1902 Atlantic Ltd. v. United States

26 Cl. Ct. 575, 23 Envtl. L. Rep. (Envtl. Law Inst.) 21202, 35 ERC (BNA) 1706, 1992 U.S. Claims LEXIS 254, 1992 WL 138078
CourtUnited States Court of Claims
DecidedJune 19, 1992
DocketNo. 637-87L
StatusPublished
Cited by15 cases

This text of 26 Cl. Ct. 575 (1902 Atlantic Ltd. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
1902 Atlantic Ltd. v. United States, 26 Cl. Ct. 575, 23 Envtl. L. Rep. (Envtl. Law Inst.) 21202, 35 ERC (BNA) 1706, 1992 U.S. Claims LEXIS 254, 1992 WL 138078 (cc 1992).

Opinion

OPINION

ROBINSON, Judge.

In this Fifth Amendment temporary taking case, plaintiff seeks damages allegedly arising from defendant’s denial of a Section 404 permit under the Clean Water Act to discharge dredged or fill material on plaintiff’s land. Trial was held in June, 1991. Oral and documentary evidence were admitted at the trial, and post-trial briefs were filed. After careful consideration of the entire record, the court finds that defendant's actions do not constitute a temporary taking. The reasons for this decision are set forth below.

Factual Background

On April 7, 1981, plaintiff, 1902 Atlantic Limited (“Atlantic”), purchased an 11 acre borrow pit in Chesapeake, Virginia for $25,-000. Atlantic bought the property intending to fill it with construction debris resulting from neighboring demolition projects. Once filled, plaintiff expected that the land could be used for commercial or industrial development. The borrow pit resulted from the excavation of highlands for the construction of a highway overpass.1 The pit was connected by a ditch to Mill Dam Creek, a tributary of the southern branch of the Elizabeth River. As a result, the borrow pit was subject to inundation from the creek’s tidal flow and, therefore, contained wetlands within its boundaries. The United States Army Corps of Engineers (“Corps”) asserted jurisdiction over those wetlands pursuant to Section 10 of the Rivers and Harbors Act, 33 U.S.C. § 403, and Section 404 of the Clean Water Act, 33 U.S.C. § 1344.

On April 22, 1981, plaintiff applied to the Corps for a Section 404 permit to fill the entire borrow pit area. At that time, Atlantic had obtained all of the necessary local and state permits and had substantially complied with all other restrictions on its proposed land development. On June 8, 1981, the Corps issued a preliminary assessment of plaintiff’s permit request. The Corps recommended that the application be denied as the proposed project was not water dependent. The “water dependency” rule essentially' requires that any proposed filling of wetlands be for a project which is dependent upon water, such as a marina. See 33 C.F.R. § 320.-4(b)(4) and 40 C.F.R. § 230.10(a)(3). On July 10,1981, the Corps advised plaintiff of its objections. Atlantic immediately submitted additional support for an amended application.which proposed the digging of a [577]*577ditch around a portion of the perimeter of the borrow pit and reducing the 32,000 square feet of effected wetlands to approximately 15,000 square feet.

On October 26, 1981, the Corps advised plaintiff of its preliminary decision to deny the permit, notwithstanding the proposed mitigation. Atlantic again tried to satisfy the Corps’ objections but was unsuccessful. On July 27, 1982, plaintiff filed suit in the United States District Court for the Eastern District of Virginia, Norfolk Division (“District Court”), seeking equitable relief, a declaration that defendant had taken the land, and a declaration that the Corps’ actions were arbitrary, capricious and an abuse of discretion in violation of the Administrative Procedure Act, 5 U.S.C. § 701 et seq. Two days later, on July 29, 1982, Colonel Ronald E. Hudson, Corps District Engineer, denied plaintiff’s permit application. This denial was premised upon the Corps’ conclusion that plaintiff’s proposed project violated both the Corps’ Wetland Policy and the Environmental Protection Agency’s (“EPA”) guidelines. See 40 C.F.R. Part 230.

