Abraham v. T. Henry Construction, Inc.

217 P.3d 212, 230 Or. App. 564, 2009 Ore. App. LEXIS 1271
CourtCourt of Appeals of Oregon
DecidedSeptember 2, 2009
DocketCV06060031; A136228
StatusPublished
Cited by20 cases

This text of 217 P.3d 212 (Abraham v. T. Henry Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Abraham v. T. Henry Construction, Inc., 217 P.3d 212, 230 Or. App. 564, 2009 Ore. App. LEXIS 1271 (Or. Ct. App. 2009).

Opinion

*567 SCHUMAN, J.

Plaintiffs own a house that was built for them by several contractors and subcontractors, including defendants. 1 After the house was finished, plaintiffs discovered damage to the property allegedly caused by water leakage. Sometime after that discovery, but more than eight years after the construction was substantially complete, plaintiffs brought this action against defendants, alleging breach of contract and negligence due to construction defects. Defendants moved for summary judgment on both claims, arguing that the contract claims were filed after the six-year statute of limitations had run and that the negligence claims were barred because one party to a contract cannot bring a tort action against the other party unless that action arises from the breach of some standard of care that is independent of the terms of the contract. The court granted defendants’ motions. We hold that the contract claims were barred by the statute of limitations, but that the tort claims survive summary judgment because they are based on the alleged violation of a regulatory standard that is independent of the contract. We therefore affirm in part and reverse in part.

First, we agree with the trial court that plaintiffs’ contract claims are barred by the six-year statute of limitations set forth in ORS 12.080(1). Plaintiffs argue that a 10-year statute of limitations applies to construction defect claims under ORS 12.135 and that, even if the applicable period is six years, that limitations period did not begin until plaintiffs discovered or should have discovered the water leakage. After briefing in this case was complete, we rejected indistinguishable arguments in Waxman v. Waxman & Associates, Inc., 224 Or App 499, 504-12, 198 P3d 445 (2008). For the reasons stated in that case, we agree with the trial court that the applicable statute of limitations for plaintiffs’ contract claims is six years from the date of breach and that no discovery rule applies. Because plaintiffs did not *568 bring this action within that time, we reject plaintiffs’ first assignment of error without further discussion.

We turn to plaintiffs’ assignment of error regarding their negligence claims. We begin with an overview of the legal principles that apply to the viability of tort claims by one party to a contract against the other party. Obligations specified in the terms of a contract are “ ‘based on the manifested intention of the parties to a bargaining transaction,’ ” while obligations in tort, or “duties,” are “ ‘imposed by law— apart from and independent of promises made and therefore apart from the manifested intention of the parties — to avoid injury to others.’ ” Conway v. Pacific University, 324 Or 231, 237, 924 P2d 818 (1996) (quoting W. Page Keeton, Prosser and Keeton on the Law of Torts, § 92, 655, 656 (5th ed 1984)) (emphasis in Conway). In other words, a contract details the specific obligations that each party agrees to undertake with respect to the other and, if one party fails to meet an obligation, that breach results in contract liability. Conway, 324 Or at 237; Georgetown Realty v. The Home Ins. Co., 313 Or 97, 106, 831 P2d 7 (1992). “That is so whether the breach of contract was negligent, intentional, or otherwise.” Georgetown Realty, 313 Or at 106.

For the injured party to have a tort claim, however, that party must allege the breach of a standard of care that is independent of the contract and without reference to its specific terms. 2 As the court explained in a frequently cited passage from Georgetown Realty, 313 Or at 106:

“When the relationship involved is between contracting parties, and the gravamen of the complaint is that one party caused damage to the other by negligently performing its obligations under the contract, then, and even though the relationship between the parties arises out of the contract, the injured party may bring a claim for negligence if the other party is subject to a standard of care independent of the terms of the contract. If the plaintiffs *569 claim is based solely on a breach of a provision in the contract, which itself spells out the party’s obligation, then the remedy normally will be only in contract, with contract measures of damages and contract statutes of limitation.”

In most cases, the “independent standard of care” derives from a “special relationship” between the contracting parties. We have also held, however, that a standard of care expressed in a statute is considered to be independent of the terms of the contract. Butterfield v. State of Oregon, 163 Or App 227, 235, 987 P2d 569 (1999), rev den, 330 Or 252 (2000) (action based on violation of Fair Labor Standards Act sounds in tort); see also Griffin v. Tri-Met, 318 Or 500, 507, 870 P2d 808 (1994) (ORS 659.425(1), prohibiting employment discrimination based on disability, imposes “legal duty that is imposed by law, other than a duty arising from contract or quasi-contract” (internal quotation marks omitted)).

Initially, plaintiffs argue that these precepts do not apply in construction defect cases, our opinion in Jones v. Emerald Pacific Homes, Inc., 188 Or App 471, 71 P3d 574, rev den, 336 Or 125 (2003) to the contrary notwithstanding. They point to Newman v. Tualatin Development Co. Inc., 287 Or 47, 597 P2d 800 (1979). In Newman, one group of plaintiffs (the “privity plaintiffs”) had purchased homes directly from the defendant (builder); the other group (the “nonprivity plaintiffs”) was composed of subsequent, downstream purchasers. Both groups brought an action against the defendant, alleging breach of warranty and negligent construction. Id. at 49. The trial court certified the proceeding as a class action. The defendant took an interlocutory appeal, arguing that the action was not appropriate for class certification because, among other reasons, the privity plaintiffs’ chances of success were minimal. Id. at 50-51. Despite the existence of a contract between the privity plaintiffs and the defendant, the trial court affirmed the certification, concluding that, “from the evidence considered and the state of the law, plaintiffs’ chances of prevailing do not appear so minimal that they should be precluded from proceeding as a class action.” Id. at 51. From that statement, plaintiffs here infer that the court approved a negligence claim based on faulty construction *570 despite the existence of a contract and the absence of a non-contractual standard of care. Nothing in the Newman

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moody v. Oregon Community Credit Union
Oregon Supreme Court, 2023
Lunceford v. Carson
D. Oregon, 2023
Moody v. Oregon Community Credit Union
505 P.3d 1047 (Court of Appeals of Oregon, 2022)
Hammel v. McCulloch
441 P.3d 617 (Court of Appeals of Oregon, 2019)
Sonia Braun-Salinas v. American Family Ins. Group
665 F. App'x 576 (Ninth Circuit, 2016)
Deberry v. Summers
296 P.3d 610 (Court of Appeals of Oregon, 2013)
Abraham v. T. Henry Construction, Inc.
249 P.3d 534 (Oregon Supreme Court, 2011)
Paul v. Providence Health System-Oregon
240 P.3d 1110 (Court of Appeals of Oregon, 2010)
Buoy v. SOO HEE KIM
221 P.3d 771 (Court of Appeals of Oregon, 2009)
Mead v. Legacy Health System
220 P.3d 118 (Court of Appeals of Oregon, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
217 P.3d 212, 230 Or. App. 564, 2009 Ore. App. LEXIS 1271, Counsel Stack Legal Research, https://law.counselstack.com/opinion/abraham-v-t-henry-construction-inc-orctapp-2009.