Co. v. McFarlan Carriage Co.
76 N.E. 294 (Indiana Supreme Court, 1905)
Elrod v. Purlee
73 N.E. 589 (Indiana Supreme Court, 1905)
American Tin-Plate Co. v. Williams
65 N.E. 304 (Indiana Court of Appeals, 1902)
Standish v. Bridgewater
65 N.E. 189 (Indiana Supreme Court, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
61 N.E. 561, 157 Ind. 271, 1901 Ind. LEXIS 157, Counsel Stack Legal Research, https://law.counselstack.com/opinion/acme-cycle-co-v-clarke-ind-1901.