On September 28, 1983, following a trial on the merits, the District Court issued an opinion finding that the Corps had unlawfully taken Atlantic’s property. The District Court remanded the matter to the District Engineer for reconsideration of plaintiff’s permit application “in accordance with the views expressed in said opinion, or in the alternative, that the District Engineer commence condemnation proceedings if funds were available for this purpose.”2

On June 23, 1984, the Corps issued a preliminary environmental assessment concerning its reconsideration of plaintiff’s application. On June 28, 1984, the Corps advised Atlantic that it intended to once again deny the permit application. The Corps, acting through Col. Hudson, formally denied the application on July 11, 1984. Almost immediately after issuing the denial, Col. Hudson retired and was replaced by Col. Claude O. Boyd, III.

Plaintiff promptly filed a motion in the District Court to compel the Corps’ compliance with the court’s previous order. On January 29, 1985, the District Court ordered compliance within 21 days. This order was followed by a written opinion on February 8, 1985. On April 3, 1985, the Corps issued a Section 404 permit to plaintiff, authorizing Atlantic’s amended proposal. By that time, however, several of the state and local permits for the project had expired. Thus, plaintiff’s fill operations were delayed until June 3, 1986. Unfortunately, due to flooding, the preparatory work on the site did not begin until the fall of 1987. By April, 1991, approximately 30-40 percent of the approved area had been filled, but no construction had begun.

Contentions of the Parties

Plaintiff contends that the Corps’ actions constituted a temporary taking from October 26, 1981, when the Corps issued its preliminary denial of Atlantic’s permit application, until June 3,1986, when all of the necessary state and local permits had been reissued. Atlantic asserts that it has satisfied the three pronged test upon which the courts have consistently relied in determining whether governmental regulation has resulted in an unconstitutional taking. See Connolly v. Pension Ben. Guar. Corp., 475 U.S. 211, 224, 106 S.Ct. 1018, 1025-26, 89 L.Ed.2d 166 (1986). That is, plaintiff argues that the Corps’ denial of its permit application had a severe economic impact, that it substantially interfered with Atlantic’s investment-backed expectations, and that the character of the Government’s actions smacked of bad faith and abuse of discretion.

Plaintiff alternatively argues that the Corps’ regulation in this case did not substantially advance a legitimate governmen[578]*578tal interest. In this regard, Atlantic relies upon the evidence it submitted at trial which plaintiff believes showed defendant’s improper motivation, unfair conduct and unreasonable protraction of the proceedings attributable to the Government’s intractable pattern of denials. Atlantic contends that the Corps’ actions in this case have exhibited such an egregious disregard of the regulatory process as to rise to the level of “irrefragable proof” of defendant’s bad faith sufficient to provide this court with an additional basis for finding a taking. Knotts v. United States, 128 Ct.Cl. 489, 492, 121 F.Supp. 630, 631 (1954).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State ex rel. AWMS Water Solutions, L.L.C. v. Mertz
2024 Ohio 4451 (Ohio Court of Appeals, 2024)
Resource Investments, Inc. v. United States
85 Fed. Cl. 447 (Federal Claims, 2009)
Brace v. United States
72 Fed. Cl. 337 (Federal Claims, 2006)
Arctic King Fisheries, Inc. v. United States
59 Fed. Cl. 360 (Federal Claims, 2004)
Walcek v. United States
49 Fed. Cl. 248 (Federal Claims, 2001)
Landgate, Inc. v. California Coastal Commission
953 P.2d 1188 (California Supreme Court, 1998)
Bass Enterprises Production Company v. United States
133 F.3d 893 (Federal Circuit, 1998)
Bass Enterprises Production Co. v. United States
133 F.3d 893 (Federal Circuit, 1998)
Norman v. United States
38 Fed. Cl. 417 (Federal Claims, 1997)
East Cape May Associates v. State
693 A.2d 114 (New Jersey Superior Court App Division, 1997)
Bass Enterprises Production Co. v. United States
35 Fed. Cl. 615 (Federal Claims, 1996)
Anaheim Gardens v. United States
33 Fed. Cl. 24 (Federal Claims, 1995)
Cannone v. Noey
867 P.2d 797 (Alaska Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
26 Cl. Ct. 575, 23 Envtl. L. Rep. (Envtl. Law Inst.) 21202, 35 ERC (BNA) 1706, 1992 U.S. Claims LEXIS 254, 1992 WL 138078, Counsel Stack Legal Research, https://law.counselstack.com/opinion/1902-atlantic-ltd-v-united-states-cc-1992.