FEDERAL · 42 U.S.C. · Chapter SUBCHAPTER I—PROGRAMS AND ACTIVITIES
Nonattainment plan provisions in general
42 U.S.C. § 7502
Title42 — The Public Health and Welfare
ChapterSUBCHAPTER I—PROGRAMS AND ACTIVITIES
Partsubpart 1—nonattainment areas in general
This text of 42 U.S.C. § 7502 (Nonattainment plan provisions in general) is published on Counsel Stack Legal Research, covering United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
42 U.S.C. § 7502.
Text
(a)Classifications and attainment dates
(A)On or after the date the Administrator promulgates the designation of an area as a nonattainment area pursuant to section 7407(d) of this title with respect to any national ambient air quality standard (or any revised standard, including a revision of any standard in effect on November 15, 1990), the Administrator may classify the area for the purpose of applying an attainment date pursuant to paragraph (2), and for other purposes. In determining the appropriate classification, if any, for a nonattainment area, the Administrator may consider such factors as the severity of nonattainment in such area and the availability and feasibility of the pollution control measures that the Administrator believes may be necessary to provide for attainment of
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Whitman v. American Trucking Assns., Inc.
531 U.S. 457 (Supreme Court, 2001)
Loper Bright Enterprises v. Raimondo
603 U.S. 369 (Supreme Court, 2024)
Negusie v. Holder
555 U.S. 511 (Supreme Court, 2009)
New York v. U.S. Environmental Protection Agency
413 F.3d 3 (D.C. Circuit, 2005)
General Motors Corp. v. United States
496 U.S. 530 (Supreme Court, 1990)
Mississippi Hospital Ass'n v. Heckler
701 F.2d 511 (Fifth Circuit, 1983)
Wilder v. Thomas
854 F.2d 605 (Second Circuit, 1988)
Mississippi Commission on Environmental Quality v. Environmental Protection Agency
790 F.3d 138 (D.C. Circuit, 2015)
Ohio v. United States Department of Interior
880 F.2d 432 (D.C. Circuit, 1989)
Louisiana Environmental Action Network v. United States Environmental Protection Agency
382 F.3d 575 (Fifth Circuit, 2004)
Trustees for Alaska v. Fink
17 F.3d 1209 (Ninth Circuit, 1994)
Natural Resources Defense Council, Inc. v. Thomas
838 F.2d 1224 (D.C. Circuit, 1988)
Bethlehem Steel Corp. v. United States Environmental Protection Agency
723 F.2d 1303 (Seventh Circuit, 1983)
American Mining Congress v. United States Environmental Protection Agency
824 F.2d 1177 (D.C. Circuit, 1987)
Association of Irritated Residents v. United States Environmental Protection Agency
686 F.3d 668 (Ninth Circuit, 2011)
Delaware Valley Citizens' Council for Clean Air v. Pennsylvania
678 F.2d 470 (Third Circuit, 1982)
Sierra Club v. Administrator, U.S. E.P.A.
496 F.3d 1182 (Eleventh Circuit, 2007)
Environmental Defense v. United States Environmental Protection Agency
369 F.3d 193 (Second Circuit, 2004)
United States Steel Corp. v. Environmental Protection Agency
633 F.2d 671 (Third Circuit, 1980)
Source Credit
History
(July 14, 1955, ch. 360, title I, §172, as added Pub. L. 95–95, title I, §129(b), Aug. 7, 1977, 91 Stat. 746; amended Pub. L. 95–190, §14(a)(55), (56), Nov. 16, 1977, 91 Stat. 1402; Pub. L. 101–549, title I, §102(b), Nov. 15, 1990, 104 Stat. 2412.)
Editorial Notes
Editorial Notes
Amendments
1990—Pub. L. 101–549 amended section generally, substituting present provisions for provisions which related to: in subsec. (a), expeditious attainment of national ambient air quality standards; in subsec. (b), requisite provisions of plan; and in subsec. (c), attainment of applicable standard not later than July 1, 1987.
1977—Subsec. (b)(4). Pub. L. 95–190, §14(a)(55), substituted "subsection (a)" for "paragraph (1)".
Subsec. (c). Pub. L. 95–190, §14(a)(56), substituted "December 31" for "July 1".
