§ 252.217-7007 — Payments.

eCFR · current through Aug 7, 2026

252.217-7007 Payments. As prescribed in 217.7104(a), use the following clause: Payments (DEC 1991)

(a)Progress payments, as used in this clause, means payments made before completion of work in progress under a job order.
(b)Upon submission by the Contractor of invoices in the form and number of copies directed by the Contracting Officer, and as approved by the Contracting Officer, the Government will make progress payments as work progresses under the job order.
(1)Generally, the Contractor may submit invoices on a semi-monthly basis, unless expenditures justify a more frequent submission.
(2)The Government need not make progress payments for invoices aggregating less than $5,000.
(3)The Contracting Officer shall approve progress payments based on the value, computed on the pri

Free access — add to your briefcase to read the full text and ask questions with AI

48 C.F.R. § 252.217-7007 (Payments.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Nearby Sections

11
§ 252.217-7003
Changes.
§ 252.217-7006
Title.
§ 252.217-7007
Payments.
§ 252.217-7008
Bonds.
§ 252.217-7009
Default.
§ 252.217-7010
Performance.
§ 252.217-7011
Access to vessel.
View on eCFR ↗