A & a Mason, LLC v. Montagno Construction, Inc.

889 A.2d 278, 49 Conn. Supp. 405, 2005 Conn. Super. LEXIS 1236
CourtConnecticut Superior Court
DecidedMay 10, 2005
DocketFile CV-01-0809850S
StatusPublished
Cited by2 cases

This text of 889 A.2d 278 (A & a Mason, LLC v. Montagno Construction, Inc.) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A & a Mason, LLC v. Montagno Construction, Inc., 889 A.2d 278, 49 Conn. Supp. 405, 2005 Conn. Super. LEXIS 1236 (Colo. Ct. App. 2005).

Opinion

HON. ROBERT SATTER, JUDGE TRIAL REFEREE.

By reason of this court having reserved the issue of attorney’s fees in its opinion dated October 22, 2004, both parties now move for such fees. Montagno Construction, Inc, the named defendant, bases its claims on provisions of the contracts between the parties while the plaintiff, A & A Mason, LLC, bases its claim on General Statutes § 52-249, which authorizes counsel fees in actions for foreclosure of mechanic’s liens or on a surety bond given in substitution for a mechanic’s *406 lien. For the reasons stated subsequently, the court determines that neither party is entitled to counsel fees.

In the underlying action, the plaintiff, a subcontractor, sued the named defendant as contractor for the unpaid balances allegedly due the plaintiff on certain jobs in Rocky Hill and Bloomfield. Further, the plaintiff sought to foreclose the mechanic’s hens filed against the subject properties. The named defendant substituted a surety bond for the mechanic’s liens issued by the defendant United States Fidelity and Guaranty Company, and the plaintiff claimed against that bond. The named defendant interposed setoffs and counterclaims alleging that the plaintiff breached the underlying contracts.

The court heard extensive evidence on both the plaintiffs claim and the named defendant’s counterclaim. The court subsequently rendered a decision on August 2, 2004, and reconsidered on October 22, 2004. In its decision, the court found that the contract price on the Rocky Hill job, supplemented by a single change order, amounted to $36,200, against which the named defendant had paid certain sums. The parties concurred regarding certain back charges, leaving a balance due to the plaintiff of $9341. The court further found that the defendant had proved additional back charges of $4170.25, resulting in a net amount due the plaintiff of $5170.75.

With respect to the Bloomfield job, the court found that the contract price was $125,000. Against the contract price, the named defendant had paid the suppliers, incurred expenses to complete the contract and was entitled to back charges totaling $123,633.46. This leaves $1366.54 as the net amount due the plaintiff. Based on these findings, the court rendered judgment in favor of the plaintiff in the amount of $6547.29.

*407 I

THE NAMED DEFENDANT’S CLAIM FOR ATTORNEY’S FEES

The named defendant claims attorney’s fees in the amount of $80,478.95 on the basis of two provisions of the contracts between itself and the plaintiff.

Article IV of the contract pertaining to the Rocky Hill job provides that if the subcontractor (plaintiff) fails to perform or is in default under the agreement, the general contractor (named defendant) shall have the right to retain any payments then due or thereafter to become due to compensate it for the loss or damages, including legal fees, sustained by reason of the named defendant’s default.

Article XI of the contract pertaining to the Bloomfield job provides that in the case of termination of the employment of the plaintiff, the named defendant shall be entitled to damages resulting from the expenses incurred to complete the contract, including legal fees.

With respect to the Rocky Hill job, this court found that the amount owed to the named defendant exceeded the back charges claimed by it and that there was no offsetting balance. With respect to the Bloomfield job, the court also found that while the named defendant justifiably terminated the contract between the parties, the plaintiff was owed more than the amount of the named defendant’s counterclaim.

Our Supreme Court noted in Danbury v. Dana Investment Corp., 249 Conn. 1, 730 A.2d 1128 (1999): “It is elementary that, whether fees and costs are a matter of right or discretion, they ordinarily are awarded to the party that prevails in the case and until there is a prevailing party, they do not arise.” Id., 18; see also Alexander v. K&S Development Co., Superior Court, judicial district of New Haven, Docket No. 306092 (September 21, 1992) (7 C.S.C.R. 139) (Hodgson, J.). Our *408 Supreme Court held in Moran v. Lewis, 131 Conn. 680, 41 A.2d 905 (1945), that when a plaintiff prevailed on his complaint and the defendant prevailed on a counterclaim involving a separate transaction, and judgment was entered subsequently for the plaintiff on the complaint and for the defendant on the counterclaim, the court allowed the defendant costs as a prevailing party. When the plaintiff sued for the amount due under an agreement and the defendant counterclaimed against that same agreement for an amount due under it, however, and when the court subsequently offset the defendant’s counterclaim against the plaintiffs claim and rendered judgment in favor of the plaintiff on all the issues, the court held that “the defendant did not prevail upon the counterclaim and was not entitled to costs upon it.” Tomasetti v. Kowalski, 116 Conn. 371, 374, 164 A. 909 (1933).

In the present case, the plaintiffs claims for the unpaid balances of the contract prices exceeded the defendant’s counterclaims for defective work and, accordingly, judgment was rendered in favor of the plaintiff. Under such circumstances the named defendant is not a prevailing party and is not entitled to counsel fees.

Moreover, when a defendant seeks attorney’s fees under contracts the defendant itself breached by not paying the plaintiff the sums due under the contracts, it is not entitled to attorney’s fees. “A party cannot recover on a contract unless it has fully performed his obligations under it, has tendered performance, or has some legal excuse for not performing.” Ravitch v. Stollman Poultry Farms, Inc., 165 Conn. 135, 149, 328 A.2d 711 (1973); Automobile Ins. Co. v. Model Family Laundries, Inc., 133 Conn. 433, 437, 52 A.2d 137 (1947); 17A Am. Jur. 2d 348, Contracts § 361 (2004).

*409 II

THE PLAINTIFF’S CLAIM FOR ATTORNEY’S FEES

The plaintiff claims attorney’s fees of $73,521.11 (corrected to $67,187.36) on the basis of § 52-249 (a). The present case involved an extended trial of the plaintiffs claim for the contract price on two separate jobs and the named defendant’s counterclaim for deficiencies in the plaintiffs performance of the contracts. The plaintiffs action was on a surety bond substituted for the mechanic’s lien.

The law in Connecticut is that “attorney’s fees are not allowed to the prevailing party as an element of damage unless recovery is allowed by statute or contract.” A. Secondino & Son, Inc. v. LoRicco, 19 Conn. App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Watson Real Estate, LLC v. Woodland Ridge, LLC
208 Conn. App. 115 (Connecticut Appellate Court, 2021)
Dubaldo Electric, LLC v. Montagno Construction, Inc.
988 A.2d 351 (Connecticut Appellate Court, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
889 A.2d 278, 49 Conn. Supp. 405, 2005 Conn. Super. LEXIS 1236, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-a-mason-llc-v-montagno-construction-inc-connsuperct-2005.