Statutory Notes and Related Subsidiaries
Nonattainment Areas
Pub. L. 95–95, title I, §129(a), Aug. 7, 1977, 91 Stat. 745, as amended by Pub. L. 95–190, §14(b)(2), (3), Nov. 16, 1977, 91 Stat. 1404, provided that:
"(1) Before July 1, 1979, the interpretative regulation of the Administrator of the Environmental Protection Agency published in 41 Federal Register 55524–30, December 21, 1976, as may be modified by rule of the Administrator, shall apply except that the baseline to be used for determination of appropriate emission offsets under such regulation shall be the applicable implementation plan of the State in effect at the time of application for a permit by a proposed major stationary source (within the meaning of section 302 of the Clean Air Act) [section 7602 of this title].
"(2) Before July 1, 1979, the requirements of the regulation referred to in paragraph (1) shall be waived by the Administrator with respect to any pollutant if he determines that the State has—
"(A) an inventory of emissions of the applicable pollutant for each nonattainment area (as defined in section 171 of the Clean Air Act [section 7501 of this title]) that identifies the type, quantity, and source of such pollutant so as to provide information sufficient to demonstrate that the requirements of subparagraph (C) are being met;
"(B) an enforceable permit program which—
"(i) requires new or modified major stationary sources to meet emission limitations at least as stringent as required under the permit requirements referred to in paragraphs (2) and (3) of section 173 of the Clean Air Act [section 7503 of this title] (relating to lowest achievable emission rate and compliance by other sources) and which assures compliance with the annual reduction requirements of subparagraph (C); and
"(ii) requires existing sources to achieve such reduction in emissions in the area as may be obtained through the adoption, at a minimum of reasonably available control technology, and
"(C) a program which requires reductions in total allowable emissions in the area prior to July 1, 1979, so as to provide for the same level of emission reduction as would result from the application of the regulation referred to in paragraph (1).
The Administrator shall terminate such waiver if in his judgment the reduction in emissions actually being attained is less than the reduction on which the waiver was conditioned pursuant to subparagraph (C), or if the Administrator determines that the State is no longer in compliance with any requirement of this paragraph. Upon application by the State, the Administrator may reinstate a waiver terminated under the preceding sentence if he is satisfied that such State is in compliance with all requirements of this subsection.
"(3) Operating permits may be issued to those applicants who were properly granted construction permits, in accordance with the law and applicable regulations in effect at the time granted, for construction of a new or modified source in areas exceeding national primary air quality standards on or before the date of the enactment of this Act [Aug. 7, 1977] if such construction permits were granted prior to the date of the enactment of this Act and the person issued any such permit is able to demonstrate that the emissions from the source will be within the limitations set forth in such construction permit."
State Implementation Plan Revision
Pub. L. 95–95, title I, §129(c), Aug. 7, 1977, 91 Stat. 750, as amended by Pub. L. 95–190, §14(b)(4), Nov. 16, 1977, 91 Stat. 1405, provided that: "Notwithstanding the requirements of section 406(d)(2) [set out as an Effective Date of 1977 Amendment note under section 7401 of this title] (relating to date required for submission of certain implementation plan revisions), for purposes of section 110(a)(2) of the Clean Air Act [section 7410(a)(2) of this title] each State in which there is any nonattainment area (as defined in part D of title I of the Clean Air Act) [this part] shall adopt and submit an implementation plan revision which meets the requirements of section 110(a)(2)(I) [section 7410(a)(2)(I) of this title] and part D of title I of the Clean Air Act [this part] not later than January 1, 1979. In the case of any State for which a plan revision adopted and submitted before such date has made the demonstration required under section 172(a)(2) of the Clean Air Act [subsec. (a)(2) of this section] (respecting impossibility of attainment before 1983), such State shall adopt and submit to the Administrator a plan revision before July 1, 1982, which meets the requirements of section 172(b) and (c) of such Act [subsecs. (b) and (c) of this section]."
Amendments
1990—Pub. L. 101–549 amended section generally, substituting present provisions for provisions which related to: in subsec. (a), expeditious attainment of national ambient air quality standards; in subsec. (b), requisite provisions of plan; and in subsec. (c), attainment of applicable standard not later than July 1, 1987.
