60 Key Centre Inc. v. Administrator of General Services Administration (Gsa) Acquest Holding, Inc.

47 F.3d 55, 40 Cont. Cas. Fed. 76,770, 1995 U.S. App. LEXIS 2194, 1995 WL 49289
CourtCourt of Appeals for the Second Circuit
DecidedFebruary 1, 1995
Docket205, Docket 94-6043
StatusPublished
Cited by6 cases

This text of 47 F.3d 55 (60 Key Centre Inc. v. Administrator of General Services Administration (Gsa) Acquest Holding, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
60 Key Centre Inc. v. Administrator of General Services Administration (Gsa) Acquest Holding, Inc., 47 F.3d 55, 40 Cont. Cas. Fed. 76,770, 1995 U.S. App. LEXIS 2194, 1995 WL 49289 (2d Cir. 1995).

Opinion

MAHONEY, Circuit Judge:

Plaintiff-appellant 60 Key Centre Inc. (“60 Key”) appeals from a judgment entered February 3, 1994 in the United States District Court for the Western District of New York, Michael B. Mukasey, Judge, 1 that denied 60 Key’s application for: (1) an injunction barring defendant-appellee Administrator of the General Services Administration (the “GSA”) from proceeding with performance of an award of a lease for space (to be occupied by the offices of the United States Attorney for the Western District of New York) to defendant-appellee Acquest Holding, Inc. (“Ac-quést”); and (2) for a declaratory judgment directing the GSA to award the lease to 60 Key. See 60 Key Centre Inc. v. Administrator of General Servs. Admin., No. 93 Civ. 0154A (MBM), 1994 WL 25842 (W.D.N.Y. Jan. 25, 1994) (opinion supporting judgment).

We affirm the judgment of the district court.

Background

Until December 1993, the offices of the United States Attorney for the Western District of New York (the “U.S. Attorney”) were located in the United States Courthouse at 68 Court Street, Buffalo, New York. In 1990, an extensive renovation and expansion project for the Courthouse was commenced, requiring that the U.S. Attorney vacate the premises by December 15, 1993. Consequently, the U.S. Attorney was required to find and lease new office space. The GSA, through its realty specialist Paul O’Brien, solicited bids.

O’Brien prepared a solicitation for offers (“SFO”) that provided the specifications and other relevant information for a ten-year lease with two five-year renewal options (the “Lease”), and specified a deadline of February 26, 1992 for initial bids. The SFO required that bids remain open until August 3, 1992, but did not provide a deadline date for Best and Final Offers (“BAFOs”). 60 Key submitted its initial bid on February 25, 1992, but Acquest did not submit its initial bid until August 10, 1992, more than five months after the deadline for initial bids.

After receiving Acquest’s bid, the GSA set the BAFO deadline as November 18, 1992; both 60 Key and Acquest submitted their BAFOs before the deadline. The GSA considered Acquest’s bid even though it was submitted after the deadline for initial bids stated in the SFO, because General Services *57 Administration Regulation (“GSAR”) § 552.270~3(a), 48 C.F.R. § 552.270-3(a), bars (with certain exceptions) the consideration only of offers received after the BAFO deadline. 60 Key, Acquest, and an entity called Court Tower were selected as the finalists in the bid competition.

The GSA relied on the five “Award Factor Criteria” listed in the SFO (security, quality, location, space layout, and delivery), as well as price, to assess the competing bids. 60 Key scored seventeen (out of 100) points lower than Acquest, and nineteen points lower than Court Tower, on the qualitative criteria. In addition, 60 Key’s overall price for the initial and renewal terms of the leasehold was higher than the price in either Acquest’s or Court Tower’s bid.

On January 22, 1993, GSA awarded the Lease to Acquest. On January 29, 1993, 60 Key filed a bid protest with the General Accounting Office (the “GAO”) pursuant to the procurement protest system established by 31 U.S.C. §§ 3551-3556, but the GSA determined, pursuant to 31 U.S.C. § 3553(d)(2), that Acquest should be permitted to continue its performance. 2 On February 23, 1993, 60 Key commenced the instant action, alleging that the award of the lease violated applicable federal laws and regulations and the SFO, and seeking (1) temporary and permanent injunctive relief prohibiting the GSA and Acquest from proceeding with the award of the Lease, and (2) a declaratory judgment directing the GSA to award the Lease to 60 Key. 3

60 Key waited until June 3, 1993, however, to move for a preliminary injunction, and did not file a supporting memorandum until October 15, 1993. 60 Key Centre, 1994 WL 25842 at *2. At 60 Key’s suggestion, made during the oral argument of that motion on December 22, 1993, the district court combined the hearing of that motion with the trial on the merits. Id. The parties thereafter stipulated to the documents and deposition testimony which, together with the transcript of the December 22 hearing, constitute the record in this case. Id. By December 22,1993, Acquest had completed construction of the project, and the GSA had preliminarily accepted the office space. By the time the district court’s opinion was issued on January 25, 1994, the U.S. Attorney had moved into the new premises.

The district court’s comprehensive and thoughtful opinion considered and rejected 60 Key’s claims that the GSA had violated federal law, federal regulations, and the SFO in awarding the Lease to Acquest, see id. at *3-10, and we affirm substantially for the reasons stated in the opinion of the district court. We address only 60 Key’s challenge to the timeliness of Acquest’s bid.

The district court rejected that challenge, stating:

Plaintiff contends also that the Acquest bid was late and should never have been considered. Initial offers were due February 26, 1992. Acquest’s initial offer was not received until mid-August 1992. However, GSA regulations governing evaluation of BAFO’s and the award of contracts *58 are interpreted by GSA to permit evaluation of offers received after the deadline for initial offers, provided that BAFO’s are timely.... In particular, 48 CFR § 552.270-3(a) contains th[e] following introductory language: “Any offer received at the office designated in the solicitation after the exact time specified for receipt of best and final offers will not be considered unless....” The regulation then goes on to specify the requirement for a postmark consistent with the timely mailing, and the like. However, the regulation makes it plain that the critical date is the deadline for BAFO’s. Nor is this surprising. The point of the bidding process, after all, is to assure that the government can get the best deal. It would be pointless to shut out a potentially successful bidder at the beginning of the process when discussions are ongoing and the time for BAFO’s has not yet passed. Here, the deadline for BAFO’s was November 18, 1992. Plaintiff does not dispute GSA’s claim that Ac-quest’s BAFO was received on November 17, 1992. Thus, 60 Key’s objection to the timing of Acquest’s bid is without merit.

1994 WL 25842 at *5 (alterations partially added).

This appeal followed. During the pen-dency of this appeal, 60 Key called to our attention the decision, rendered after the district court’s decision in this case, of the United States Court of Federal Claims in Aerolease Long Beach v. United States, 31 Fed.Cl.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
47 F.3d 55, 40 Cont. Cas. Fed. 76,770, 1995 U.S. App. LEXIS 2194, 1995 WL 49289, Counsel Stack Legal Research, https://law.counselstack.com/opinion/60-key-centre-inc-v-administrator-of-general-services-administration-ca2-1995.