§ 252.217-7003 — Changes.
eCFR · current through Aug 7, 2026
252.217-7003 Changes. As prescribed in 217.7104(a), use the following clause: Changes (DEC 1991)
(a)The Contracting Officer may, at any time and without notice to the sureties, by written change order, make changes within the general scope of any job order issued under the Master Agreement in—
(1)Drawings, designs, plans, and specifications;
(2)Work itemized;
(3)Place of performance of the work;
(4)Time of commencement or completion of the work; and
(5)Any other requirement of the job order.
(b)If a change causes an increase or decrease in the cost of, or time required for, performance of the job order, whether or not changed by the order, the Contracting Officer shall make an equitable adjustment in the price or date of completion, or both, and shall modify the job order in
Free access — add to your briefcase to read the full text and ask questions with AI
48 C.F.R. § 252.217-7003 (Changes.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Nearby Sections
11
§ 252.217-7001
Surge option.§ 252.217-7002
Offering property for exchange.§ 252.217-7003
Changes.§ 252.217-7004
Job orders and compensation.§ 252.217-7005
Inspection and manner of doing work.§ 252.217-7006
Title.§ 252.217-7007
Payments.§ 252.217-7008
Bonds.