1977—Subsec. (b)(4). Pub. L. 95–190, §14(a)(55), substituted "subsection (a)" for "paragraph (1)".
Subsec. (c). Pub. L. 95–190, §14(a)(56), substituted "December 31" for "July 1".
Statutory Notes and Related Subsidiaries
Nonattainment Areas
Pub. L. 95–95, title I, §129(a), Aug. 7, 1977, 91 Stat. 745, as amended by Pub. L. 95–190, §14(b)(2), (3), Nov. 16, 1977, 91 Stat. 1404, provided that:
"(1) Before July 1, 1979, the interpretative regulation of the Administrator of the Environmental Protection Agency published in 41 Federal Register 55524–30, December 21, 1976, as may be modified by rule of the Administrator, shall apply except that the baseline to be used for determination of appropriate emission offsets under such regulation shall be the applicable implementation plan of the State in effect at the time of application for a permit by a proposed major stationary source (within the meaning of section 302 of the Clean Air Act) [section 7602 of this title].
"(2) Before July 1, 1979, the requirements of the regulation referred to in paragraph (1) shall be waived by the Administrator with respect to any pollutant if he determines that the State has—
"(A) an inventory of emissions of the applicable pollutant for each nonattainment area (as defined in section 171 of the Clean Air Act [section 7501 of this title]) that identifies the type, quantity, and source of such pollutant so as to provide information sufficient to demonstrate that the requirements of subparagraph (C) are being met;
"(B) an enforceable permit program which—
"(i) requires new or modified major stationary sources to meet emission limitations at least as stringent as required under the permit requirements referred to in paragraphs (2) and (3) of section 173 of the Clean Air Act [section 7503 of this title] (relating to lowest achievable emission rate and compliance by other sources) and which assures compliance with the annual reduction requirements of subparagraph (C); and
"(ii) requires existing sources to achieve such reduction in emissions in the area as may be obtained through the adoption, at a minimum of reasonably available control technology, and
"(C) a program which requires reductions in total allowable emissions in the area prior to July 1, 1979, so as to provide for the same level of emission reduction as would result from the application of the regulation referred to in paragraph (1).
The Administrator shall terminate such waiver if in his judgment the reduction in emissions actually being attained is less than the reduction on which the waiver was conditioned pursuant to subparagraph (C), or if the Administrator determines that the State is no longer in compliance with any requirement of this paragraph. Upon application by the State, the Administrator may reinstate a waiver terminated under the preceding sentence if he is satisfied that such State is in compliance with all requirements of this subsection.
"(3) Operating permits may be issued to those applicants who were properly granted construction permits, in accordance with the law and applicable regulations in effect at the time granted, for construction of a new or modified source in areas exceeding national primary air quality standards on or before the date of the enactment of this Act [Aug. 7, 1977] if such construction permits were granted prior to the date of the enactment of this Act and the person issued any such permit is able to demonstrate that the emissions from the source will be within the limitations set forth in such construction permit."
State Implementation Plan Revision
Pub. L. 95–95, title I, §129(c), Aug. 7, 1977, 91 Stat. 750, as amended by Pub. L. 95–190, §14(b)(4), Nov. 16, 1977, 91 Stat. 1405, provided that: "Notwithstanding the requirements of section 406(d)(2) [set out as an Effective Date of 1977 Amendment note under section 7401 of this title] (relating to date required for submission of certain implementation plan revisions), for purposes of section 110(a)(2) of the Clean Air Act [section 7410(a)(2) of this title] each State in which there is any nonattainment area (as defined in part D of title I of the Clean Air Act) [this part] shall adopt and submit an implementation plan revision which meets the requirements of section 110(a)(2)(I) [section 7410(a)(2)(I) of this title] and part D of title I of the Clean Air Act [this part] not later than January 1, 1979. In the case of any State for which a plan revision adopted and submitted before such date has made the demonstration required under section 172(a)(2) of the Clean Air Act [subsec. (a)(2) of this section] (respecting impossibility of attainment before 1983), such State shall adopt and submit to the Administrator a plan revision before July 1, 1982, which meets the requirements of section 172(b) and (c) of such Act [subsecs. (b) and (c) of this section]."