Waxman v. Waxman & Associates, Inc.

198 P.3d 445, 224 Or. App. 499, 2008 Ore. App. LEXIS 1798
CourtCourt of Appeals of Oregon
DecidedDecember 24, 2008
Docket050910112, A132602
StatusPublished
Cited by23 cases

This text of 198 P.3d 445 (Waxman v. Waxman & Associates, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Waxman v. Waxman & Associates, Inc., 198 P.3d 445, 224 Or. App. 499, 2008 Ore. App. LEXIS 1798 (Or. Ct. App. 2008).

Opinion

*501 HASELTON, P. J.

Plaintiffs, who are owners of one of four connected row houses, appeal, challenging the dismissal, on summary judgment, of their tort and contract claims against defendant, the builder/developer, to recover their share of costs associated with the repair of certain construction defects in the common elements of the building. Plaintiffs contend, principally, that the trial court erred (1) in concluding that the “economic loss” doctrine bars plaintiffs’ negligence claims, (2) in concluding that plaintiffs’ contract claims are barred by the six-year statute of limitations set forth in ORS 12.080(1), and (3) in failing to give preclusive effect in this case to an earlier arbitration award in favor of the owner of another of the row houses. As explained below, we conclude that the trial court erred in determining that the economic loss doctrine bars plaintiffs’ negligence claims. However, we also conclude that the court correctly held that plaintiffs’ contract claims are barred by the statute of limitations and that the arbitration award cannot be given preclusive effect. Consequently, we affirm the dismissal of the contract claims, reverse the dismissal of the tort claims, and remand for further proceedings.

The material facts are not in dispute. In the mid-1990s, defendant developed and built four row houses. 1 After completing construction, defendant sold the row houses to Jean Slyman, Sharolyn Shearer, Julie Bussing, and Ruth and Douglas Menely (referred to collectively as the original purchasers). The Menelys sold their row house to plaintiffs in 2001.

There were significant construction defects in the common elements of the row houses, necessitating extensive repairs. The row houses are subject to covenants, conditions, and restrictions, which give each row house owner a 25 percent ownership interest in and responsibility for the common elements. As a result, the four property owners at the time of the repairs, Slyman, Shearer, Bussing, and plaintiffs, were each responsible for 25 percent of the repair bill.

*502 The purchase agreements between defendant and the original purchasers required that unresolved claims be submitted to arbitration. In October 2004, the row house owners filed an arbitration claim against defendant, seeking damages associated with the construction defects. Defendant filed an answer in the arbitration that, among other things, challenged plaintiffs’ eligibility to participate in the arbitration, contending that there was no arbitration agreement between plaintiffs and defendant. After initiation of the arbitration proceeding, the Menelys and plaintiffs executed an agreement captioned “Addendum to Real Estate Sales Agreement” (the assignment) in which the Menelys purported to assign to plaintiffs all claims and causes of action arising from the construction of the row houses.

While the arbitration proceeding was underway, defendant filed suit in circuit court against some of the subcontractors that participated in the building of the row houses. In the context of that action, defendant (as a plaintiff there) sought a declaration that plaintiffs could not participate in the arbitration with the other row house owners because plaintiffs had not been parties to the original purchase agreement, which included the arbitration clause. The circuit court in that action ultimately held that plaintiffs were not eligible to participate in the arbitration. Thereafter, defendant settled with Shearer and Slyman, but Bussing proceeded to arbitration on her claims. In October 2005, following a full evidentiary hearing, the arbitration panel awarded Bussing a money judgment, costs, and attorney fees.

Meanwhile, in September 2005, plaintiffs filed a complaint against defendant in circuit court to recover their portion of the repair costs, asserting claims for negligence and breach of contract. The parties filed cross-motions for summary judgment. Defendant argued that it was entitled to summary judgment on plaintiffs’ negligence claims because, among other things, those claims were barred by the economic loss doctrine. With regard to plaintiffs’ contract claims, defendant argued that it had no contractual duty to plaintiffs, because the assignment from the Menelys was ineffective. Defendant also argued that, even if the assignment was *503 effective, the applicable statute of limitations barred plaintiffs’ contract claims. Plaintiffs, while disputing those arguments, further maintained that they were entitled to partial summary judgment because defendant was “precluded from re-litigating its legal responsibility for the damages” by virtue of the arbitration award.

