4922 Holdings, LLC and Horizon United Group International, LLC v. Salvador Rivera D/B/A Rivera's Commercial

Court of Appeals of Texas·Decided May 4, 2021·No. 14-19-00922-CV·Published

Opinion

Affirmed and Opinion filed May 4, 2021.

In The

Fourteenth Court of Appeals

NO. 14-19-00922-CV

4922 HOLDINGS, LLC AND HORIZON UNITED GROUP INTERNATIONAL, LLC, Appellants/Cross-Appellees

V.

SALVADOR RIVERA D/B/A RIVERA’S COMMERCIAL, Appellee/Cross-Appellant

On Appeal from the 189th District Court Harris County, Texas

Trial Court Cause No. 2017-30658

OPINION

This appeal arises from a contract dispute between a subcontractor and an owner/general contractor following a construction renovation project. A jury found that both parties materially breached the contract, but that the owner/general contractor breached first and that its breach was not excused. The trial court signed a judgment awarding the subcontractor $3,875 in breach-of-contract damages found

by the jury, $52,300 in attorney’s fees (plus conditional appellate attorney’s fees), and pre- and post-judgment interest.

Both parties appeal. In three issues, the owner/general contractor asserts that no legally or factually sufficient evidence supports: (1) the jury’s damages finding in the subcontractor’s favor; (2) the jury’s finding that the owner/general contractor breached the contract first; and (3) the trial court’s award of attorney’s fees to the subcontractor.

The subcontractor presents two cross-issues. First, the subcontractor contends the trial court erred in awarding only $3,875 in contract damages when the jury found a larger amount—$17,775—represented the value of its unpaid labor in response to a separate lien-foreclosurequestion. Second, the subcontractor urges that the trial court should have awarded pre-judgment interest at 18%, instead of 5.5%, because the jury found that the owner/subcontractor failed to promptly pay for the work performed.

We conclude that legally and factually sufficient evidence supports the verdict and the judgment, and we overrule the owner/general contractor’s three issues. We overrule the subcontractor’s issues because it failed to preserve them in the trial court. Accordingly, we affirm the trial court’s judgment.

Background

Appellants Horizon United Group International, LLC and 4922 Holdings, LLC (collectively, “Horizon”)1 hired Salvador Rivera d/b/a Rivera Commercial (“Rivera”) to perform “structural repairs and upgrades” to church property located in Houston. In November 2014, Horizon and Rivera signed a subcontract agreement

1 The parties do not distinguish between Horizon and 4922 Holdings, so we refer to them collectively as “Horizon.”

(the “Contract”) with a price of $121,000. Generally, the original scope of work included demolition, framing, truss repairs, ceiling repairs, interior drywall repairs and painting, and exterior painting. Two written and signed change orders or addenda altered the Contract terms. Together, these orders changed the Contract price to a maximum of $139,000.2

Horizon was to pay Rivera periodically in an amount equal to the value of the work performed and approved by Horizon, less a retainage equal to ten percent of the amount Rivera requested.

Based on Horizon’s alleged failure to pay all Contract amounts due, Rivera sued Horizon for breach of contract, quantum meruit, prompt payment violations, and lien foreclosure. Horizon countersued Rivera for fraudulent lien and breach of contract based on Rivera’s allegedly shoddy workmanship and failure to complete the Contract’s work scope.

A two-day jury trial included testimony from Rivera’s owner, Salvador Rivera, and his son, Brian, who worked on the project and handled paperwork and communications with Horizon. The parties agree that work proceeded and Horizon paid Rivera for its work up to approximately January or February 2016, when Horizon told Rivera to stop work. According to Salvador and Brian, the entire scope of work—including the first and second change orders—had been completed as of February 2016, and the only task remaining was exterior painting, which was just beginning when they were told to stop. Brian explained that Horizon halted the job because a lack of waterproofing on the exterior concrete block walls led to interior leakage problems.

2 The $139,000 price included a potential $5,000 bonus if Rivera completed the second change order’s scope timely. The parties disputed whether Rivera completed the second change order.

