1995-2 Trade Cases P 76,817, 40 cont.cas.fed. (Cch) P 76,817 Frank D. Minelli, D/B/A Swiss Craft Professional Painters v. United States

61 F.3d 920, 1995 WL 424858
CourtCourt of Appeals for the Federal Circuit
DecidedJuly 18, 1995
Docket95-5018
StatusUnpublished

This text of 61 F.3d 920 (1995-2 Trade Cases P 76,817, 40 cont.cas.fed. (Cch) P 76,817 Frank D. Minelli, D/B/A Swiss Craft Professional Painters v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
1995-2 Trade Cases P 76,817, 40 cont.cas.fed. (Cch) P 76,817 Frank D. Minelli, D/B/A Swiss Craft Professional Painters v. United States, 61 F.3d 920, 1995 WL 424858 (Fed. Cir. 1995).

Opinion

61 F.3d 920

1995-2 Trade Cases P 76,817, 40 Cont.Cas.Fed.
(CCH) P 76,817
NOTICE: Federal Circuit Local Rule 47.6(b) states that opinions and orders which are designated as not citable as precedent shall not be employed or cited as precedent. This does not preclude assertion of issues of claim preclusion, issue preclusion, judicial estoppel, law of the case or the like based on a decision of the Court rendered in a nonprecedential opinion or order.
Frank D. MINELLI, d/b/a Swiss Craft Professional Painters,
Plaintiff-Appellant,
v.
The UNITED STATES, Defendant-Appellee.

No. 95-5018.

United States Court of Appeals, Federal Circuit.

July 18, 1995.

Before RICH, LOURIE, and BRYSON, Circuit Judges.

DECISION

BRYSON, Circuit Judge.

Frank D. Minelli, sole proprietor of Swiss Craft Professional Painters, appeals the order of the United States Court of Federal Claims, Docket Nos. 90-228C and 90-4047C, in which the court held, on summary judgment, that the government acted lawfully when it terminated its contract with Swiss Craft for default. We affirm.

BACKGROUND

On February 19, 1988, the Army Corps of Engineers awarded a contract to Swiss Craft to sandblast and paint 30 reservoir control gates on the W.D. Mayo and Robert S. Kerr Dams in Oklahoma. Swiss Craft received the Corps' notice to proceed with the work on June 13, 1988, but because Swiss Craft was occupied with other projects, it did not begin work until March 23, 1989. Under the terms of the contract, Swiss Craft was required to complete the work at the Mayo Dam by October 15, 1989, and at the Kerr Dam by July 22, 1990.

Even after Swiss Craft began working on the project, its progress was halting at best. From the outset, the Corps warned Swiss Craft about a number of safety violations and directed that the violations be corrected. Swiss Craft failed to remedy the deficiencies, and on April 24, 1989, the contracting officer's representative ordered Swiss Craft to stop work because of the violations.

On May 11, 1989, Swiss Craft sent the Corps a letter advising that it had corrected the safety violations, and the next day the Corps advised Swiss Craft that it could resume working. During safety inspections in late May and early June, however, the Corps' district safety engineer discovered additional safety violations, which he characterized as "eminently dangerous." On June 9, 1989, the Corps therefore again ordered Swiss Craft to stop work because of safety violations. By June 29, 1989, Swiss Craft had corrected most of those violations, and on July 7, the Corps lifted the work stoppage on the condition that Swiss Craft correct the remaining minor violations.

Between March 23 and the end of June, 1989, Swiss Craft had painted two of the Mayo Dam gates. When Swiss Craft presented those gates to the Corps for acceptance, however, the Corps rejected them for failing to conform to the contract's specifications. The Corps directed Swiss Craft to redo all the work on those two gates, including re-sandblasting the steel surfaces. By the end of June 1989, then, Swiss Craft had effectively completed none of the work under the contract satisfactorily, it had suffered several lengthy work stoppages because of continuing and serious safety violations, and only three and one-half months (out of the 16-month period available under the contract) remained within which to do all the work on the Mayo Dam.

On June 30, 1989, the contracting officer sent Swiss Craft a cure notice stating that Swiss Craft would be terminated for default unless it provided within ten days "a comprehensive responsive written plan evidencing your commitment and program for completing the work in accordance with the contract specifications." In its response, Swiss Craft proposed to use a subcontractor to complete the bulk of the work on the 12 Mayo Dam gates. By using a subcontractor, Swiss Craft estimated that it could complete the bulk of the work on the Mayo Dam by October 14, 1989, assuming that there were no further safety-related work stoppages and that there would be no need to redo any of the work. Swiss Craft proposed that the work on the service bridges and gate hoist machinery would be completed in the winter of 1990, after the period specified in the contract.

In a second submission, dated July 11, 1989, Swiss Craft informed the Corps that unless the contracting officer waived the contract provision prohibiting painting whenever the temperature of the painting surface exceeded 95 degrees, Swiss Craft would be "forced to shut this job down for the remainder of July and August." In a July 13, 1989, meeting with the Corps, Swiss Craft reiterated its request that the contract requirements be relaxed in various ways, including allowing painting to proceed as long as the painting surface did not exceed 125 degrees, allowing the painting of service bridges in January and February 1990, modifying the specification regarding the time lapse between the primer and second coats of paint, accepting one of the previously rejected gates, and agreeing to permit a subcontractor to complete the work on the project. In a letter dated July 15, 1989, Swiss Craft advised the contracting officer that the proposed subcontractor had taken the position that it would not be able to take over the job if the temperature limitations in the contract were not modified.

On July 18, 1989, the contracting officer terminated the contract for default. The contracting officer explained that the conditions Swiss Craft had set forth in response to the June 30 cure notice concerning the relaxation and modification of various contract specifications were unacceptable. Minelli then filed this action in the Court of Federal Claims, contending that the contracting officer had abused his discretion by terminating the contract for default. The Court of Federal Claims granted the government's motion for summary judgment and dismissed Minelli's complaint.

DISCUSSION

A contracting officer may terminate a contract for default if there is "no reasonable likelihood that the [contractor] could perform the entire contract effort within the time remaining for contract performance." Lisbon Contractors, Inc. v. United States, 828 F.2d 759, 765 (Fed.Cir.1987); see also Discount Co. v. United States, 554 F.2d 435, 441 (Ct.Cl.), cert. denied, 434 U.S. 938 (1977). Minelli argues that because Swiss Craft was willing and able to fulfill its obligations under the contract, the contracting officer should not have terminated the contract for default. In particular, Minelli points to the schedule that Swiss Craft included with its July 10 letter, in which Swiss Craft promised to complete work on the Mayo Dam gates by October 14, 1989; Minelli contends that the contracting officer had no reason to doubt that Swiss Craft would adhere to that schedule.

The Court of Federal Claims rejected Minelli's argument in a thorough opinion on which we rely. The court reviewed the late start-up, the delays resulting from Swiss Craft's numerous safety violations, and the poor quality of the work done by Swiss Craft as of the end of June 1989.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Darwin Construction Co., Inc. v. United States
811 F.2d 593 (Federal Circuit, 1987)
Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)
Discount Co. v. United States
554 F.2d 435 (Court of Claims, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
61 F.3d 920, 1995 WL 424858, Counsel Stack Legal Research, https://law.counselstack.com/opinion/1995-2-trade-cases-p-76817-40-contcasfed-cch-p-76817-frank-d-cafc-1995.