The trial court granted defendant’s motion for summary judgment and denied plaintiffs’ cross-motion for partial summary judgment. The court concluded that plaintiffs’ negligence claims were barred by the economic loss doctrine and that their contract claims were barred by the statute of limitations. In denying plaintiffs’ cross-motion for partial summary judgment, the trial court refused to give preclusive effect to the arbitration award, stating that it could not determine on what basis — contract or tort — the panel had awarded Bussing damages.

We review a grant of summary judgment “to determine whether any genuine issue of material fact exists and whether defendant is entitled to judgment as a matter of law Herman v. Valley Ins. Co., 145 Or App 124, 127-28, 928 P2d 985 (1996), rev den, 325 Or 438 (1997). Because the material facts are undisputed, this appeal presents only legal issues, which we review for errors of law. Bunnell v. Dalton Construction, Inc., 210 Or App 138, 142, 149 P3d 1240 (2006), rev den, 344 Or 558 (2008).

For the reasons that follow, we reverse the allowance of summary judgment in part and affirm in part. We also affirm the trial court’s denial of plaintiffs’ cross-motion for partial summary judgment. In particular, we conclude that the trial court erred in determining that the economic loss doctrine bars plaintiffs’ negligence claims. However, the court correctly concluded that plaintiffs’ contract claims are barred by the statute of limitations and that the arbitration award cannot be given preclusive effect vis-a-vis plaintiffs’ tort claims, which are the only viable claims remaining.

We turn to the trial court’s application of the economic loss doctrine to plaintiffs’ tort claims. That doctrine provides that, in the absence of a special relationship, a party that has suffered purely economic loss may not bring a negligence action against the party that caused such loss. See, *504 e.g., Onita Pacific Corp. v. Trustees of Bronson, 315 Or 149, 159, 843 P2d 890 (1992). After the trial court’s decision in this case, the Supreme Court issued its decision in Harris v. Suniga, 344 Or 301, 180 P3d 12 (2008). In Harris,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lynn v. Ellis
347 Or. App. 532 (Court of Appeals of Oregon, 2026)
Hathaway v. B & J Property Investments, Inc.
531 P.3d 152 (Court of Appeals of Oregon, 2023)
Romero v. Amburn
523 P.3d 1135 (Court of Appeals of Oregon, 2022)
Ditech Holding Corporation
S.D. New York, 2021
MAT, Inc. v. American Tower Asset Sub, LLC
493 P.3d 14 (Court of Appeals of Oregon, 2021)
MORGAN v. STATE FARM MUTUAL AUTOMOBILE INSUR. CO.
2021 OK 27 (Supreme Court of Oklahoma, 2021)
Communication Management Services, LLC v. Qwest Corp.
67 F. Supp. 3d 1159 (D. Oregon, 2014)
Bates v. Bankers Life & Casualty Co.
993 F. Supp. 2d 1318 (D. Oregon, 2014)
Whalen v. American Medical Response Northwest, Inc.
300 P.3d 247 (Court of Appeals of Oregon, 2013)
Doughton v. Morrow
298 P.3d 578 (Court of Appeals of Oregon, 2013)
Frakes v. Nay
295 P.3d 94 (Court of Appeals of Oregon, 2012)
Rice v. Rabb
284 P.3d 1178 (Court of Appeals of Oregon, 2012)
Doe v. Medford School District 549C
221 P.3d 787 (Court of Appeals of Oregon, 2009)
Abraham v. T. Henry Construction, Inc.
217 P.3d 212 (Court of Appeals of Oregon, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
198 P.3d 445, 224 Or. App. 499, 2008 Ore. App. LEXIS 1798, Counsel Stack Legal Research, https://law.counselstack.com/opinion/waxman-v-waxman-associates-inc-orctapp-2008.