According to Brian, Horizon asked Rivera to waterproof the exterior concrete masonry, a task the parties refer to as applying “block filler.” Brian and Salvador testified that block filler was not part of the original work scope, so Rivera provided an additional proposal for it. The court admitted a document labeled “Additional #3,” which provided for Rivera to “apply waterproofing all around exterior wall” in exchange for an additional $7,750. This document was not signed by either Rivera or Horizon, but Salvador said that Horizon’s superintendent verbally approved the block-filler work over the phone. Horizon’s position was that block filler is much like paint primer and was included within the original work scope as part of the exterior painting. In any event, it is undisputed that Rivera completed the block- filler work and invoiced Horizon for $7,750 (less retainage of $750) on April 21, 2016. Horizon did not pay Rivera for the block-filler work. After Brian and Salvador completed the block filler, they did not resume or complete the exterior painting because they had been told to stop.

The parties agree that Horizon paid Rivera a total of $118,100 for work performed up to February 2016. The parties also agree that Horizon withheld $13,900 as retainage. Rivera claims it is owed $13,900 for the retainage and $7,750 for the block-filler work. Brian filed a lien against the property for $21,650, reflective of these two amounts.

Horizon believed that Rivera failed to complete the work scope and inadequately performed certain tasks. On cross-examination, Brian acknowledged that Rivera had not met some contractual obligations, such as providing daily written reports, obtaining inspections (although Brian stated, “Horizon has always done the inspections for us”), securing permits for some items (such as an interior stage that Rivera built as part of the second change order), and building steps leading to the stage front as contemplated by the second change order’s work scope. Brian testified

that Horizon never informed Rivera that its work was incomplete or that any part of the work was deficient and needed repair.

Another task Horizon asserted Rivera either failed to perform or performed deficiently was exterior painting, which was included in the original work scope. Brian and Salvador acknowledged that no deductive change order removed the exterior painting from the work scope. However, Horizon told Rivera to stop work as the exterior painting began, and Rivera’s February 2016 invoice noted that exterior painting remained to be performed. As the invoice indicates, the exterior painting would cost $7,000 but Rivera was not requesting payment for that work. The February 2016 invoice was in writing and signed by Horizon’s project manager, David Pratt, who approved it subject to a later adjustment.

Brian also acknowledged that Rivera did not have a signed change order regarding the block-filler work, but he testified that Horizon approved the work over the phone. Brian said that change orders did not need to be in any specific form.

Free access — add to your briefcase to read the full text and ask questions with AI

4922 Holdings, LLC and Horizon United Group International, LLC v. Salvador Rivera D/B/A Rivera's Commercial, (Tex. Ct. App. 2021).

4922 Holdings, LLC and Horizon United Group International, LLC v. Salvador Rivera D/B/A Rivera's Commercial (4922 Holdings, LLC and Horizon United Group International, LLC v. Salvador Rivera D/B/A Rivera's Commercial) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Volkswagen of America, Inc. v. Ramirez
159 S.W.3d 897 (Texas Supreme Court, 2004)
Columbia Medical Center of Las Colinas, Inc. v. Hogue
271 S.W.3d 238 (Texas Supreme Court, 2008)
Bayer Corp. v. DX Terminals, Ltd.
214 S.W.3d 586 (Court of Appeals of Texas, 2007)
Dow Chemical Co. v. Francis
46 S.W.3d 237 (Texas Supreme Court, 2001)
Maritime Overseas Corp. v. Ellis
971 S.W.2d 402 (Texas Supreme Court, 1998)
Star Enterprise v. Marze
61 S.W.3d 449 (Court of Appeals of Texas, 2001)
GTE Mobilnet of South Texas Ltd. Partnership v. Pascouet
61 S.W.3d 599 (Court of Appeals of Texas, 2001)
In Re Blakeney
254 S.W.3d 659 (Court of Appeals of Texas, 2008)
Dobbins v. Redden
785 S.W.2d 377 (Texas Supreme Court, 1990)
Randy v. Squires Construction, Inc.
188 S.W.3d 396 (Court of Appeals of Texas, 2006)
San Antonio Credit Union v. O'CONNOR
115 S.W.3d 82 (Court of Appeals of Texas, 2003)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
McGalliard v. Kuhlmann
722 S.W.2d 694 (Texas Supreme Court, 1986)
Arthur Andersen & Co. v. Perry Equipment Corp.
945 S.W.2d 812 (Texas Supreme Court, 1997)
Vance v. My Apartment Steak House of San Antonio, Inc.
677 S.W.2d 480 (Texas Supreme Court, 1984)
Bartush-Schnitzius Foods Co. v. Cimco Refrigeration, Inc.
518 S.W.3d 432 (Texas Supreme Court, 2017)
TecLogistics, Inc. and Josephine Treurnie v. Dresser-Rand Group, Inc.
527 S.W.3d 589 (Court of Appeals of Texas, 2017)